The GOP’s Big Permitting Reform Idea Is Mostly Dead

Zapped by the Senate parliamentarian

The Capitol and power lines.
Heatmap Illustration/Getty Images

The Republican effort at permitting reform by way of the reconciliation process appears to have failed — or at least gotten washed out in the “Byrd Bath.”

Democrats on the Senate Budget Committee announced late Thursday night that the chamber’s parliamentarian had advised that several provisions of the new reconciliation bill text violated the “Byrd Rule” and thus were subject to a 60-vote threshold instead of simple majority rule. The parliamentarian has been going over the Senate bill for the past week and her rulings on more sections of the bill are expected this weekend.

The permitting reform plan drawn by the Senate Environment and Public Works Committee essentially allowed project developers to prevent environmental reviews from being subject to litigation if they paid an upfront fee of 125% of the review’s expected cost. A similar provision was included in the House bill.

Rhode Island Democrat Sheldon White House, the ranking member on the Committee, described the permitting language as “turning the National Environmental Policy Act into a pay-to-play scheme” and “a scam ripe for Trump-style corruption.”

Clean energy groups have historically supported efforts to streamline and speed up permitting (and many environmental groups have opposed them), although typically bipartisan ones, like the legislation worked out by the Senate Energy and Natural Resources Committee in the previous Congress, that never gained support in the House of Representatives. Environmental groups have long worried that permitting reform, even bipartisan bills, would benefit the fossil fuel industry by disabling checks against massive oil, coal, and gas projects, whereas the renewable energy industry often sees as an opportunity to more quickly and cheaply advance their own projects.

Payment of the fee would also impose a one year timeline for an environmental impact statement, the most extensive type of review, and a six month timeline for an environmental assessment. The timelines were not ruled out by the parliamentarian, according to the Senate Budget Democrats.

The payment aspect of the plan was crucial to give it a shot at surviving the Byrd Rule, because it meant that the provisions decreased the deficit and thus could be argued to be primarily budgetary in nature (the same way, say, a new tax is).

While the parliamentarian or the Budget Committee didn’t disclose the justification for ruling out the judicial review provisions, Bobby Kogan, a former Budget Committee staffer who works at the liberal Center for American Progress, told me that the provision could have tripped up multiple provisions of the Byrd Rule.

“My guess is that judicial review is presumably outside the jurisdiction of EPW and it’s also probably non-budgetary. If it was budgetary, it’s probably merely incidental — it’s fundamentally about permitting,” Kogan said. “Almost certainly, the judicial thing was killed for merely incidental,” Kogan told me.

A Senate Budget spokesperson did not return a request for comment.

Republicans in the Senate could simply drop the provision or force the whole Senate to take a vote on it — but that vote would be subject to the 60-vote threshold to defeat a filibuster.

While the parliamentarian’s ruling probably means that this attempt at meaningful permitting reform is likely dead, the Trump administration and the Supreme Court have taken several whacks at the National Environmental Policy Act, with the Court recently ruling that agencies can limit themselves to the immediately environmental impact of government actions and instructing lower courts to give more deference to agencies’ reviews.

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Energy

All the Nuclear Workers Are Building Data Centers Now

There has been no new nuclear construction in the U.S. since Vogtle, but the workers are still plenty busy.

A hardhat on AI.
Heatmap Illustration/Getty Images

The Trump administration wants to have 10 new large nuclear reactors under construction by 2030 — an ambitious goal under any circumstances. It looks downright zany, though, when you consider that the workforce that should be driving steel into the ground, pouring concrete, and laying down wires for nuclear plants is instead building and linking up data centers.

This isn’t how it was supposed to be. Thousands of people, from construction laborers to pipefitters to electricians, worked on the two new reactors at the Plant Vogtle in Georgia, which were intended to be the start of a sequence of projects, erecting new Westinghouse AP1000 reactors across Georgia and South Carolina. Instead, years of delays and cost overruns resulted in two long-delayed reactors 35 miles southeast of Augusta, Georgia — and nothing else.

Keep reading...Show less
Blue
Q&A

How California Is Fighting the Battery Backlash

A conversation with Dustin Mulvaney of San Jose State University

Dustin Mulvaney.
Heatmap Illustration

This week’s conversation is a follow up with Dustin Mulvaney, a professor of environmental studies at San Jose State University. As you may recall we spoke with Mulvaney in the immediate aftermath of the Moss Landing battery fire disaster, which occurred near his university’s campus. Mulvaney told us the blaze created a true-blue PR crisis for the energy storage industry in California and predicted it would cause a wave of local moratoria on development. Eight months after our conversation, it’s clear as day how right he was. So I wanted to check back in with him to see how the state’s development landscape looks now and what the future may hold with the Moss Landing dust settled.

Help my readers get a state of play – where are we now in terms of the post-Moss Landing resistance landscape?

Keep reading...Show less
Yellow
Hotspots

A Tough Week for Wind Power and Batteries — But a Good One for Solar

The week’s most important fights around renewable energy.

The United States.
Heatmap Illustration/Getty Images

1. Nantucket, Massachusetts – A federal court for the first time has granted the Trump administration legal permission to rescind permits given to renewable energy projects.

  • This week District Judge Tanya Chutkan – an Obama appointee – ruled that Trump’s Bureau of Ocean Energy Management has the legal latitude to request the withdrawal of permits previously issued to offshore wind projects. Chutkan found that any “regulatory uncertainty” from rescinding a permit would be an “insubstantial” hardship and not enough to stop the court from approving the government’s desires to reconsider issuing it.
  • The ruling was in a case that the Massachusetts town of Nantucket brought against the SouthCoast offshore wind project; SouthCoast developer Ocean Winds said in statements to media after the decision that it harbors “serious concerns” about the ruling but is staying committed to the project through this new layer of review.
  • But it’s important to understand this will have profound implications for other projects up and down the coastline, because the court challenges against other offshore wind projects bear a resemblance to the SouthCoast litigation. This means that project opponents could reach deals with the federal government to “voluntarily remand” permits, technically sending those documents back to the federal government for reconsideration – only for the approvals to get lost in bureaucratic limbo.
  • What I’m watching for: do opponents of land-based solar and wind projects look at this ruling and decide to go after those facilities next?

2. Harvey County, Kansas – The sleeper election result of 2025 happened in the town of Halstead, Kansas, where voters backed a moratorium on battery storage.

Keep reading...Show less