Trump Has Paralyzed Renewables Permitting, Leaked Memo Reveals

The American Clean Power Association wrote to its members about federal guidance that has been “widely variable and changing quickly.”

Donald Trump.
Heatmap Illustration/Getty Images

Chaos within the Trump administration has all but paralyzed environmental permitting decisions on solar and wind projects in crucial government offices, including sign-offs needed for projects on private lands.

According to an internal memo issued by the American Clean Power Association, the renewables trade association that represents the largest U.S. solar and wind developers, Trump’s Day One executive order putting a 60-day freeze on final decisions for renewable energy projects on federal lands has also ground key pre-decisional work in government offices responsible for wetlands and species protection to a halt. Renewables developers and their representatives in Washington have pressed the government for answers, yet received inconsistent information on its approach to renewables permitting that varies between lower level regional offices.

In other words, despite years of the Republican Party inching slowly toward “all of the above” energy and climate rhetoric that seemed to leave room for renewables, solar and wind developers have so far found themselves at times shut out of the second Trump administration.

ACP’s memo, which is dated February 3 and was sent to its members, states that companies are facing major challenges getting specific sign-offs and guidance from the Army Corps of Engineers, which handles wetlands permits, as well as the Fish and Wildlife Service, our nation’s primary office for endangered species and migratory bird regulation.

Federal environmental protection laws require that large construction projects — even those on state and private lands — seek direction from these agencies before building can commence. Wetlands permitting has long been the job of the Army Corps, which determines whether particularly wet areas are protected under the Clean Water Act. Wetlands have historically been a vector for opponents of large pipelines and mines, as such areas are often co-located with sensitive ecosystems that activists want to preserve.

Fish and Wildlife, meanwhile, often must weigh in on development far from federal acreage because, according to the agency, two-thirds of federally listed species have at least some habitat on private land. FWS also handles the conservation of bird species that migrate between the U.S. and Canada, which are protected under the Migratory Bird Treaty Act. Any changes to federal bird consultation could impact wind developers because turbine blades can kill birds.

Now, apparently, all those important decision-makers are getting harder to read — or even reach. Army Corps district activity has become “widely variable” and is “changing quickly,” per the memo, with at least two districts indicating that for “wind or solar projects” they “will not be issuing any JDs,” meaning jurisdictional determinations for federally protected wetlands — that is, they won’t even say whether federal wetlands are present at a construction site or not. According to the Army Corps, receiving a JD is optional, but it is nevertheless an essential tool for developers trying to avoid future legal problems in the permitting process.

In addition, emails from staff in FWS’ migratory birds protection office now apparently include a “boilerplate notice” that says the office “is unable to communicate with wind facilities regarding permitting at this time.”

Usually, renewables developers just get a simple go-ahead from the government saying that they don’t have wetlands or bird nests present and that therefore work can begin. Or maybe they do have one of those features at the construction site, so guardrails need to be put in place. Either way, this is supposed to be routine stuff unless a project is controversial, like the Keystone XL pipeline or Pebble Mine in Alaska.

It’s not immediately clear how solar and wind developers move forward in this situation if they are building in areas where wetlands or protected species even may be present. Violating wetlands and species protection laws carries legal penalties, and with the Trump administration arranging itself in such an openly hostile fashion against renewables developers, it’s probably not a good idea to break those laws.

Unfortunately for industry, the ACP memo describes a confusing state of affairs. “Written guidance from ACOE [Army Corps of Engineers] to industry has been expected but members have not seen it yet. Actions and communications from regional districts appear to be guided by internal ACOE emails,” the document states. Staffing within the Army Corps is “uncertain” due to questions over whether money from the Inflation Reduction Act — which provided funds to hire permitting personnel — will be “available to continue funding staff positions in some offices,” or whether permitting staff will take the administration’s voluntary resignation offer, which the memo claims “is apparently still actively being pushed on staff with emails.”

Meanwhile, at Fish and Wildlife, ACP’s members “have indicated some staff are still taking phone calls and responding to emails to answer questions, while others are not.”

As with a lot happening in the early era of Trump 2.0, much of the permitting mess is still unclear. We don’t know who is behind these difficulties because there have been no public policy or guidance changes from the Army Corps or Fish and Wildlife. Trump did order agencies to stop issuing “new or renewed approvals” for wind projects shortly after entering office, but the ACP memo describes something altogether different: agency staff potentially refusing to declare whether an approval is even necessary to build on state or private lands.

Another example of how confusing this is? Interior had issued a 60-day pause on final decisions for solar projects, but the Army Corps isn’t under Interior’s control — it’s part of the Defense Department.

It’s also unclear if the contagion of permitting confusion has spread to other agencies, such as the Federal Aviation Administration, which we previously reported must regularly weigh in on wind turbines for aviation safety purposes. As I reported before Inauguration Day, anti-wind activists urged the Trump administration to essentially weaponize environmental laws against wind energy projects.

ACP didn’t respond to a request for comment. I also reached out to the Army Corps of Engineers and Fish and Wildlife Service, so I’ll let you know if and when I hear back from any of them.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

Fighting NIMBYism with Cash and State Overrides

And more of the week’s top news about renewable energy fights.

The United States.
Heatmap Illustration/Getty Images

1. Jefferson County, New York – Two solar projects have been stymied by a new moratorium in the small rural town of Lyme in upstate New York.

  • Lyme passed the solar moratorium earlier this week in response to AES’ Riverside and Bay Breeze solar projects and it’ll remain in place at least through October. Riverside had been approved already by state regulators, circumventing local concerns, but will reportedly still need to be relocated due to the moratorium.
  • Notably, opposition in the New York town has been fomented by a small chapter of Citizens for Responsible Solar, the anti-solar umbrella organization we wrote about in our profile of Virginia renewables fights last month.

2. Sussex County, Delaware – The Delaware legislature is intervening after Sussex County rejected the substation for the offshore MarWin wind project.

Keep reading...Show less
Yellow
Q&A

Has Solar Done This Before?

A conversation with Robb Jetty, CEO of REC Solar, about how the developer is navigating an uncertain environment.

Robb Jetty.
Heatmap Illustration

This week I chatted with REC Solar CEO Robb Jetty, who reached out to me through his team after I asked for public thoughts from renewables developers about their uncertain futures given all the action in Congress around the Inflation Reduction Act. Jetty had a more optimistic tone than I’ve heard from other folks, partially because of the structure of his business – which is actually why I wanted to include his feelings in this week’s otherwise quite gloomy newsletter.

The following conversation has been lightly edited for clarity. Shall we?

Keep reading...Show less
Yellow
Spotlight

Trump’s Onshore Wind Pause Is Still On

Six months in, federal agencies are still refusing to grant crucial permits to wind developers.

Donald Trump and a wind turbine.
Heatmap Illustration/Getty Images

Federal agencies are still refusing to process permit applications for onshore wind energy facilities nearly six months into the Trump administration, putting billions in energy infrastructure investments at risk.

On Trump’s first day in office, he issued two executive orders threatening the wind energy industry – one halting solar and wind approvals for 60 days and another commanding agencies to “not issue new or renewed approvals, rights of way, permits, leases or loans” for all wind projects until the completion of a new governmental review of the entire industry. As we were first to report, the solar pause was lifted in March and multiple solar projects have since been approved by the Bureau of Land Management. In addition, I learned in March that at least some transmission for wind farms sited on private lands may have a shot at getting federal permits, so it was unclear if some arms of the government might let wind projects proceed.

Keep reading...Show less