Another Solar Company Trying Gas-Powered Data Center on Federal Lands

And more of the week’s top news around project development.

•
The United States.
Heatmap Illustration/Getty Images

1. Ada County, Idaho – Trump’s push for more data centers on federal lands is causing a lot more ruckus and catching another solar company in the cross-fire.

  • Last week, D.C. news outlet The Washington Sun first reported that a subsidiary of solar developer Arevia Power submitted a right-of-way application for a data center project on federal lands in Idaho, a fact the Bureau of Land Management confirmed in a statement to me Thursday. The project is currently in a preliminary phase of permitting and a public notice can be expected this year, a Bureau of Land Management representative told me.
  • Until the initiation of any National Environmental Policy Act review, information on the data center is scarcely available on public websites. So here’s what BLM told me about it in a statement: the data center project will be 4 million square feet and include a 3,226-acre parcel of federal land. An additional 514 acres will be needed for a 10.6-mile “electrical load line corridor.” The data center complex will include a substation, stepdown electrical yards, a water connection, and a 450-megawatt on-site natural gas-fired power facility. The project is expected to use upwards of 600 megawatts though, which explains the potential load lines.
  • The Sun story also claimed the Arevia project will connect to a “sprawling utility-scale” solar project. BLM has previously said the data center is in some way “linked” to an Arevia solar farm proposed on federal lands north of Twin Falls, Idaho.
  • Arevia Power did not respond to a request for comment on the project nor the reported inclusion of gas generation along with solar, which I could not find discussed on their website. This is not the first time I’ve seen reports of this kind of activity from a solar developer. On August 3, I reported that solar developer Clearway canceled a proposal submitted to the Bureau of Land Management to transform a solar application into a data center and gas project – after we made the existence of the proposal public.
  • On Thursday I spoke with Heather Tied-Nelson, acting communications lead for the Bureau of Land Management Idaho field office, briefly over the phone about the project. “It’s all so very early in the process. We’re working with the company to try to finalize their plan of development and probably publish a notice of intent to begin the planning process later this fall or winter,” Tied-Nelson told me. Then I asked whether the data center was tied to Arevia’s solar efforts and if this was another solar farm-for-data center application swap kind of situation. She replied: “I can’t speak to that.”

2. Carbon County, Wyoming – Tell me if you’ve heard this one before: The Trump administration just delayed a large fossil-free power project after criticism from a powerful Republican senator. But this time, it’s hydropower.

  • The Bureau of Land Management will now be conducting an extra environmental analysis of the final NEPA environmental impact statement for rPlus’ Seminoe pumped storage hydropower project, which was approved by the Federal Energy Regulatory Commission in June. The project was opposed by fishing enthusiasts, recreationalists, and conservation activists. It could also provide 900 megawatts of power, which rPlus notes is about the same as two operational coal plants nearby.
  • Delay was made more likely after Wyoming Sen. John Barrasso, the Republican Senate Majority Whip and former chair of the Energy and Natural Resources Committee, backed calls to stop development at the project site. “This is an area that must be protected,” Barrasso said.
  • A supplemental review post-NEPA is hardly a common occurrence and it’s often controversial with industry when administrations take that step under political pressure. I anticipate we’ll hear more from the hydropower sector about what happened here if action doesn’t proceed with haste.

3. Crawford County, Wisconsin – Fighting transmission lines in Wisconsin is bipartisan now.

  • Midcontinent Grid Solutions is planning to build a large high-voltage transmission line to cut across about 190 miles from Crawford County to Walworth County in southern Wisconsin. Rep. Derrick Van Orden, a stalwart Trump ally backed by the Crawford County GOP’s chair, is now opposing the project. “I have heard directly from my constituents about the significant impacts of the proposed line,” he said in a letter to the developer. “They feel like they are being pushed around by your company. This is something I will not stand for.”
  • Rep. Mark Pocan, a progressive Democrat, is now opposing the line too, citing frustrations and fears from constituents in three counties the line cuts through: Dane, Sauk, and Rock. “People who received letters just weeks ago are now being asked to absorb the entirety of a 190-mile, 765-kV line, identify the parties involved, understand potential routes through their communities, and provide meaningful feedback, all on a compressed timeline that does not match the scale of the project's impact on their land, their livelihoods, and their communities,” Pocan said in a letter to the Midcontinent Grid Solutions.

4. Highland County, Ohio – If you want good news, here’s a slightly positive story in Ohio.

  • The Ohio Power Siting Board approved a 300-megawatt Hecate Energy BESS facility at a solar farm in Highland County and greenlit new documents submitted for Savion’s Oak Run agri-voltaics project, which has been kicking around in court battles until the state Supreme Court approved legal remand. This means Oak Run is also approved unless something else changes.
  • Does this mean Ohio is actually easier for energy developers? The last Ohio solar project update registered in the Heatmap Pro database indicates the Ohio Power Siting Board will soon reject a Geronimo Power solar project. So, tough luck.
Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Plus

The Promise and Peril of the Blue Wave for Renewables

Talking with Arnab Pal, the executive director of Deploy Action.

•
The Q&A subject.
Heatmap Illustration

This week’s conversation is with Arnab Pal, executive director of Deploy Action, president of Clean Infrastructure Advisors, and former principal advisor at the Energy Department’s Loan Programs Office under the Biden administration alongside Jigar Shah.

I reached out to Pal for guidance on where he saw state-level policy going around renewables development after the 2026 blue wave election. Simply put, few could’ve provided better guidance. We have no idea what could happen next after an unprecedented election result, but he couldn’t have been more clear-eyed and, as he put it to me, focused on the future. I appreciated our conversation and decided it was worthwhile to provide it to you in full.

Keep reading...Show less
Yellow
Spotlight

Was This Really the Data Center Election?

Evidence suggests data center concerns probably didn’t actually flip many votes.

•
Voting signs and a data center.
Heatmap Illustration/Getty Images, Library of Congress

This week’s midterm elections were undeniably horrible for the data center industry. But a closer look indicates dominant media narratives about the impact of AI infrastructure on voting behavior also deserve more scrutiny.

On election night, candidates who railed against data center sprawl during their campaigns won across the country, including statewide races in red areas. The most striking example was Gina Hinojosa, now governor-elect for the data center-centric state of Texas, who ran on instituting a complete pause on projects across the Lone Star State. So striking was her win, it sent AI and data center stocks into freefall. Cleanview, a clean energy news and data site, said Hinojosa’s pause, if put into effect, could affect up to 88.4 gigawatts of “planned” data center development, depending on how it's implemented.

Keep reading...Show less
Yellow
Hotspots

The Place Where a Candidate Promising to Do Less on Data Centers Actually Won

And more of the week’s top fights around development.

•
The United States.
Heatmap Illustration/Getty Images

1. McCracken County, Kentucky – A rare bright spot for the data center sector quietly occurred in deep red Kentucky in a race defined by what’ll likely be the first project built on federal land.

  • As I previously reported, a large data center project became the primary point of conflict in the race for McCracken County’s judge-executive. The incumbent Republican Craig Clymer had welcomed the project, and faced a challenge from independent George Bray, mayor of the county’s largest city of Paducah. Bray also supported the data center but said his city, which is adjacent to the project, should’ve received more demarcated benefits. Bray called for a community benefit agreement.
  • Turns out voters in McCracken County didn’t care enough about this issue to make a change and wanted to keep Clymer in office. He won handily, netting more than 12,000 votes to Bray’s roughly 7,600. It’s one of the few races across the country that went in favor of the candidate promising to do less when it came to data centers.

2. Pulaski County, Arkansas – After a blue wave election in Little Rock, this county government is on a collision course with data center development.

Keep reading...Show less