Why the Senate Permitting Bill Isn’t a ‘Grand Bargain’

A conversation with Josh Freed of Third Way

•
Josh Freed.
Heatmap Illustration

This week’s conversation is about the big energy policy story of the week – month? year? – which is the new bipartisan permitting deal in the U.S. Senate. As my colleagues and I were feverishly working on our mega-explainer about the bill, I rang up Josh Freed, founder of Third Way’s energy and climate program, who graciously picked up the phone despite traveling in London. Freed, a fellow energy wonk-slash-musician, was gracious to jam out with me on all the things I felt you needed to know about this bill – including whether there really is only one shot to get what he believes would be landmark legislation into law.

The following chat was lightly abridged for clarity. Let’s dive in.

Let’s start with descriptions. Thomas Hochman, a friend of Heatmap News, published a lengthy blog about the new bipartisan Senate permitting bill in which he describes it as a “grand bargain.”

Do you agree with that description?

No. See, it’s so funny, I saw that description as well and I think over the years I’ve soured on the concept of ‘grand bargains.’ But it’s hugely significant.

Okay. If it’s not a ‘grand bargain,’ how would you describe it?

Well the problem with a ‘grand bargain’ is it assumes there’s all these trade-offs and everyone gets a little bit of something. But the reason I think it’s just significant, and not that, is it took the transmission architecture that Manchin-Barrasso had that was close to passing and built it out for current load growth. That’s a big deal given how much the transmission side has been a blockage in the system. And how much they dealt with the permitting of infrastructure, generally.

When we did our survey of over 200 project developers a little over a year ago, we were surprised at how much that was what they were concerned about – transmission and permitting of utility-scale solar. They’ve added those two things into the bill. So we’ve got consequential transmission permitting provisions and steps to add a lot of certainty, while shortening the window where objections based on those laws can pop up. This means a lot more is likely to be built and it’s very likely that’ll be clean.

There’s infrastructure with fossil fuels that’ll be built. We get that. But when costs are so high, that’s also sort of inevitable. The overall proposal is more of a win to build than a bargain.

Does the language in this bill adequately address Trump’s freeze on federal permits for renewable energy projects?

I think it is a really important step in the right direction with permitting certainty for solar and wind but this question with national security, and making sure this gives the certainty that these projects will ultimately be delivered… I just genuinely don’t know. But we need to make sure it's sufficiently airtight. Is this the best, most reasonable attempt to do this? That’s the question that needs to be answered.

The combination of permitting certainty and anti-discrimination language barring the executive branch from category wide attacks on offshore wind or solar are steps that need to be taken. At some point we’re all going to have to take the step off the cliff together and see what happens next because we’re getting as good as we’re going to get, presuming the administration will follow the law. If they don’t follow the law, there’ll be actions to be taken to get them back on track.

But this is what you have to do, because otherwise, everything’s still broken. At least it gives us additional mechanisms to keep them in line.

Do you think this has to happen before the next Congress convenes?

The most likely time for action is the lame duck period in Congress. I think there’s a slim chance you could see something happen next year but it’s impossible to predict how likely that chance is or what it would look like until we see the election results. I wouldn’t want to gamble on everything lining up to get another bite at the apple next year. And lame duck’s always been the most likely time for this to happen.

Okay. So let’s say this bill becomes law. What do folks like you do next on energy in D.C.?

I think we get this done and then we’ve got to make sure the law works. Assuming this passes, we’ve got to make sure the obstacles we thought were obstacles really were the obstacles, and this still doesn’t address additional issues data centers have raised. We need an enforceable framework so as data centers come onto the system, the additional generation and transmission is built in a way that’s in the best interest of communities and paid for by the data centers.

There are questions of whether the market structures created more than a hundred years ago are still the correct structures for 2026. If they’re not, then what’s the path to getting stuff built and maintained effectively? That alone is enough. And I think the next biggest thing: what parts of the supply chain should be developed and where? Transformers, batteries, the future of the auto industry… all those fun things are up in the air.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

A Giant Data Center Offers a Permitting Reform Test Case

What would happen to Project Jupiter if the Bipartisan American Affordability and Jobs Act is passed?

•
Project Jupiter.
Heatmap Illustration/Project Jupiter, Library of Congress

One of the nation’s largest data centers is struggling under permitting woes. So let’s play a game: would the bipartisan permitting bill in Congress make the path easier, or might the federal legislation be irrelevant to large hyperscalers under development today?

Meet Project Jupiter, a mega project in southern New Mexico in Dona Ana County under development by Oracle and OpenAI, with financial backing from SoftBank and political support from the Trump administration for being a part of Stargate, a major Trump administration public-private initiative boosting AI development. Project Jupiter would be one of the largest data centers in the country if completed and currently is expected to run on a microgrid powered by fuel cells converting gas to electricity, which the developers claim will burn much cleaner than a typical off-grid gas turbine power plant.

Keep reading...Show less
Yellow
Hotspots

The Trump Administration Is Still Messing with Offshore Wind Farms

And more of the week’s top news around project fights.

•
The United States.
Heatmap Illustration/Getty Images

1. New England (and Maryland) – The Trump administration is still messing with offshore wind farms, even while trying to pass a permitting reform deal. Examining the court filings reveals why they may feel empowered to do it — and I’m not sure how this ends.

  • Last Friday, in a legal case brought by anti-wind activists, the Justice Department submitted a motion in federal court to send the construction and operations plan for Orsted’s Revolution Wind project in New England back to the Interior Department for more analysis. On Wednesday, the DOJ entered a similar motion in another case challenging the construction and operations plan for U.S. Wind’s MarWin project off the coast of Maryland in a lawsuit brought by the state’s coastal community of Ocean City.
  • Trump’s actions led some to question whether the president was sabotaging the deal, and others to claim the media coverage itself was an attempt to kill it. Going further, supporters of the bipartisan bill claimed the DOJ's motions were precisely why the bill should become law, implying it would guard offshore wind farms against this sort of maneuver.
  • However, for the bill’s backers, it’s worth considering why the Trump administration believes it has the legal authority to do this. It’s also time to ask whether the bill would actually protect these wind farms against this tactic.
  • To answer those questions, you have to rewind. On May 1, 2025, the Interior Department withdrew a Biden solicitor’s opinion instructing the agency to “strike a rational balance” between wind power and fishing interests. This revocation document is technically not in effect at the moment; one year later, a federal court ruled the opinion was potentially illegal as a part of a preliminary injunction on five anti-renewables actions requested by solar and wind trade groups. The Trump administration is contesting that ruling, and the administration has filed a notice of appeal.
  • In August, despite that opinion being in doubt, a federal judge granted Trump permission under the Outer Continental Shelf Lands Act to remand the construction and operations plan for the now-defunct Atlantic Shores offshore wind farm in the waters of New Jersey. U.S. District Judge Jia Cobb specifically wrote that Atlantic Shores failed to demonstrate the federal government had limitations under OSCLA on revisiting these plans and that the injunction from the litigation on appeal “did not prohibit all reevaluation of agency action.”
  • In the recent Revolution and MarWin filings, Trump’s Justice Department argues the construction and operations plans should be remanded under OSCLA without being vacated. The DOJ motions include claims that previous decision documents did not adequately explain impacts to commercial fishing and other industries that use OSCLA waters. It’s not clear if the administration will win these motions.
  • The bipartisan permitting bill would bar the Interior Department and other federal agencies from taking “any new action that would revoke, rescind, withdraw, terminate, suspend, amend, or alter a federal authorization or permit in effect on or after September 16, 2026,” or “any other action to interfere with or prevent the construction or operation at full capacity of a project that has secured all necessary federal authorizations and permits.” The restriction exempts cases where “the agency is required to take such action by order of a court.” As I wrote in our lengthy piece explaining the bill, this provision has a damages component that allows companies impacted by violations to pursue financial compensation.
  • Here’s the billion-dollar question I expect we won’t have answered unless the bill language is enacted and then litigated: Would the court order exception apply to rulings that grant these motions? Or would the developers be able to sue for damages?

2. Columbia County, N.Y. – New York’s renewable energy permitting office has rejected an upstate solar farm on farmland as a House Democrat representing the area joined hands with the Trump administration in publicly railing against the project.

Keep reading...Show less
Yellow
Q&A

The Developer that Builds Local Support with ‘Right-sized’ Data Centers

A conversation with Harmol Samra of Host Digital

•
The Q&A subject.
Heatmap Illustration

This week’s conversation is with Harmol Samra, CEO of data center developer Host Digital. I asked Samra for a conversation because his team expressed a willingness to offer candid views on the industry’s problems with social license to operate — namely, why is the industry botching this so badly? From his point of view, many could learn a lot from industrial revolutions of the past, and they should be careful not to let mega-project expansions get in the way of broader acceptance of the data center sector.

The following conversation was lightly edited for clarity.

Keep reading...Show less