You’re out of free articles.
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.
Sign In or Create an Account.
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Welcome to Heatmap
Thank you for registering with Heatmap. Climate change is one of the greatest challenges of our lives, a force reshaping our economy, our politics, and our culture. We hope to be your trusted, friendly, and insightful guide to that transformation. Please enjoy your free articles. You can check your profile here .
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Subscribe to get unlimited Access
Hey, you are out of free articles but you are only a few clicks away from full access. Subscribe below and take advantage of our introductory offer.
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Create Your Account
Please Enter Your Password
Forgot your password?
Please enter the email address you use for your account so we can send you a link to reset your password:
There’s a lot more big talk than reactor-building going on.

America’s technology companies need power, and lots of it.
Artificial intelligence combined with still-growing internet and smartphone use will likely require a game-changing investment in data centers — one that its already showing up in huge projected increases for electricity demand across the country. At the same time, many technology companies want to procure and invest in clean power, while many states have clean energy goals that may make it difficult to add new load to the grid without a corresponding investment in clean generation. All told, the Department of Energy estimates that some 700 to 900 gigawatts of new clean firm capacity — energy generation that doesn’t emit greenhouse gases and can run 24 hours a day — will be necessary to build a fully decarbonized grid. Even in the real world, technology companies are interested in acquiring whatever clean power they can.
This is where the nuclear industry would love to step in, specifically the segment of the industry making small modular reactors, otherwise known as SMRs. These reactors, which promise to be cheaper, smaller, and faster to build than the existing nuclear fleet, seem like an ideal match for what technology companies need. What could be better for data centers than on-site power (meaning no transmission costs) that runs all day (meaning no intermittency issues) with no carbon emissions (meaning no climate worries)? And if those nuclear power plants could be built quickly and cheaply out of pre-fabricated parts, all the better, right?
Whether SMRs actually can step in, well ... “If I had every agreement in principle SMRs have signed, I could walk from here to Europe without getting my feet wet,” Dan Yurman, the publisher of Neutron Bytes and a former project manager at the Idaho National Laboratory, told me.
The issue is that the most optimistic timeline for commercial deployment of SMRs starts in the late 2020s, with most observers putting actual deployment into sometimes in the 2030s. All the while, demand for data centers is growing now and is projected to accelerate sharply in the next few years.
As of today only a handful of small modular reactors are currently operational anywhere in the world, and none in the United States. The Nuclear Regulatory Commission, which governs all civilian nuclear construction in the country, has so far approved just one SMR design; NuScale, the company behind said design, recently laid off almost a third of its employees after its deal to build a power plant in Utah for a collection of local utilities fell through due to rising costs.
That approval process cost $500 million and took around five years, according to the Wall Street Journal — and, of course, NuScale has yet to get a functioning reactor out of it. The company is currently in the process of getting the go-ahead on a more powerful version of its existing design, which the company’s chief executive said could be approved “within 24 months.”
On paper, however, enthusiasm for co-locating SMRs with data centers and industrial sites abounds. Despite the collapse of the Utah project, during an earnings call this month, NuScale eagerly talked up a partnership with Standard Power to provide 2 gigawatts of electricity to data centers in Ohio and Pennsylvania. While its shares are down around 50% for the past 12 months, they are up about 35% (albeit to around $4.20) since the end of last year. In its presentation to investors, NuScale cited estimates that data center electricity consumption would triple by the beginning of the next decade.
“Management is quite enthusiastic around its opportunity with data center operators, noting that it's in discussions with large players as electricity demand accelerates via the AI buildout,” Ryan Pfingst and Chris Souther, two analysts for B. Riley Securities, wrote in a note to clients following the release of NuScale’s earnings report.
That enthusiasm notwithstanding, it’s not clear how far along the Standard Power project is. “A project of this size has a significant amount of detail that’s confirmed and structured before a project begins construction and those discussions are ongoing,” NuScale CEO John Hopkins told analysts on the company’s most recent earnings call. Standard Power did not return a request for comment asking for more details on the financing or construction timeline for its project. When asked for an update from NuScale, a spokesperson referred me to the earnings call.
Meanwhile, in Surry County, Virginia, work is advancing on a project adjacent to the existing Surry nuclear plant. The project would combine data centers, small modular reactors, and hydrogen fuel production; the data centers would come first, with SMRs following once costs come down, according to Michael Hewitt, the co-founder and chief executive officer of IP3, the project’s developer.
For Hewitt, the model for SMR deployment is to build them in factories and scale them directly for end users. “That’s the future of energy: If I want a gigawatt of data center, I build SMRs for the data center on day one,” he told me.
Which company will get there first? “If I had to guess right now, in terms of what will be factory-built first and available to consumers like us, it will more than likely be a light water reactor design — GE, NuScale, or perhaps Rolls-Royce,” Hewitt said. GE’s SMR design, the BWRX-300, is in the pre-application process with the NRC, and was picked by Ontario Power Generation for a nuclear development on its existing Darlington site. The Rolls-Royce SMR has been advancing through the British regulatory and procurement process, while the company currently designs light-water reactors for the Royal Navy.
“The first guy to get the factory built is the winner,” Hewitt said. But none will likely be ready for the Virginia project, at least not within the next eight to 10 years, though, he added. Nevertheless, urgent interest persists.
On Tuesday, Google, Microsoft, and the steel company Nucor announced that they were forming a group that would commit to purchasing clean firm technologies and included in its laundry list of potential power sources advanced nuclear. Another advanced nuclear developer, TerraPower, which is backed by Microsoft’s founder Bill Gates, announced Tuesday that it was applying for a construction permit for a plant in Wyoming and plans to start building non-nuclear portions of it in June. The company expects the full plant to come online in 2030.
There are dozens of other SMR designs at various stage of realization, but the absolute fastest a new design could get online, according to Adam Stein of the Breakthrough Institute, is around four years. “If a developer has not already submitted an application to the NRC to build a power plant — which none of them have for a specific site — then they mostly likely would not be able to operate a power plant before 2028,” Stein told me. “That is the soonest it could happen.”
That said, “If there’s more urgency from the market, a clearer and larger demand signal, then developers will move faster than they are right now,” Stein added.
What’s far more likely, according to Yurman, is that tech companies will sign power purchase agreements for existing nuclear power plants, as Amazon has with Talen Energy. “That’s immediate access to reliable power,” Yurman said.
And even if SMRs are actually built, they may not end up adjacent to data centers, but instead on the sites of existing nuclear and even coal plants (this is the plan for the TerraPower site) which have preexisting grid connections. “If I’m putting together this kind of deal,” Yurman told me, “I’m looking at an old coal power plant I can demolish and keep the grid connection.”
While American tech companies are eager to buy up new power, the real opportunity, should it ever come, may be overseas, where smaller countries without indigenous energy supplies could be especially interested in nuclear power.
“What we need to do is get to full rate production and start stamping out SMRs with low risk,” Hewitt said. “If we do that, we can take these things everywhere.”
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.
There has been no new nuclear construction in the U.S. since Vogtle, but the workers are still plenty busy.
The Trump administration wants to have 10 new large nuclear reactors under construction by 2030 — an ambitious goal under any circumstances. It looks downright zany, though, when you consider that the workforce that should be driving steel into the ground, pouring concrete, and laying down wires for nuclear plants is instead building and linking up data centers.
This isn’t how it was supposed to be. Thousands of people, from construction laborers to pipefitters to electricians, worked on the two new reactors at the Plant Vogtle in Georgia, which were intended to be the start of a sequence of projects, erecting new Westinghouse AP1000 reactors across Georgia and South Carolina. Instead, years of delays and cost overruns resulted in two long-delayed reactors 35 miles southeast of Augusta, Georgia — and nothing else.
“We had challenges as we were building a new supply chain for a new technology and then workforce,” John Williams, an executive at Southern Nuclear Operating Company, which owns over 45% of Plant Vogtle, said in a webinar hosted by the environmental group Resources for the Future in October.
“It had been 30 years since we had built a new nuclear plant from scratch in the United States. Our workforce didn’t have that muscle memory that they have in other parts of the world, where they have been building on a more regular frequency.”
That workforce “hasn’t been building nuclear plants” since heavy construction stopped at Vogtle in 2023, he noted — but they have been busy “building data centers and car manufacturing in Georgia.”
Williams said that it would take another “six to 10” AP1000 projects for costs to come down far enough to make nuclear construction routine. “If we were currently building the next AP1000s, we would be farther down that road,” he said. “But we’ve stopped again.”
J.R. Richardson, business manager and financial secretary of the International Brotherhood of Electric Workers Local 1579, based in Augusta, Georgia, told me his union “had 2,000 electricians on that job,” referring to Vogtle. “So now we have a skill set with electricians that did that project. If you wait 20 or 30 years, that skill set is not going to be there anymore.”
Richardson pointed to the potential revitalization of the failed V.C. Summer nuclear project in South Carolina, saying that his union had already been reached out to about it starting up again. Until then, he said, he had 350 electricians working on a Meta data center project between Augusta and Atlanta.
“They’re all basically the same,” he told me of the data center projects. “They’re like cookie cutter homes, but it’s on a bigger scale.”
To be clear, though the segue from nuclear construction to data center construction may hold back the nuclear industry, it has been great for workers, especially unionized electrical and construction workers.
“If an IBEW electrician says they're going hungry, something’s wrong with them,” Richardson said.
Meta’s Northwest Louisiana data center project will require 700 or 800 electricians sitewide, Richardson told me. He estimated that of the IBEW’s 875,000 members, about a tenth were working on data centers, and about 30% of his local were on a single data center job.
When I asked him whether that workforce could be reassembled for future nuclear plants, he said that the “majority” of the workforce likes working on nuclear projects, even if they’re currently doing data center work. “A lot of IBEW electricians look at the longevity of the job,” Richardson told me — and nuclear plants famously take a long, long time to build.
America isn’t building any new nuclear power plants right now (though it will soon if Rick Perry gets his way), but the question of how to balance a workforce between energy construction and data center projects is a pressing one across the country.
It’s not just nuclear developers that have to think about data centers when it comes to recruiting workers — it’s renewables developers, as well.
“We don’t see people leaving the workforce,” said Adam Sokolski, director of regulatory and economic affairs at EDF Renewables North America. “We do see some competition.”
He pointed specifically to Ohio, where he said, “You have a strong concentration of solar happening at the same time as a strong concentration of data center work and manufacturing expansion. There’s something in the water there.”
Sokolski told me that for EDF’s renewable projects, in order to secure workers, he and the company have to “communicate real early where we know we’re going to do a project and start talking to labor in those areas. We’re trying to give them a market signal as a way to say, We’re going to be here in two years.”
Solar and data center projects have lots of overlapping personnel needs, Sokolski said. There are operating engineers “working excavators and bulldozers and graders” or pounding posts into place. And then, of course, there are electricians, who Sokolski said were “a big, big piece of the puzzle — everything from picking up the solar panel off from the pallet to installing it on the racking system, wiring it together to the substations, the inverters to the communication systems, ultimately up to the high voltage step-up transformers and onto the grid.”
On the other hand, explained Kevin Pranis, marketing manager of the Great Lakes regional organizing committee of the Laborers’ International Union of North America, a data center is like a “fancy, very nice warehouse.” This means that when a data center project starts up, “you basically have pretty much all building trades” working on it. “You’ve got site and civil work, and you’re doing a big concrete foundation, and then you’re erecting iron and putting a building around it.”
Data centers also have more mechanical systems than the average building, “so you have more electricians and more plumbers and pipefitters” on site, as well.
Individual projects may face competition for workers, but Pranis framed the larger issue differently: Renewable energy projects are often built to support data centers. “If we get a data center, that means we probably also get a wind or solar project, and batteries,” he said.
While the data center boom is putting upward pressure on labor demand, Pranis told me that in some parts of the country, like the Upper Midwest, it’s helping to compensate for a slump in commercial real estate, which is one of the bread and butter industries for his construction union.
Data centers, Pranis said, aren’t the best projects for his members to work on. They really like doing manufacturing work. But, he added, it’s “a nice large load and it’s a nice big building, and there’s some number of good jobs.”
A conversation with Dustin Mulvaney of San Jose State University
This week’s conversation is a follow up with Dustin Mulvaney, a professor of environmental studies at San Jose State University. As you may recall we spoke with Mulvaney in the immediate aftermath of the Moss Landing battery fire disaster, which occurred near his university’s campus. Mulvaney told us the blaze created a true-blue PR crisis for the energy storage industry in California and predicted it would cause a wave of local moratoria on development. Eight months after our conversation, it’s clear as day how right he was. So I wanted to check back in with him to see how the state’s development landscape looks now and what the future may hold with the Moss Landing dust settled.
Help my readers get a state of play – where are we now in terms of the post-Moss Landing resistance landscape?
A couple things are going on. Monterey Bay is surrounded by Monterey County and Santa Cruz County and both are considering ordinances around battery storage. That’s different than a ban – important. You can have an ordinance that helps facilitate storage. Some people here are very focused on climate change issues and the grid, because here in Santa Cruz County we’re at a terminal point where there really is no renewable energy, so we have to have battery storage. And like, in Santa Cruz County the ordinance would be for unincorporated areas – I’m not sure how materially that would impact things. There’s one storage project in Watsonville near Moss Landing, and the ordinance wouldn’t even impact that. Even in Monterey County, the idea is to issue a moratorium and again, that’s in unincorporated areas, too.
It’s important to say how important battery storage is going to be for the coastal areas. That’s where you see the opposition, but all of our renewables are trapped in southern California and we have a bottleneck that moves power up and down the state. If California doesn’t get offshore wind or wind from Wyoming into the northern part of the state, we’re relying on batteries to get that part of the grid decarbonized.
In the areas of California where batteries are being opposed, who is supporting them and fighting against the protests? I mean, aside from the developers and an occasional climate activist.
The state has been strongly supporting the industry. Lawmakers in the state have been really behind energy storage and keeping things headed in that direction of more deployment. Other than that, I think you’re right to point out there’s not local advocates saying, “We need more battery storage.” It tends to come from Sacramento. I’m not sure you’d see local folks in energy siting usually, but I think it’s also because we are still actually deploying battery storage in some areas of the state. If we were having even more trouble, maybe we’d have more advocacy for development in response.
Has the Moss Landing incident impacted renewable energy development in California? I’ve seen some references to fears about that incident crop up in fights over solar in Imperial County, for example, which I know has been coveted for development.
Everywhere there’s batteries, people are pointing at Moss Landing and asking how people will deal with fires. I don’t know how powerful the arguments are in California, but I see it in almost every single renewable project that has a battery.
Okay, then what do you think the next phase of this is? Are we just going to be trapped in a battery fire fear cycle, or do you think this backlash will evolve?
We’re starting to see it play out here with the state opt-in process where developers can seek state approval to build without local approval. As this situation after Moss Landing has played out, more battery developers have wound up in the opt-in process. So what we’ll see is more battery developers try to get permission from the state as opposed to local officials.
There are some trade-offs with that. But there are benefits in having more resources to help make the decisions. The state will have more expertise in emergency response, for example, whereas every local jurisdiction has to educate themselves. But no matter what I think they’ll be pursuing the opt-in process – there’s nothing local governments can really do to stop them with that.
Part of what we’re seeing though is, you have to have a community benefit agreement in place for the project to advance under the California Environmental Quality Act. The state has been pretty strict about that, and that’s the one thing local folks could still do – influence whether a developer can get a community benefits agreement with representatives on the ground. That’s the one strategy local folks who want to push back on a battery could use, block those agreements. Other than that, I think some counties here in California may not have much resistance. They need the revenue and see these as economic opportunities.
I can’t help but hear optimism in your tone of voice here. It seems like in spite of the disaster, development is still moving forward. Do you think California is doing a better or worse job than other states at deploying battery storage and handling the trade offs?
Oh, better. I think the opt-in process looks like a nice balance between taking local authority away over things and the better decision-making that can be brought in. The state creating that program is one way to help encourage renewables and avoid a backlash, honestly, while staying on track with its decarbonization goals.
The week’s most important fights around renewable energy.
1. Nantucket, Massachusetts – A federal court for the first time has granted the Trump administration legal permission to rescind permits given to renewable energy projects.
2. Harvey County, Kansas – The sleeper election result of 2025 happened in the town of Halstead, Kansas, where voters backed a moratorium on battery storage.
3. Cheboygan County, Michigan – A group of landowners is waging a new legal challenge against Michigan’s permitting primacy law, which gives renewables developers a shot at circumventing local restrictions.
4. Klamath County, Oregon – It’s not all bad news today, as this rural Oregon county blessed a very large solar project with permits.
5. Muscatine County, Iowa – To quote DJ Khaled, another one: This county is also advancing a solar farm, eliding a handful of upset neighbors.