People Who Hate Renewables Hate Data Centers, Too

And more thoughts on the week’s most notable fights around project development.

The United States.
Heatmap Illustration/Getty Images

1. Pinal County, Arizona – If you can’t build a solar or a wind farm somewhere, it’s really hard to get a data center built there too.

  • That’s the lesson readers should take away from the situation in Pinal County, where historically speaking at least 5 solar projects have been withdrawn over the years after facing local opposition, according to Heatmap Pro data. You should expect some data centers to potentially wind up in the same graveyard.
  • On Wednesday, the Pinal County Board of Supervisors rejected the La Osa Energy Center, a large proposed data center and gas-fired power complex. The board in this deep red rural desert community is rock-ribbed Republican. Only one supervisor on the board dissented, citing private property rights concerns.
  • The county currently has a restrictive ordinance against data center development unless they are in industrial areas, but has not yet approved a project since the ordinance was crafted, making this now a de facto no-go zone for developers. This went against the requests of the county zoning board, which recommended making the project site as industrial. If that pattern sounds familiar to you, that’s because you recognize it from the many cases we’ve seen in solar and wind development where political officials similarly override zoning staff.

2. St. Joseph County, Indiana – Thousands of miles away from Arizona, a similar division is dominating the fight over whether to enact a 2-year moratorium on data centers in the county home of South Bend.

  • Unlike Pinal, St. Joseph is run by a county council that apparently split down partisan lines on whether to enact the moratorium. Republicans are supportive; Democrats are against using an arbitrarily timed mechanism. Democratic Council President Bryan Tanner told local public radio affiliate WVPE this week: “I don’t think that an arbitrary time clock is a replacement for good judgement and a sound alignment with the five components of rezoning and land use that the state of Indiana ascribes local government with.”
  • But this county is also just like Pinal. Before data centers occupied officials, they were struggling under the weight of a solar power backlash that’s still ongoing. Also, both Pinal and St. Joseph have roughly the same clean energy and data center opposition risk in the Heatmap Pro database.

3. Ingham County, Michigan – The first solar farm fight has been resolved under Michigan’s new renewables siting law.

  • Along with creating a streamlined permitting system, the state’s 2023 permitting law put forth a regime to resolve disputes between localities and renewables developers. On Thursday, Ranger Power’s 90-megawatt Acceleration Solar project was cleared for construction under a settlement agreement between the company and multiple townships who were opposed to the project.
  • Now, Ranger Power will have numerous noise and light regulations, as well as restrictions on tree clearing and visibility. The most interesting thing about the agreement to me is that Ranger Power will have to pay at least $2,000 per megawatt towards “host community benefit payments” that would go towards the towns’ sewer and drain maintenance as well as firefighting staff.
  • This is probably the first time in my history of writing The Fight that I’m able to say a law is actually resolving disputes between developers and localities, a mark of model legislation.
Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

What Nevada’s Democratic Candidate for Governor Would Do About Data Centers

A conversation with Nevada attorney general Aaron Ford

Aaron Ford.
Heatmap Illustration

This week’s conversation is with Nevada attorney general Aaron Ford, the Democratic candidate for governor in the state. His campaign reached out recently asking if I wanted to chat about what he’d want to do on data center and energy policy, which is essentially catnip for a reporter like me. So we hopped on the phone and chatted about his approach to regulation as he seeks to oust the sitting GOP governor Joe Lombardo.

The following conversation was lightly edited and abridged for clarity.

Keep reading...Show less
Yellow
Spotlight

The Top Five States to Watch for Clean Energy Policy

What’s the matter with Wisconsin?

The Texas statehouse and clean energy.
Heatmap Illustration/Getty Images

The most important states to watch for the future of renewable energy policy sit at the nexus of the data center backlash.

Over the last week, I’ve poured over what I believe to be the top five most important spaces to watch for all things utility-scale solar, battery storage and transmission development: Texas, California, Arizona, Alabama and Wisconsin. I selected these five states because they either have some of the largest generation capacity (Texas, California, Arizona) or crucial statewide elections that could decide not only the future of renewable energy in the state but elsewhere across the country (Alabama, Wisconsin).

Keep reading...Show less
Yellow
Spotlight

Data Center Moratoria Are ‘Unconstitutional,’ Lawsuits Claim

A new front opens in the data center wars.

An anti-data-center sign.
Heatmap Illustration/Getty Images

A series of lawsuits filed in federal court asks a big question – are data center moratoria constitutional?

In early August, data center developer DC Blox sued the city of Nashville in federal court to overturn a zoning moratorium stopping them from building a hyperscale facility adjacent to the city zoo. “The Data Center Moratorium, moreover, is a targeted attack against DC BLOX, in violation of federal constitutional protections,” the suit argued, claiming that it defied the corporation’s due process and equal protection rights.

Keep reading...Show less