The National Park Service is Fighting a Solar Farm

A battle ostensibly over endangered shrimp in Kentucky

Mammoth Cave.
Heatmap Illustration/Library of Congress, Getty Images

A national park is fighting a large-scale solar farm over potential impacts to an endangered shrimp – what appears to be the first real instance of a federal entity fighting a solar project under the Trump administration.

At issue is Geenex Solar’s 100-megawatt Wood Duck solar project in Barren County, Kentucky, which would be sited in the watershed of Mammoth Cave National Park. In a letter sent to Kentucky power regulators in April, park superintendent Barclay Trimble claimed the National Park Service is opposing the project because Geenex did not sufficiently answer questions about “irreversible harm” it could potentially pose to an endangered shrimp that lives in “cave streams fed by surface water from this solar project.”

Trimble wrote these frustrations boiled after “multiple attempts to have a dialogue” with Geenex “over the past several months” about whether battery storage would exist at the site, what sorts of batteries would be used, and to what extent leak prevention would be considered in development of the Wood Duck project.

“The NPS is choosing to speak out in opposition of this project and requesting the board to consider environmental protection of these endangered species when debating the merits of this project,” stated the letter. “We look forward to working with the Board to ensure clean water in our national park for the safety of protection of endangered species.”

On first blush, this letter looks like normal government environmental stewardship. It’s true the cave shrimp’s population decline is likely the result of pollution into these streams, according to NPS data. And it was written by career officials at the National Park Service, not political personnel.

But there’s a few things that are odd about this situation and there’s reason to believe this may be the start of a shift in federal policy direction towards a more critical view of solar energy’s environmental impacts.

First off, Geenex has told local media that batteries are not part of the project and that “several voicemails have been exchanged” between the company and representatives of the national park, a sign that the company and the park have not directly spoken on this matter. That’s nothing like the sort of communication breakdown described in the letter. Then there’s a few things about this letter that ring strange, including the fact Fish and Wildlife Service – not the Park Service – ordinarily weighs in on endangered species impacts, and there’s a contradiction in referencing the Endangered Species Act at a time when the Trump administration is trying to significantly pare back application of the statute in the name of a faster permitting process. All of this reminds me of the Trump administration’s attempts to supposedly protect endangered whales by stopping offshore wind projects.

I don’t know whether this solar farm’s construction will indeed impact wildlife in the surrounding area. Perhaps it may. But the letter strikes me as fascinating regardless, given the myriad other ways federal agencies – including the Park Service – are standing down from stringent environmental protection enforcement under Trump 2.0.

Notably, I reviewed the other public comments filed against the project and they cite a litany of other reasons – but also state that because the county itself has no local zoning ordinance, there’s no way for local residents or municipalities opposed to the project to really stop it. Heatmap Pro predicts that local residents would be particularly sensitive to projects taking up farmland and — you guessed it — harming wildlife.

Barren County is in the process of developing a restrictive ordinance in the wake of this project, but it won’t apply to Wood Duck. So opponents’ best shot at stopping this project – which will otherwise be online as soon as next year – might be relying on the Park Service to intervene.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

The Loud Fight Over Inaudible Data Center Noise

Why local governments are getting an earful about “infrasound”

Data center noise.
Heatmap Illustration/Getty Images

As the data center boom pressures counties, cities, and towns into fights over noise, the trickiest tone local officials are starting to hear complaints about is one they can’t even hear – a low-frequency rumble known as infrasound.

Infrasound is a phenomenon best described as sounds so low, they’re inaudible. These are the sorts of vibrations and pressure at the heart of earthquakes and volcanic activity. Infrasound can be anything from the waves shot out from a sonic boom or an explosion to very minute changes in air pressure around HVAC systems or refrigerators.

Keep reading...Show less
Yellow
Hotspots

An Anti-Battery Avalanche Outside Seattle

And more on the week’s top fights around project development.

The United States.
Heatmap Illustration/Getty Images

1. King County, Washington – The Moss Landing battery backlash is alive and well more than a year after the fiery disaster, fomenting an opposition stampede that threatens to delay a massive energy storage project two dozen miles east of Seattle.

  • Moss Landing looms large in Snoqualmie, a city in the Cascade Mountains where Jupiter Power is trying to build Cascade Ridge Resiliency Energy Storage, a 130-megawatt facility conveniently located on unincorporated county land right by a substation and transmission infrastructure.
  • To say residents nearby are upset would be an understatement. A giant number of protestors – reportedly 650 people, which is large for this community of about 14,000 – showed up to rally against the project this weekend, just as Jupiter Power submitted its application for the project to county regulators.
  • The opposition is led by Snoqualmie Valley for Responsible Energy, a grassroots organization that primarily has focused on the risk of thermal runaway from battery storage events and rhetoric about the Moss Landing fire. “The battery chemistry proposed for Cascadia Ridge has not been verified in any public filing. Recent incidents illustrate what is at stake,” state SVRE strategy materials posted to their website.
  • Jupiter Power has tried to combat this campaign with its own organizing coalition – dubbed “Keep the Lights On!” – that includes local union labor and some environmentalists, including volunteers for Sierra Club. This campaign has emphasized how modern engineering around battery storage is nothing like the set-up was at Moss Landing.
  • However, the concerned voices are winning out over those who want the storage project. On Wednesday night, this outcry led the Snoqualmie city council at a special meeting to vote to request via letter for the storage project to be relocated and communicate that dissent to both the local utility, Puget Sound Energy, and King County.
  • “We encourage consideration of alternate locations within the Puget Sound Energy transmission and distribution system to better address the concerns that have been raised,” read a draft version of the letter presented by councilors at the meeting.
  • Jupiter Power told me it “welcome[s] any feedback from the community” and King County said in a statement, “We understand the concerns.” PSE told me they had not “received official notification about the formal action by the City Council and we can't comment on something we have not received.”
  • This degree of on-the-ground frustration will be challenging for any higher-level decision maker in Washington State to ignore. I’d argue the entire storage sector should be watching closely.

2. Prince Williams County, Virginia – It was a big week for data center troubles. Let’s start with Data Center Alley, which started to show cracks this week as data center developer Compass announced it was pulling out of the controversial Digital Gateway mega-project.

Keep reading...Show less
Yellow
Q&A

Is the Left Making a ‘Massive Strategic Blunder’ on Data Centers?

A conversation with Holly Jean Buck, author of a buzzy story about Bernie Sanders’ proposal for a national data center moratorium.

Holly Jean Buck.
Heatmap Illustration

This week’s conversation is with Holly Jean Buck, an associate professor at the University of Buffalo and former official in the Energy Department’s Office of Fossil Energy and Carbon Management. Buck got into the thicket of the data center siting debate this past week after authoring a polemic epistemology of sorts in Jacobin arguing against a national data center ban. In the piece, she called a moratorium on AI data centers “a massive strategic blunder for the left, and we should think through the global justice implications and follow-on effects.” It argued that environmental and climate activists would be better suited not courting a left-right coalition that doesn’t seem to have shared goals in the long term.

Her article was praised by more Abundance-leaning thinkers like Matthew Yglesias and pilloried by some of the more influential people in the anti-data center organizing space, such as Ben Inskeep of Citizens Action Coalition of Indiana. So I wanted to chat with her about the discourse around her piece. She humbly obliged.

Keep reading...Show less
Yellow