The Fight

Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Spotlight

Trump’s Onshore Wind Pause Is Still On

Six months in, federal agencies are still refusing to grant crucial permits to wind developers.

Donald Trump and a wind turbine.
Heatmap Illustration/Getty Images

Federal agencies are still refusing to process permit applications for onshore wind energy facilities nearly six months into the Trump administration, putting billions in energy infrastructure investments at risk.

On Trump’s first day in office, he issued two executive orders threatening the wind energy industry – one halting solar and wind approvals for 60 days and another commanding agencies to “not issue new or renewed approvals, rights of way, permits, leases or loans” for all wind projects until the completion of a new governmental review of the entire industry. As we were first to report, the solar pause was lifted in March and multiple solar projects have since been approved by the Bureau of Land Management. In addition, I learned in March that at least some transmission for wind farms sited on private lands may have a shot at getting federal permits, so it was unclear if some arms of the government might let wind projects proceed.

However, I have learned that the wind industry’s worst fears are indeed coming to pass. The Fish and Wildlife Service, which is responsible for approving any activity impacting endangered birds, and the U.S. Army Corps of Engineers, tasked with greenlighting construction in federal wetlands, have simply stopped processing wind project permit applications after Trump’s orders – and the freeze appears immovable, unless something changes.

According to filings submitted to federal court Monday under penalty of perjury by Alliance for Clean Energy New York, at least three wind projects in the Empire State – Terra-Gen’s Prattsburgh Wind, Invenergy’s Canisteo Wind, and Apex’s Heritage Wind – have been unable to get the Army Corps or Fish and Wildlife Service to continue processing their permitting applications. In the filings, ACE NY states that land-based wind projects “cannot simply be put on a shelf for a few years until such time as the federal government may choose to resume permit review and issuance,” because “land leases expire, local permits and agreements expire, and as a result, the project must be terminated.”

While ACE NY’s filings discuss only these projects in New York, they describe the impacts as indicative of the national industry’s experience, and ACE NY’s executive director Marguerite Wells told me it is her understanding “that this is happening nationwide.”

“I can confirm that developers have conveyed to me that [the] Army Corps has stopped processing their applications specifically citing the wind ban,” Wells wrote in an email. “As I have understood it, the initial freeze covered both wind and solar projects, but the freeze was lifted for solar projects and not for wind projects.”

Lots of attention has been paid to Trump’s attacks on offshore wind, because those projects are sited entirely in federal waters. But while wind projects sited on private lands can hypothetically escape a federal review and keep sailing on through to operation, wind turbines are just so large in size that it’s hard to imagine that bird protection laws can’t apply to most of them. And that doesn’t account for wetlands, which seem to be now bedeviling multiple wind developers.

This means there’s an enormous economic risk in a six-month permitting pause, beyond impacts to future energy generation. The ACE NY filings state the impacts to New York alone represent more than $2 billion in capital investments, just in the land-based wind project pipeline, and there’s significant reason to believe other states are also experiencing similar risks. In a legal filing submitted by Democratic states challenging the executive order targeting wind, attorneys general listed at least three wind projects in Arizona – RWE’s Forged Ethic, AES’s West Camp, and Repsol’s Lava Run – as examples that may require approval from the federal government under the Bald and Golden Eagle Protection Act. As I’ve previously written, this is the same law that bird conservation advocates in Wyoming want Trump to use to reject wind proposals in their state, too.

The Fish and Wildlife Service and Army Corps of Engineers declined to comment after this story’s publication due to litigation on the matter. I also reached out to the developers involved in these projects to inquire about their commitments to these projects in light of the permitting pause. We’ll let you know if we hear back from them.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

Judge, Siding With Trump, Saves Solar From NEPA

And more on the week’s biggest conflicts around renewable energy projects.

The United States.
Heatmap Illustration/Getty Images

1. Jackson County, Kansas – A judge has rejected a Hail Mary lawsuit to kill a single solar farm over it benefiting from the Inflation Reduction Act, siding with arguments from a somewhat unexpected source — the Trump administration’s Justice Department — which argued that projects qualifying for tax credits do not require federal environmental reviews.

  • We previously reported that this lawsuit filed by frustrated Kansans targeted implementation of the IRA when it first was filed in February. That was true then, but afterwards an amended complaint was filed that focused entirely on the solar farm at the heart of the case: NextEra’s Jeffrey Solar. The case focuses now on whether Jeffrey benefiting from IRA credits means it should’ve gotten reviewed under the National Environmental Policy Act.
  • Perhaps surprisingly to some, the Trump Justice Department argued against these NEPA reviews – a posture that jibes with the administration’s approach to streamlining the overall environmental analysis process but works in favor of companies using IRA credits.
  • In a ruling that came down on Tuesday, District Judge Holly Teeter ruled the landowners lacked standing to sue because “there is a mismatch between their environmental concerns tied to construction of the Jeffrey Solar Project and the tax credits and regulations,” and they did not “plausibly allege the substantial federal control and responsibility necessary to trigger NEPA review.”
  • “Plaintiffs’ claims, arguments, and requested relief have been difficult to analyze,” Teeter wrote in her opinion. “They are trying to use the procedural requirements of NEPA as a roadblock because they do not like what Congress has chosen to incentivize and what regulations Jackson County is considering. But those challenges must be made to the legislative branch, not to the judiciary.”

2. Portage County, Wisconsin – The largest solar project in the Badger State is now one step closer to construction after settling with environmentalists concerned about impacts to the Greater Prairie Chicken, an imperiled bird species beloved in wildlife conservation circles.

Keep reading...Show less
Yellow
Spotlight

Renewables Swept Up in Data Center Backlash

Just look at Virginia.

A data center.
Heatmap Illustration/Getty Images

Solar and wind projects are getting swept up in the blowback to data center construction, presenting a risk to renewable energy companies who are hoping to ride the rise of AI in an otherwise difficult moment for the industry.

The American data center boom is going to demand an enormous amount of electricity and renewables developers believe much of it will come from solar and wind. But while these types of energy generation may be more easily constructed than, say, a fossil power plant, it doesn’t necessarily mean a connection to a data center will make a renewable project more popular. Not to mention data centers in rural areas face complaints that overlap with prominent arguments against solar and wind – like noise and impacts to water and farmland – which is leading to unfavorable outcomes for renewable energy developers more broadly when a community turns against a data center.

Keep reading...Show less
Yellow
Q&A

How the Wind Industry Can Fight Back

A conversation with Chris Moyer of Echo Communications

The Q&A subject.
Heatmap Illustration

Today’s conversation is with Chris Moyer of Echo Communications, a D.C.-based communications firm that focuses on defending zero- and low-carbon energy and federal investments in climate action. Moyer, a veteran communications adviser who previously worked on Capitol Hill, has some hot takes as of late about how he believes industry and political leaders have in his view failed to properly rebut attacks on solar and wind energy, in addition to the Inflation Reduction Act. On Tuesday he sent an email blast out to his listserv – which I am on – that boldly declared: “The Wind Industry’s Strategy is Failing.”

Of course after getting that email, it shouldn’t surprise readers of The Fight to hear I had to understand what he meant by that, and share it with all of you. So here goes. The following conversation has been abridged and lightly edited for clarity.

Keep reading...Show less
Yellow