Scoop: Giant Wind Farm Off New Jersey Coast Is Getting Killed

Leading Light can’t move forward, a legal counsel wrote to state regulators.

A wind turbine and New Jersey.
Heatmap Illustration/Getty Images, Library of Congress

Another offshore wind project on the East Coast is being quietly killed.

Legal counsel for the Leading Light Wind offshore project filed a letter on Nov. 7 to the New Jersey Board of Public Utilities informing the regulator it no longer sees any way to complete construction and wants to pull the plug.

“The Board is well aware that the offshore wind industry has experienced economic and regulatory conditions that have made the development of new offshore wind projects extremely difficult,” counsel Colleen Foley wrote in the letter, which was reviewed by Heatmap News. “Like many other industry participants, the Company has faced a series of obstacles in the development of the LLW Project including supply chain, equipment and vendor challenges as well as changing regulatory requirements, to name but a few of the issues the Company has confronted.”

Leading Light was going to be built about 35 miles off the coast of New Jersey. It was awarded a renewable energy certificate from the state in January 2024 and was expected to provide roughly 2.4 gigawatts of electricity to the grid, which would have made it one of the largest renewable energy projects in the country and enough, the developers said, to power a million homes.

That certificate, known as an OREC, came with state financial assistance but also required developers Invenergy and energyRe to meet specific project milestones. Yet in addition to facing supply chain issues both companies had been unable to pursue federal permitting because of the Trump administration’s policy on offshore wind. And for months, they had submitted extension after extension to filing a motion binding it legally to complete construction of the project.

But now Leading Light is dead for the foreseeable future. “The company regrets this decision but does not see a pathway forward for the LLW Project on this OREC award and looks forward to the future for possible solicitations,” Foley stated.

This means New Jersey’s offshore wind horizons are incredibly bleak, especially after Shell dumped its stake in the defunct Atlantic Shores offshore wind project last month. Almost all of New Jersey’s offshore wind contracts have now fallen apart, including those for the Ocean Wind, and there is little chance of Attentive Energy receiving federal permits under the current administration.

Only one project is now set to be operational off the New Jersey coast: Empire Wind. But it’s unclear if Empire will ever provide electrons to New Jersey itself since its only contract is with New York regulators. (It remains to be seen whether Empire’s developer, Equinor, will bid into New Jersey’s markets for the project’s second phase.)

It’s also important to consider the timing. On Nov. 4, New Jersey voters were swept up in a blue wave – but one that didn’t really hit many coastal areas, where a large majority of voters remained in the GOP camp. Republican gubernatorial candidate Jack Ciattarelli focused enormously on fighting offshore wind during his campaign, going so far as to sell anti-wind merch. So one can imagine a world where the coastline was part of a blue wave and an offshore wind developer wouldn’t immediately pull out of the state, but that’s not a world we live in.

When reached for comment on whether the project might still be built, Invenergy simply said, “Please refer to the filing.”

Editor’s note: This story has been updated to reflect comment from Invenergy and clarify Attentive Energy’s current status.

Emily Pontecorvo contributed to this article.

Blue

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Energy

Exclusive: Japan’s Tiny Nuclear Reactors Are Headed to Texas

The fourth-generation gas-cooled reactor company ZettaJoule is setting up shop at an unnamed university.

A Texas sign at a ZettaJoule facility.
Heatmap Illustration/Getty Images, ZettaJoule

The appeal of next-generation nuclear technology is simple. Unlike the vast majority of existing reactors that use water, so-called fourth-generation units use coolants such as molten salt, liquid metal, or gases that can withstand intense heat such as helium. That allows the machines to reach and maintain the high temperatures necessary to decarbonize industrial processes, which currently only fossil fuels are able to reach.

But the execution requirements of these advanced reactors are complex, making skepticism easy to understand. While the U.S., Germany, and other countries experimented with fourth-generation reactors in earlier decades, there is only one commercial unit in operation today. That’s in China, arguably the leader in advanced nuclear, which hooked up a demonstration model of a high-temperature gas-cooled reactor to its grid two years ago, and just approved building another project in September.

Keep reading...Show less
Blue
Spotlight

The 5 Fights to Watch in 2026

Spoiler: A lot of them are about data centers.

Data centers and clean energy.
Heatmap Illustration/Getty Images

It’s now clear that 2026 will be big for American energy, but it’s going to be incredibly tense.

Over the past 365 days, we at The Fight have closely monitored numerous conflicts over siting and permitting for renewable energy and battery storage projects. As we’ve done so, the data center boom has come into full view, igniting a tinderbox of resentment over land use, local governance and, well, lots more. The future of the U.S. economy and the energy grid may well ride on the outcomes of the very same city council and board of commissioners meetings I’ve been reporting on every day. It’s a scary yet exciting prospect.

Keep reading...Show less
Yellow
Hotspots

A Texas Data Center Dispute Turns Tawdry

Plus a resolution for Vineyard Wind and more of the week’s big renewables fights.

The United States.
Heatmap Illustration/Getty Images

1. Hopkins County, Texas – A Dallas-area data center fight pitting developer Vistra against Texas attorney general Ken Paxton has exploded into a full-blown political controversy as the power company now argues the project’s developer had an improper romance with a city official for the host community.

  • For those who weren’t around for the first go, here’s the low-down: The Dallas ex-urb of Sulphur Springs is welcoming a data center project proposed by a relatively new firm, MSB Global. But the land – a former coal plant site – is held by Vistra, which acquired the property in a deal intended for remediating the site. After the city approved the project, Vistra refused to allow construction on the land, so Sulphur Springs sued, and in its bid to win the case, the city received support from Texas attorney general Ken Paxton, whose office then opened an antitrust investigation into the power company’s land holdings.
  • Since we first reported this news, the lawsuit has escalated. Vistra’s attorneys have requested Sulphur Springs’ attorney be removed from the court proceedings because, according to screenshots of lengthy social media posts submitted to the court, the city itself has confirmed that the attorney dated a senior executive for MSB Global as recently as the winter of 2024.
  • In a letter dated December 10, posted online by activists fighting the data center, Vistra’s attorneys now argue the relationship is what led to the data center coming to the city in the first place, and that the attorney cannot argue on behalf of the city because they’ll be a fact witness who may need to provide testimony in the case: “These allegations make awareness of negotiations surrounding the deed and the City’s subsequent conduct post-transaction, including any purported ‘reliance’ on Vistra Parties’ actions and omissions, relevant.”
  • I have not heard back from MSB Global or Sulphur Springs about this case, but if I do, you’ll be hearing about it.

2. La Plata County, Colorado – This county has just voted to extend its moratorium on battery energy storage facilities over fire fears.

Keep reading...Show less