Hotspots

The Data Center Most Likely to Get Investigated by a Democratic Congress

And more of the week’s top news around project fights.

Map of data center and renewable energy fights.
Heatmap Illustration

1. Richland Township, Louisiana - The Meta Hyperion project is suddenly now a central focus of activists and media coverage, just as it is seeking environmental permits for a key gas pipeline.

  • A number of painful investigations about Hyperion published in the last week: a New York Times profile of the local negotiations surrounding the deal that involved interviews with more than 40 people, painting the entire development as secretive. Then came an article from States Newsroom’s Louisiana affiliate claiming Governor Jeff Landry’s staff signed more than 100 NDAs, including some with Meta. Environmental advocates are trying to marshal up more public opposition to the project; on Monday, Earthjustice and advocates they’re working with on the ground in the Bayou are holding a press conference about Hyperion.
  • Why all the attention now? For starters, the state regulatory commission is considering whether to approve more gas plants at the project site. In addition, a Federal Register notice published last week disclosed ETC Tiger filed paperwork with the Federal Regulatory Energy Commission to get authorization for a gas pipeline that’ll pump roughly 1 million dekatherms per day to Hyperion. (A single dekatherm is a common measurement for gas transport volume equal to about 1,000,000 BTUs, so you do the math on how massive that pipeline is going to be.)
  • Louisiana is a hot bed for environmental justice advocacy because of Cancer Alley and a long legacy of offshore oil and gas development. I expect that as we saw under Trump 1.0, this amount of media coverage will lead to this project becoming an oversight topic in Congress, especially given the likelihood of prolonged federal review.

2. Memphis, Tennessee – Hyperion won’t be the first data centers that House Democrats go after if they retake the lower chamber in Congress though – that looks like it’ll be xAI’s Colossus projects. Congrats, Elon!

  • House Energy and Commerce Ranking Member Frank Pallone sent a letter to SpaceXAI this week “demanding answers” about the company’s two data centers in the Memphis metro region. As you may be well aware, the facilities are subject to a headline-grabbing lawsuit from the ACLU alleging significant Clean Air Act violations stemming from diesel gas operation without proper permits. The Trump administration has intervened in the case arguing these facilities are necessary for national security reasons so they didn’t need permits.
  • The oversight letter makes it plain what Pallone is up to, requesting SpaceXAI provide “all communications and records relating to Colossus 1 and Colossus 2” between company employees and any government officials “including the White House.” Plainly, if Democrats retake the House in November, we’ll likely get a big congressional probe into the federal government’s handling of the data centers.
  • One of the primary voices fighting those projects is also running for Congress this year. State Rep. Justin Pearson is on the ballot Aug. 6 in his Memphis area district’s Democratic congressional primaries. He’s endorsed by major environmental groups and polling ahead in the race. If he wins, all the more reason for Democrats to go for Elon’s jugular early.

3. Clark and Nye Counties, Nevada – The federal government’s decision to use an environmental review for a solar farm on a data center instead, which I scooped earlier this week, quickly became a national story. Now the fight against the move is coming into focus.

  • The Center for Biological Diversity and Sierra Club’s legal challenge has begun with an administrative appeal to the Bureau of Land Management. This will then be decided by the Interior Department Board of Land Appeals, where the governing administrative judges are split between appointees from Democratic and Republican administrations. At its core, the appeal hinges on the reused review failing to include any new environmental impacts and an inability for the public to comment. Boulder City will make a similar appeal. I do not know how this will go but it’s entirely possible litigation will follow, whatever decision is made here.
  • As this challenge proceeds, the Bureau of Land Management has begun reviewing a separate solar project overseen by Clearway, the renewables developer behind the solar-farm-for-data-center switch. The Mosey solar project is now scheduled to get its draft environmental impact state in early 2027.

4. Suffolk County, New York – Last but not least, we have to talk about the battery fire mess on Long Island because it’s a disaster in the making.

  • The Suffolk County Water Authority is now suing NextEra and National Grid claiming they have failed to properly contain groundwater contamination from a 2023 fire at a battery plant they oversee in Long Island. Allegedly, these companies fought the fire but let the water drain into the soil – a big no no. (Both companies deny any wrongdoing.)
  • Unfortunately for the battery storage industry, the project is in Hauppauge – hometown of EPA administrator Lee Zeldin, who visited late last year to rail against future BESS facilities coming to town. If I was working with a battery developer right now, I’d be watching to see if this scene becomes a new Trumpian boogeyman for the MAGA crowd.

5. Montgomery County, Maryland – Bonus for you: my home county just instituted an 18-month moratorium on new data centers. I don’t really have much to add except, if the backlash has come to my neighborhood it’ll probably hit yours sooner rather than later.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

A Big Battery Relief in New York

And more of the week’s top news around project fights.

The United States.
Heatmap Illustration/Getty Images

1. Suffolk County, New York – Rarely do I get to say battery fire fears can be quelched but we have a very good example brewing in the Empire State.

  • On September 11, New York state regulators did a Friday News Dump: The Department of Environmental Conservation confirmed a large PFAS pollution site in East Hampton was explicitly tied to fighting a battery storage site fire. The investigation began after PFAS chemicals, known as “forever chemicals,” were detected in drinking water wells.
  • Investigators will still have to produce a final report, but in their bulletin confirming the pollution source, the agency said it is now working with state energy and fire officials to avoid a specific chemical fire suppression system identified as a potential culprit known as Novec 1230. “The investigation points to the fire suppression system, not battery storage, as a [PFAS] source,” the bulletin states, adding this system wasn’t used in other recent fires at BESS facilities.This defuses what was poised to be a new PR problem for the battery storage sector in a state where local moratoria and restrictive ordinances have become increasingly common.

2. Loudon County, Virginia – I can’t believe it: Data Center Alley is going to enact a moratorium.

Keep reading...Show less
Yellow
Q&A

The Case for a Data Center Dividend

A conversation with Sam Lyman of the Bitcoin Policy Institute.

The Bitcoin Policy Institute’s Sam Lyman.
Heatmap Illustration

This week’s conversation is with Sam Lyman, head of research at the Bitcoin Policy Institute. Originally focused on cryptocurrency, Lyman’s organization has expanded to policy and messaging development around data centers, most notably providing research many AI boosters cite to claim foreign influence is driving opposition to new hyperscale projects. Last week, the think tank released a new report calling for a novel solution to the data center permitting bottleneck: direct cash payments from data center projects to individuals involved with building them, as well as residents nearby facilities once they’re operating.

I reached out to BPI and asked for a chat with Lyman about the data center dividend proposal. I also tried to get to the bottom of where this increasingly relevant think tank stands on the general idea of a national data center law. The conversation was immensely informative. So here it is, in a lightly abridged and edited format.

Keep reading...Show less
Yellow
Spotlight

Trump Keeps Wind Farms Waiting Despite Court Ruling

The administration told a federal court that it has a “new analytical methodology,” hence the continued delays.

Trump measuring wind turbines.
Heatmap Illustration/Getty Images

A federal judge ruled in early August that the Trump administration’s freeze on vertical height clearances for wind turbines was likely illegal. More than a month later nearly all of the wind energy projects remain on pause, as federal officials add new red tape that industry representatives say runs afoul of the court’s edict.

Let’s catch-up quickly on the American wind sector’s existential dilemma: the federal government has control over airspace higher than 200 feet from the ground and wind farm turbines essentially always enter that sphere of control. For at least a year and a half, the Trump administration through the Department of Defense and the Federal Aviation Administration has slowly gummed up what industry and former government officials have said was once a rote, benign bureaucratic process for ensuring turbine rotation didn’t interfere with flight patterns or radar at nearby airports.

Keep reading...Show less