Q&A

Permitting on Federal Land Has Long Been a Headache

A conversation with Elizabeth McCarthy of the Breakthrough Institute.

Elizabeth McCarthy.
Heatmap Illustration/The Breakthrough Institute

This week’s conversation is with Elizabeth McCarthy of the Breakthrough Institute. Elizabeth was one of several researchers involved in a comprehensive review of a decade of energy project litigation – between 2013 and 2022 – under the National Environment Policy Act. Notably, the review – which Breakthrough released a few weeks ago – found that a lot of energy projects get tied up in NEPA litigation. While she and her colleagues ultimately found fossil fuels are more vulnerable to this problem than renewables, the entire sector has a common enemy: difficulty of developing on federal lands because of NEPA. So I called her up this week to chat about what this research found.

The following conversation was lightly edited for clarity.

So why are you so fixated on NEPA?

Personally and institutionally, [Breakthrough is] curious about all regulatory policy – land use, environmental regulatory policy – and we see NEPA as the thing that connects them all. If we understand how that’s functioning at a high level, we can start to pull at the strings of other players. So, we wanted to understand the barrier that touches the most projects.

What aspects of zero-carbon energy generation are most affected by NEPA?

Anything with a federal nexus that doesn’t include tax credits. Solar and wind that is on federal land is subject to a NEPA review, and anything that is linear infrastructure – transmission often has to go through multiple NEPA reviews. We don’t see a ton of transmission being litigated over on our end, but we think that is a sign NEPA is such a known obstacle that no one even wants to touch a transmission line that’ll go through 14 years of review, so there’s this unknown graveyard of transmission that wasn’t even planned.

In your report, you noted there was a relatively small number of zero-carbon energy projects in your database of NEPA cases. Is solar and wind just being developed more frequently on private land, so there’s less of these sorts of conflicts?

Precisely. The states that are the most powered by wind or create the most wind energy are Texas and Iowa, and those are bypassing the national federal environmental review process [with private land], in addition to not having their own state requirements, so it’s easier to build projects.

What would you tell a solar or wind developer about your research?

This is confirming a lot of things they may have already instinctually known or believed to be true, which is that NEPA and filling out an environmental impact statement takes a really long time and is likely to be litigated over. If you’re a developer who can’t avoid putting your energy project on federal land, you may just want to avoid moving forward with it – the cost may outweigh whatever revenue you could get from that project because you can’t know how much money you’ll have to pour into it.

Huh. Sounds like everything is working well. I do think your work identifies a clear risk in developing on federal lands, which is baked into the marketplace now given the pause on permits for renewables on federal lands.

Yeah. And if you think about where the best places would be to put these technologies? It is on federal lands. The West is way more federal land than anywhere else in the county. Nevada is a great place to put solar — there’s a lot of sun. But we’re not going to put anything there if we can’t put anything there.

What’s the remedy?

We propose a set of policy suggestions. We think the judicial review process could be sped along or not be as burdensome. Our research most obviously points to shortening the statute of limitations under the Administrative Procedures Act from six years to six months, because a great deal of the projects we reviewed made it in that time, so you’d see more cases in good faith as opposed to someone waiting six years waiting to challenge it.

We also think engaging stakeholders much earlier in the process would help.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

Washington Wants Data Centers to Bring Their Own Clean Energy

The state is poised to join a chorus of states with BYO energy policies.

Washington State and a data center.
Heatmap Illustration/Getty Images

With the backlash to data center development growing around the country, some states are launching a preemptive strike to shield residents from higher energy costs and environmental impacts.

A bill wending through the Washington State legislature would require data centers to pick up the tab for all of the costs associated with connecting them to the grid. It echoes laws passed in Oregon and Minnesota last year, and others currently under consideration in Florida, Georgia, Illinois, and Delaware.

Keep reading...Show less
Yellow
Hotspots

Michigan’s Data Center Bans Are Getting Longer

Plus more of the week’s top fights in renewable energy.

The United States.
Heatmap Illustration/Getty Images

1. Kent County, Michigan — Yet another Michigan municipality has banned data centers — for the second time in just a few months.

  • Solon Township, a rural community north of Grand Rapids, passed a six-month moratorium on Monday after residents learned that a consulting agency that works with data center developers was scouting sites in the area. The decision extended a previous 90-day ban.
  • Solon is at least the tenth township in Michigan to enact a moratorium on data center development in the past three months. The state has seen a surge in development since Governor Gretchen Whitmer signed a law exempting data centers from sales and use taxes last April, and a number of projects — such as the 1,400-megawatt, $7 billion behemoth planned by Oracle and OpenAI in Washtenaw County — have become local political flashpoints.
  • Some communities have passed moratoria on data center development even without receiving any interest from developers. In Romeo, for instance, residents urged the village’s board of trustees to pass a moratorium after a project was proposed for neighboring Washington Township. The board assented and passed a one-year moratorium in late January.

2. Pima County, Arizona — Opposition groups submitted twice the required number of signatures in a petition to put a rezoning proposal for a $3.6 billion data center project on the ballot in November.

Keep reading...Show less
Yellow
Q&A

Could Blocking Data Centers Raise Electricity Prices?

A conversation with Advanced Energy United’s Trish Demeter about a new report with Synapse Energy Economics.

Trish Demeter.
Heatmap Illustration

This week’s conversation is with Trish Demeter, a senior managing director at Advanced Energy United, a national trade group representing energy and transportation businesses. I spoke with Demeter about the group’s new report, produced by Synapse Energy Economics, which found that failing to address local moratoria and restrictive siting ordinances in Indiana could hinder efforts to reduce electricity prices in the state. Given Indiana is one of the fastest growing hubs for data center development, I wanted to talk about what policymakers could do to address this problem — and what it could mean for the rest of the country. Our conversation was edited for length and clarity.

Can you walk readers through what you found in your report on energy development in Indiana?

Keep reading...Show less
Yellow