This week’s conversation is with Ryan Norris, senior fellow for energy policy at the Abundance Institute. The libertarian-leaning institute — whose name cleverly shortens to AI — is a new-ish entity with increasing relevance in energy and tech spaces. As Norris and I discussed, it’s starting to help shape policy on data center development and the generation that’ll power it all, especially in Republican circles. Norris himself previously worked with Americans for Prosperity, a right-wing political organization. I reached out to him and asked if we could chat because I wanted to know more about the institute’s work within the energy space. He wound up saying a lot more than I expected. So let’s dive into it.

The following conversation was lightly edited and abridged for clarity.

So let’s start with what you’re working on. What’s on your desk these days?

Here at Abundance, we sit at the juncture of emerging technology and the energy they need to bring that new technology to bear to impact life positively. We are always in a constant state of learning and researching what the latest thoughts and feelings are around certain policies, particularly around AI and data centers, and then energy technology. How do they feel about nuclear? Geothermal? Solar and battery arrays?

A lot of what I’m working on is Project Gigawatt, a body of policy that fits into permitting, generation, the grid, transmission, and then market and demand. Policies that we believe will generate more, transmit more, and as much of a free market approach as possible. Knowing that a lot of states have regulated utilities, when the state utility can’t produce what the state can potentially actually generate or would need to in order to accommodate large loads, we think there needs to be other opportunities to either bring that power or purchase it in a different way.

When it comes to this policy set, how are you taking into account the intensifying backlash to data center and AI infrastructure, as well as the energy attached to it?

As everyone can sense, things are moving rapidly, and there is a natural inclination to question how fast we’re going. I think these concerns need to be addressed seriously and respectfully. You can’t just say negative things about people who care about water quality or impacts to their local economies. Those are valid. I’ve lived through those. I come from a rural place in Arkansas that had oil and gas plays. And I’ve seen there needs to be conversations with people living in those areas too.

We cannot discount the backlash. When you take the legitimate concerns and pair them with the opportunities coming, I think there’s actually a chance to set up win-win solutions. It shouldn’t be a win-lose scenario here. They have skepticism about AI in the short and long term — that’s a natural inclination and not a negative, per se. But educating people and policymakers about data centers, that’s important.

What is your approach to the rise in land use regulation around data centers and energy infrastructure, moratoria and restrictive ordinances?

As much as possible, you want the infrastructure and cost allocation to be borne by the business causing it. That’s the motivation behind a lot of colocation partnerships happening right now, like the Kilby project in Texas, with natural gas powering a Microsoft hyperscale.

To us, it’s about setting up the opportunity for private property owners to sell to those hyperscalers and those generating the energy. Setting up situations where you’re not stopping people from benefiting. A lot of the “bring your own power” concept, we really like that. Maybe having it where power purchase agreements are more in the mix, things along those lines. That’s where I see things.

The energy increases to our utility bills, people are concerned about it, and that’s a bread and butter issue. That’s the approach: We know we need grid upgrades and want to have the most cost effective versions of those as possible, but you want those needing the power paying for it and not putting it on the backs of residents.

I’m curious, what’s you and your organization’s approach to the rise of gas infrastructure built for AI and the potential impacts that could have on climate change?

I don’t discount the issue of climate change.

Let’s say we’re not able to decarbonize enough to reverse the effects of warmth. We know we’ll have to create energy. We know we have other options for energy that need to be in the mix — more nuclear, which now even some of those who are climate-minded understand is an abundant energy source. I’m also interested in new technologies in geothermal where it can be viable in more places than we thought. You can drill down and tap hot rocks, a basin of water, turn a turbine, and that’s more acceptable for those who care about the climate. And states are looking at it, including my state of Arkansas. I bring these up because I also care about sources that provide firm, consistently available power.

We attended the American Legislative Exchange Council, and one of the things we do, we’re voting members on the energy, environment, and agriculture task force. We’re pro letting the market decide what they need. So we took opposite stances from what people typically consider normal standards on the center-right about banning “net-zero” for local governments. It did pass as model legislation but if we believe “all of the above” is the approach, we also want to be principally correct to ourselves that it doesn’t mean banning wind or solar where it’s viable.

My last question: What’s your thought on the future of politics around AI infrastructure and energy generation for it?

There’s definitely headwinds to those in that industry. I think the sense is, they understood what they wanted and didn’t see any barriers to the way they’d go about it. That’s causing ripple effects in our politics at the local level, including here in Arkansas, where I live in Pulaski County. I think it’ll stay important particularly as it connects to affordability concerns around energy. We know we need more energy, but we want it at the lowest cost possible to the residential side. If people are feeling like data centers are driving the demand for the energy and aren’t on the hook for it, that’s going to position them to be more negative towards the technology.

But we have to expand the conversation. There are folks out there talking about 3D printing for homes, using proprietary cement mixes to build homes in a few weeks when they took months. Agriculture is using robotics in lieu of pesticides and herbicides. Advanced manufacturing is improving the quality of medical equipment. No one completely understands the end goal of new energy to fuel the data centers and AI to get us where there’s a net benefit to them.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

A Big Battery Relief in New York

And more of the week’s top news around project fights.

•
The United States.
Heatmap Illustration/Getty Images

1. Suffolk County, New York – Rarely do I get to say battery fire fears can be quelched but we have a very good example brewing in the Empire State.

  • On September 11, New York state regulators did a Friday News Dump: The Department of Environmental Conservation confirmed a large PFAS pollution site in East Hampton was explicitly tied to fighting a battery storage site fire. The investigation began after PFAS chemicals, known as “forever chemicals,” were detected in drinking water wells.
  • Investigators will still have to produce a final report, but in their bulletin confirming the pollution source, the agency said it is now working with state energy and fire officials to avoid a specific chemical fire suppression system identified as a potential culprit known as Novec 1230. “The investigation points to the fire suppression system, not battery storage, as a [PFAS] source,” the bulletin states, adding this system wasn’t used in other recent fires at BESS facilities.This defuses what was poised to be a new PR problem for the battery storage sector in a state where local moratoria and restrictive ordinances have become increasingly common.

2. Loudon County, Virginia – I can’t believe it: Data Center Alley is going to enact a moratorium.

Keep reading...Show less
Yellow
Q&A

The Case for a Data Center Dividend

A conversation with Sam Lyman of the Bitcoin Policy Institute.

•
The Bitcoin Policy Institute’s Sam Lyman.
Heatmap Illustration

This week’s conversation is with Sam Lyman, head of research at the Bitcoin Policy Institute. Originally focused on cryptocurrency, Lyman’s organization has expanded to policy and messaging development around data centers, most notably providing research many AI boosters cite to claim foreign influence is driving opposition to new hyperscale projects. Last week, the think tank released a new report calling for a novel solution to the data center permitting bottleneck: direct cash payments from data center projects to individuals involved with building them, as well as residents nearby facilities once they’re operating.

I reached out to BPI and asked for a chat with Lyman about the data center dividend proposal. I also tried to get to the bottom of where this increasingly relevant think tank stands on the general idea of a national data center law. The conversation was immensely informative. So here it is, in a lightly abridged and edited format.

Keep reading...Show less
Yellow
Spotlight

Trump Keeps Wind Farms Waiting Despite Court Ruling

The administration told a federal court that it has a “new analytical methodology,” hence the continued delays.

•
Trump measuring wind turbines.
Heatmap Illustration/Getty Images

A federal judge ruled in early August that the Trump administration’s freeze on vertical height clearances for wind turbines was likely illegal. More than a month later nearly all of the wind energy projects remain on pause, as federal officials add new red tape that industry representatives say runs afoul of the court’s edict.

Let’s catch-up quickly on the American wind sector’s existential dilemma: the federal government has control over airspace higher than 200 feet from the ground and wind farm turbines essentially always enter that sphere of control. For at least a year and a half, the Trump administration through the Department of Defense and the Federal Aviation Administration has slowly gummed up what industry and former government officials have said was once a rote, benign bureaucratic process for ensuring turbine rotation didn’t interfere with flight patterns or radar at nearby airports.

Keep reading...Show less