The Fight

Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Spotlight

‘Enhanced’ Reviews Await Power Lines Tied to Solar and Wind, BLM Says

Uh oh.

Power lines.
Heatmap Illustration/Getty Images

The Bureau of Land Management says it will be heavily scrutinizing transmission lines if they are expressly necessary to bring solar or wind energy to the power grid.

Since the beginning of July, I’ve been reporting out how the Trump administration has all but halted progress for solar and wind projects on federal lands through a series of orders issued by the Interior Department. But last week, I explained it was unclear whether transmission lines that connect to renewable energy projects would be subject to the permitting freeze. I also identified a major transmission line in Nevada – the north branch of NV Energy’s Greenlink project – as a crucial test case for the future of transmission siting in federal rights-of-way under Trump. Greenlink would cross a litany of federal solar leases and has been promoted as “essential to helping Nevada achieve its de-carbonization goals and increased renewable portfolio standard.”

Well, BLM has now told me Greenlink North will still proceed despite a delay made public shortly after permitting was frozen for renewables, and that the agency still expects to publish the record of decision for the line in September.

This is possible because, as BLM told me, transmission projects that bring solar and wind power to the grid will be subject to heightened scrutiny. In an exclusive statement, BLM press secretary Brian Hires told me via e-mail that a secretarial order choking out solar and wind permitting on federal lands will require “enhanced environmental review for transmission lines only when they are a part of, and necessary for, a wind or solar energy project.”

However, if a transmission project is not expressly tied to wind or solar or is not required for those projects to be constructed… apparently, then it can still get a federal green light. For instance in the case of Greenlink, the project itself is not explicitly tied to any single project, but is kind of like a transmission highway alongside many potential future solar projects. So a power line can get approved if it could one day connect to wind or solar, but the line’s purpose cannot solely be for a wind or solar project.

This is different than, say, lines tied explicitly to connecting a wind or solar project to an existing transmission network. Known as gen-tie lines, these will definitely face hardships with this federal government. This explains why, for example, BLM has yet to approve a gen-tie line for a wind project in Wyoming that would connect the Lucky Star wind project to the grid.

At the same time, it appears projects may be given a wider berth if a line has other reasons for existing, like improving resilience on the existing grid, or can be flexibly used by not just renewables but also fossil energy.

So, the lesson to me is that if you’re trying to build transmission infrastructure across federal property under this administration, you might want to be a little more … vague.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Trump’s Renewable Freeze Is Chilling Climate Tech

A chat with CleanCapital founder Jon Powers.

Jon Powers.
Heatmap Illustration

This week’s conversation is with Jon Powers, founder of the investment firm CleanCapital. I reached out to Powers because I wanted to get a better understanding of how renewable energy investments were shifting one year into the Trump administration. What followed was a candid, detailed look inside the thinking of how the big money in cleantech actually views Trump’s war on renewable energy permitting.

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

Indiana Rejects One Data Center, Welcomes Another

Plus more on the week’s biggest renewables fights.

The United States.
Heatmap Illustration/Getty Images

Shelby County, Indiana – A large data center was rejected late Wednesday southeast of Indianapolis, as the takedown of a major Google campus last year continues to reverberate in the area.

  • Real estate firm Prologis was the loser at the end of a five-hour hearing last night before the planning commission in Shelbyville, a city whose municipal council earlier this week approved a nearly 500-acre land annexation for new data center construction. After hearing from countless Shelbyville residents, the planning commission gave the Prologis data center proposal an “unfavorable” recommendation, meaning it wants the city to ultimately reject the project. (Simpsons fans: maybe they could build the data center in Springfield instead.)
  • This is at least the third data center to be rejected by local officials in four months in Indiana. It comes after Indianapolis’ headline-grabbing decision to turn down a massive Google complex and commissioners in St. Joseph County – in the town of New Carlisle, outside of South Bend – also voted down a data center project.
  • Not all data centers are failing in Indiana, though. In the northwest border community of Hobart, just outside of Chicago, the mayor and city council unanimously approved an $11 billion Amazon data center complex in spite of a similar uproar against development. Hobart Mayor Josh Huddlestun defended the decision in a Facebook post, declaring the deal with Amazon “the largest publicly known upfront cash payment ever for a private development on private land” in the United States.
  • “This comes at a critical time,” Huddlestun wrote, pointing to future lost tax revenue due to a state law cutting property taxes. “Those cuts will significantly reduce revenue for cities across Indiana. We prepared early because we did not want to lay off employees or cut the services you depend on.”

Dane County, Wisconsin – Heading northwest, the QTS data center in DeForest we’ve been tracking is broiling into a major conflict, after activists uncovered controversial emails between the village’s president and the company.

Keep reading...Show less
Yellow
Spotlight

Can the Courts Rescue Renewables?

The offshore wind industry is using the law to fight back against the Trump administration.

Donald Trump, a judge, and renewable energy.
Heatmap Illustration/Getty Images

It’s time for a big renewable energy legal update because Trump’s war on renewable energy projects will soon be decided in the courts.

A flurry of lawsuits were filed around the holidays after the Interior Department issued stop work orders against every offshore wind project under construction, citing a classified military analysis. By my count, at least three developers filed individual suits against these actions: Dominion Energy over the Coastal Virginia offshore wind project, Equinor over Empire Wind in New York, and Orsted over Revolution Wind (for the second time).

Keep reading...Show less
Yellow