‘Enhanced’ Reviews Await Power Lines Tied to Solar and Wind, BLM Says

Uh oh.

Power lines.
Heatmap Illustration/Getty Images

The Bureau of Land Management says it will be heavily scrutinizing transmission lines if they are expressly necessary to bring solar or wind energy to the power grid.

Since the beginning of July, I’ve been reporting out how the Trump administration has all but halted progress for solar and wind projects on federal lands through a series of orders issued by the Interior Department. But last week, I explained it was unclear whether transmission lines that connect to renewable energy projects would be subject to the permitting freeze. I also identified a major transmission line in Nevada – the north branch of NV Energy’s Greenlink project – as a crucial test case for the future of transmission siting in federal rights-of-way under Trump. Greenlink would cross a litany of federal solar leases and has been promoted as “essential to helping Nevada achieve its de-carbonization goals and increased renewable portfolio standard.”

Well, BLM has now told me Greenlink North will still proceed despite a delay made public shortly after permitting was frozen for renewables, and that the agency still expects to publish the record of decision for the line in September.

This is possible because, as BLM told me, transmission projects that bring solar and wind power to the grid will be subject to heightened scrutiny. In an exclusive statement, BLM press secretary Brian Hires told me via e-mail that a secretarial order choking out solar and wind permitting on federal lands will require “enhanced environmental review for transmission lines only when they are a part of, and necessary for, a wind or solar energy project.”

However, if a transmission project is not expressly tied to wind or solar or is not required for those projects to be constructed… apparently, then it can still get a federal green light. For instance in the case of Greenlink, the project itself is not explicitly tied to any single project, but is kind of like a transmission highway alongside many potential future solar projects. So a power line can get approved if it could one day connect to wind or solar, but the line’s purpose cannot solely be for a wind or solar project.

This is different than, say, lines tied explicitly to connecting a wind or solar project to an existing transmission network. Known as gen-tie lines, these will definitely face hardships with this federal government. This explains why, for example, BLM has yet to approve a gen-tie line for a wind project in Wyoming that would connect the Lucky Star wind project to the grid.

At the same time, it appears projects may be given a wider berth if a line has other reasons for existing, like improving resilience on the existing grid, or can be flexibly used by not just renewables but also fossil energy.

So, the lesson to me is that if you’re trying to build transmission infrastructure across federal property under this administration, you might want to be a little more … vague.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

A Permitting U-Turn in Indiana

map of renewable energy and data center conflicts
Heatmap Illustration

1. Marion County, Indiana — State legislators made a U-turn this week in Indiana.

  • The Indiana House passed a bill on Tuesday that would have allowed solar projects, data centers, and oil refineries on “poor soil.” Critics lambasted the bill for language they said was too vague and would wrest control from local governments, and on Thursday, local media reported that the legislation as written had effectively died.
  • Had it passed, the new rules would have brought Indiana’s solar permitting process closer to that of neighboring Illinois and Michigan, both of which limit the ability of counties and townships to restrict renewable energy projects. According to Heatmap Pro data, local governments in Indiana currently have more than 60 ordinances and moratoriums restricting renewable development on the books, making it one of the most difficult places to build renewable energy in the country.

2. Baldwin County, Alabama — Alabamians are fighting a solar project they say was dropped into their laps without adequate warning.

Keep reading...Show less
Yellow
Q&A

What Data Centers Mean for Local Jobs

A conversation with Emily Pritzkow of Wisconsin Building Trades

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Emily Pritzkow, executive director for the Wisconsin Building Trades, which represents over 40,000 workers at 15 unions, including the International Brotherhood of Electrical Workers, the International Union of Operating Engineers, and the Wisconsin Pipe Trades Association. I wanted to speak with her about the kinds of jobs needed to build and maintain data centers and whether they have a big impact on how communities view a project. Our conversation was edited for length and clarity.

So first of all, how do data centers actually drive employment for your members?

Keep reading...Show less
Yellow
Spotlight

Are Republicans Turning on Data Centers?

The number of data centers opposed in Republican-voting areas has risen 330% over the past six months.

Trump signs and a data center.
Heatmap Illustration/Getty Images

It’s probably an exaggeration to say that there are more alligators than people in Colleton County, South Carolina, but it’s close. A rural swath of the Lowcountry that went for Trump by almost 20%, the “alligator alley” is nearly 10% coastal marshes and wetlands, and is home to one of the largest undeveloped watersheds in the nation. Only 38,600 people — about the population of New York’s Kew Gardens neighborhood — call the county home.

Colleton County could soon have a new landmark, though: South Carolina’s first gigawatt data center project, proposed by Eagle Rock Partners.

Keep reading...Show less