The Fight

Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Spotlight

‘Enhanced’ Reviews Await Power Lines Tied to Solar and Wind, BLM Says

Uh oh.

Power lines.
Heatmap Illustration/Getty Images

The Bureau of Land Management says it will be heavily scrutinizing transmission lines if they are expressly necessary to bring solar or wind energy to the power grid.

Since the beginning of July, I’ve been reporting out how the Trump administration has all but halted progress for solar and wind projects on federal lands through a series of orders issued by the Interior Department. But last week, I explained it was unclear whether transmission lines that connect to renewable energy projects would be subject to the permitting freeze. I also identified a major transmission line in Nevada – the north branch of NV Energy’s Greenlink project – as a crucial test case for the future of transmission siting in federal rights-of-way under Trump. Greenlink would cross a litany of federal solar leases and has been promoted as “essential to helping Nevada achieve its de-carbonization goals and increased renewable portfolio standard.”

Well, BLM has now told me Greenlink North will still proceed despite a delay made public shortly after permitting was frozen for renewables, and that the agency still expects to publish the record of decision for the line in September.

This is possible because, as BLM told me, transmission projects that bring solar and wind power to the grid will be subject to heightened scrutiny. In an exclusive statement, BLM press secretary Brian Hires told me via e-mail that a secretarial order choking out solar and wind permitting on federal lands will require “enhanced environmental review for transmission lines only when they are a part of, and necessary for, a wind or solar energy project.”

However, if a transmission project is not expressly tied to wind or solar or is not required for those projects to be constructed… apparently, then it can still get a federal green light. For instance in the case of Greenlink, the project itself is not explicitly tied to any single project, but is kind of like a transmission highway alongside many potential future solar projects. So a power line can get approved if it could one day connect to wind or solar, but the line’s purpose cannot solely be for a wind or solar project.

This is different than, say, lines tied explicitly to connecting a wind or solar project to an existing transmission network. Known as gen-tie lines, these will definitely face hardships with this federal government. This explains why, for example, BLM has yet to approve a gen-tie line for a wind project in Wyoming that would connect the Lucky Star wind project to the grid.

At the same time, it appears projects may be given a wider berth if a line has other reasons for existing, like improving resilience on the existing grid, or can be flexibly used by not just renewables but also fossil energy.

So, the lesson to me is that if you’re trying to build transmission infrastructure across federal property under this administration, you might want to be a little more … vague.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

Surprise! A Large Solar Farm Just Got Federal Approval

And more on the week’s most important conflicts around renewable energy projects.

The United States.
Heatmap Illustration/Getty Images

1. Lawrence County, Alabama – We now have a rare case of a large solar farm getting federal approval.

  • The Tennessee Valley Authority last week quietly published its record of decision formally approving the 200-megawatt Hillsboro Solar project. The TVA – a quasi-federal independent power agency that delivers electricity across the Southeast – completed the environmental review for the project in June, prior to the federal government’s fresh clampdown on permits for renewables, and declared the project essential to meeting future energy demand.
  • It’s honestly sort of a miracle this was even able to happen. The Trump administration has sought to strongarm the agency into making resource planning decisions in line with the president’s political whims, and has successfully browbeaten the TVA’s board into backing away from certain projects.

2. Virginia Beach, Virginia – It’s time to follow up on the Coastal Virginia offshore wind project.

Keep reading...Show less
Yellow
Q&A

Permitting on Federal Land Has Long Been a Headache

A conversation with Elizabeth McCarthy of the Breakthrough Institute.

Elizabeth McCarthy.
Heatmap Illustration/The Breakthrough Institute

This week’s conversation is with Elizabeth McCarthy of the Breakthrough Institute. Elizabeth was one of several researchers involved in a comprehensive review of a decade of energy project litigation – between 2013 and 2022 – under the National Environment Policy Act. Notably, the review – which Breakthrough released a few weeks ago – found that a lot of energy projects get tied up in NEPA litigation. While she and her colleagues ultimately found fossil fuels are more vulnerable to this problem than renewables, the entire sector has a common enemy: difficulty of developing on federal lands because of NEPA. So I called her up this week to chat about what this research found.

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

Trump Administration to ‘Reconsider’ Approval for MarWin

And more of the week’s most important conflicts around renewable energy.

The United States.
Heatmap Illustration/Getty Images

1. Sussex County, Delaware – The Trump administration has confirmed it will revisit permitting decisions for the MarWin offshore wind project off the coast of Maryland, potentially putting the proposal in jeopardy unless blue states and the courts intervene.

  • Justice Department officials admitted the plans in a paragraph tucked inside a filing submitted to a federal court in Delaware this week in litigation brought by a beach house owner opposed to the offshore wind project.
  • DOJ stated in the filing that more time was “necessary as Interior intends to reconsider its [construction and operations plan] approval” for MarWin, and that it plans to “move” for “voluntary remand of that agency action” in a separate case filed by Ocean City, Maryland against the project.
  • “The outcome of Interior’s reconsideration has the potential to affect the Plaintiff’s claims in this case,” the filing stated. “Continuing to litigate this case before any decision is made in the [Ocean City case] would potentially waste considerable time and resources for both the parties and the Court.” As of today, no new filings have been made in the Ocean City case.

2. Northwest Iowa – Locals fighting a wind project spanning multiple counties in northern Iowa are opposing legislation that purports to make renewable development easier in the state.

Keep reading...Show less
Yellow