‘Enhanced’ Reviews Await Power Lines Tied to Solar and Wind, BLM Says

Uh oh.

Power lines.
Heatmap Illustration/Getty Images

The Bureau of Land Management says it will be heavily scrutinizing transmission lines if they are expressly necessary to bring solar or wind energy to the power grid.

Since the beginning of July, I’ve been reporting out how the Trump administration has all but halted progress for solar and wind projects on federal lands through a series of orders issued by the Interior Department. But last week, I explained it was unclear whether transmission lines that connect to renewable energy projects would be subject to the permitting freeze. I also identified a major transmission line in Nevada – the north branch of NV Energy’s Greenlink project – as a crucial test case for the future of transmission siting in federal rights-of-way under Trump. Greenlink would cross a litany of federal solar leases and has been promoted as “essential to helping Nevada achieve its de-carbonization goals and increased renewable portfolio standard.”

Well, BLM has now told me Greenlink North will still proceed despite a delay made public shortly after permitting was frozen for renewables, and that the agency still expects to publish the record of decision for the line in September.

This is possible because, as BLM told me, transmission projects that bring solar and wind power to the grid will be subject to heightened scrutiny. In an exclusive statement, BLM press secretary Brian Hires told me via e-mail that a secretarial order choking out solar and wind permitting on federal lands will require “enhanced environmental review for transmission lines only when they are a part of, and necessary for, a wind or solar energy project.”

However, if a transmission project is not expressly tied to wind or solar or is not required for those projects to be constructed… apparently, then it can still get a federal green light. For instance in the case of Greenlink, the project itself is not explicitly tied to any single project, but is kind of like a transmission highway alongside many potential future solar projects. So a power line can get approved if it could one day connect to wind or solar, but the line’s purpose cannot solely be for a wind or solar project.

This is different than, say, lines tied explicitly to connecting a wind or solar project to an existing transmission network. Known as gen-tie lines, these will definitely face hardships with this federal government. This explains why, for example, BLM has yet to approve a gen-tie line for a wind project in Wyoming that would connect the Lucky Star wind project to the grid.

At the same time, it appears projects may be given a wider berth if a line has other reasons for existing, like improving resilience on the existing grid, or can be flexibly used by not just renewables but also fossil energy.

So, the lesson to me is that if you’re trying to build transmission infrastructure across federal property under this administration, you might want to be a little more … vague.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Building Transmission Could Lower Electricity Costs

Talking with National Grid’s Matthew Satterwhite about his new report with S&P Global.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Matthew Satterwhite, head of U.S. policy for National Grid. This week National Grid released a report in collaboration with S&P Global I found noteworthy amidst the data center backlash, asserting that building new transmission lines can potentially reduce consumer costs. I reached out asking if we could chat about how this argument leans into the fight over hyperscale infrastructure. I found our conversation illuminating and educational.

The following Q&A was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

The Solar Farm-to-Data Center Switcheroo Hits a Snag

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Clark County, Nevada – The first data center approved on federal lands has hit a legal brick wall.

  • On Monday, the Townsite 2 solar farm-to-data center environmental review swap I’ve previously covered received a stay from the Interior Department’s board of appeals. David Gunter, a Biden appointee, ruled that the Center for Biological Diversity’s appeal of the permit flip was likely to succeed on the merits because a solar farm … is not a data center. Seems logical!
  • As I covered at the time, the Bureau of Land Management approved the environmental review swap claiming that a solar farm and a data center have essentially the same characteristics. It was a bold claim. Both the agency and Townsite said the characteristics would have substantially the same environmental impacts. Gunter shrugged off the claim idea, however, stating that statute requires projects to be both substantially similar and have equally similar impacts under the National Environmental Policy Act.
  • Crucially, Gunter also noted that the federal agency had never done an environmental review of any data centers under NEPA, so there’s not even a proper frame of reference. “BLM has not studied the Townsite data center project, or indeed any other data center project, in any environmental document,” he wrote.

2. Jackson County, Missouri – We have yet another high-profile case of a city councilor losing their job over voting for a data center, and this one’s a doozy.

Keep reading...Show less
Yellow
Spotlight

These 5 States Are Primed for a Data Center Pause

Where temporary moratoria could happen next.

A data center protest.
Heatmap Illustration/Getty Images

Brace yourself for more statewide data center moratoria.

So far there are only two full state-wide blocks on data center permits, in New York and Texas. At least fifteen states have moratorium legislation in the pipeline, but few if any of those bills stand a chance of becoming law in the short term. Here are five states, however, where a broad development pause may gain momentum in the next year or two — and all of them are crucial to watch this November.

Keep reading...Show less