The Environmental Group That Wants to Stop Data Centers

A conversation with Public Citizen’s Deanna Noel.

Deanna Noel.
Heatmap Illustration

This week’s conversation is with Deanna Noel, climate campaigns director for the advocacy group Public Citizen. I reached out to Deanna because last week Public Citizen became one of the first major environmental groups I’ve seen call for localities and states to institute full-on moratoria against any future data center development. The exhortation was part of a broader guide for more progressive policymakers on data centers, but I found this proposal to be an especially radical one as some communities institute data center moratoria that also restrict renewable energy. I wanted to know, how do progressive political organizations talk about data center bans without inadvertently helping opponents of solar and wind projects?

The following conversation was lightly edited for clarity.

Why are you recommending we ban data centers until we have regulations?

The point of us putting this out was to give policymakers a roadmap and a starting point at all levels of government, putting in guardrails to start reeling in Big Tech. Because the reality is they’re writing their own rules with how they’d like to roll out these massive data centers.

A big reason for a moratorium at the state and local level is to put in place requirements to ensure any more development that is happening is not just stepping on local communities, undermining our climate goals, impacting water resources or having adverse societal impacts like incessant noise. Big Tech is often hiding behind non-disclosure agreements and tying the hands of local officials behind NDAs while they’re negotiating deals for their data centers, which then becomes a gag order blocking officials and the public from understanding what is happening. And so our guide set out to provide a policy roadmap and a starting point is to say, let’s put a pause on this.

Do you see any cities or states doing this now? I’m trying to get a better understanding of where this came from.

It’s happening at the local level. There was a moratorium in Prince George’s County [in Maryland], where I live, until a task force can be developed and make sure local residents’ concerns are addressed. In Georgia, localities have done this, too.

The idea on its own is simple: States and localities have the authority and should be the ones to implement these moratoriums that no data centers should go forward until baseline protections are in place. There are many protections we go through in our guide, but No. 1, Big Tech should be forced to pay their way. These are some of the most wealthy corporations on the planet, and yet they’re bending backwards to negotiate deals with local utilities and governments to ensure they’re paying as little as possible for the cost of their power infrastructure. Those costs are being put on ratepayers.

The idea of a moratorium is there’s a tension in a data center buildout without any regulations.

Do you have any concerns about pushing for blanket moratoria on new technological infrastructure? We’re seeing this policy thrown at solar and wind and batteries now. Is there any concern it’ll go from data centers to renewables next in some places?

First off, you’re right, and the Trump administration wants to fast-track an expansion that’ll rely on fossil fuels: coal, oil and gas. We’re in a climate crisis, and we’d be better off if these data centers relied entirely on renewable energy.

It’s incredibly important for policymakers to be clear when they’re setting moratoria that they’re not inadvertently halting clean, cheap energy like wind and solar. This is about the unfettered expansion of the data center industry to feed the AI machine. That’s what the focus needs to be on.

Yes, but there’s also this land use techlash going on, and I’m a little concerned advocacy for a moratorium on data centers will help those fighting to institute moratoria on solar and wind. I’m talking about Ohio and Wisconsin and Iowa. Are you at all concerned about a horseshoe phenomenon here, where people are opposing data centers for the same reasons they’re fighting renewable energy projects? What should folks in the advocacy space do to make sure those things aren’t tethered to one another?

That’s a great question. I think it comes down to clear messaging for the public.

People are opportunistic — they want to get their passion projects no matter what. We as advocates need to consistently message that renewable energy is not only the energy of tomorrow, but of today. It’s where the rest of the world is headed and the U.S. is going backwards under the Trump administration.

The data center issue is separate. Data centers are using way more land – these massive hyperscaler data center campuses – are using more land than solar and wind. We can be creative with those energies in a way we can’t with the data center expansion.

We need to make it absolutely clear: This is about corporate expansion at the expense of everyone else in a way that solar and wind aren’t. Those bring costs down and don’t have anywhere near as much of an environmental impact.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

How the Tech Industry Is Responding to Data Center Backlash

It’s aware of the problem. That doesn’t make it easier to solve.

Data center construction and tech headquarters.
Heatmap Illustration/Getty Images

The data center backlash has metastasized into a full-blown PR crisis, one the tech sector is trying to get out in front of. But it is unclear whether companies are responding effectively enough to avoid a cascading series of local bans and restrictions nationwide.

Our numbers don’t lie: At least 25 data center projects were canceled last year, and nearly 100 projects faced at least some form of opposition, according to Heatmap Pro data. We’ve also recorded more than 60 towns, cities and counties that have enacted some form of moratorium or restrictive ordinance against data center development. We expect these numbers to rise throughout the year, and it won’t be long before the data on data center opposition is rivaling the figures on total wind or solar projects fought in the United States.

Keep reading...Show less
Yellow
Hotspots

More Moratoria in Michigan and Madison, Wisconsin

Plus a storage success near Springfield, Massachusetts, and more of the week’s biggest renewables fights.

The United States.
Heatmap Illustration/Getty Images

1. Sacramento County, California – A large solar farm might go belly-up thanks to a fickle utility and fears of damage to old growth trees.

  • The Sacramento Municipal Utility District has decided to cancel the power purchase agreement for the D.E. Shaw Renewables Coyote Creek agrivoltaics project, which would provide 200 megawatts of power to the regional energy grid. The construction plans include removing thousands of very old trees, resulting in a wide breadth of opposition.
  • The utility district said it was canceling its agreement due to “project uncertainties,” including “schedule delays, environmental impacts, and pending litigation.” It also mentioned supply chain issues and tariffs, but let’s be honest – that wasn’t what was stopping this project.
  • This isn’t the end of the Coyote Creek saga, as the aforementioned litigation arose in late December – local wildlife organizations backed by the area’s Audubon chapter filed a challenge against the final environmental impact statement, suggesting further delays.

2. Hampden County, Massachusetts – The small Commonwealth city of Agawam, just outside of Springfield, is the latest site of a Massachusetts uproar over battery storage…

Keep reading...Show less
Yellow
Q&A

What Happens After a Battery Fire

A conversation with San Jose State University researcher Ivano Aiello, who’s been studying the aftermath of the catastrophe at Moss Landing.

Ivano Aiello.
Heatmap Illustration

This week’s conversation is with Ivano Aiello, a geoscientist at San Jose State University in California. I interviewed Aiello a year ago, when I began investigating the potential harm caused by the battery fire at Vistra’s Moss Landing facility, perhaps the largest battery storage fire of all time. The now-closed battery plant is located near the university, and Aiello happened to be studying a nearby estuary and wildlife habitat when the fire took place. He was therefore able to closely track metals contamination from the site. When we last spoke, he told me that he was working on a comprehensive, peer-reviewed study of the impacts of the fire.

That research was recently published and has a crucial lesson: We might not be tracking the environmental impacts of battery storage fires properly.

Keep reading...Show less
Yellow