Q&A

The Environmental Group That Wants to Stop Data Centers

A conversation with Public Citizen’s Deanna Noel.

•
Deanna Noel.
Heatmap Illustration

This week’s conversation is with Deanna Noel, climate campaigns director for the advocacy group Public Citizen. I reached out to Deanna because last week Public Citizen became one of the first major environmental groups I’ve seen call for localities and states to institute full-on moratoria against any future data center development. The exhortation was part of a broader guide for more progressive policymakers on data centers, but I found this proposal to be an especially radical one as some communities institute data center moratoria that also restrict renewable energy. I wanted to know, how do progressive political organizations talk about data center bans without inadvertently helping opponents of solar and wind projects?

The following conversation was lightly edited for clarity.

Why are you recommending we ban data centers until we have regulations?

The point of us putting this out was to give policymakers a roadmap and a starting point at all levels of government, putting in guardrails to start reeling in Big Tech. Because the reality is they’re writing their own rules with how they’d like to roll out these massive data centers.

A big reason for a moratorium at the state and local level is to put in place requirements to ensure any more development that is happening is not just stepping on local communities, undermining our climate goals, impacting water resources or having adverse societal impacts like incessant noise. Big Tech is often hiding behind non-disclosure agreements and tying the hands of local officials behind NDAs while they’re negotiating deals for their data centers, which then becomes a gag order blocking officials and the public from understanding what is happening. And so our guide set out to provide a policy roadmap and a starting point is to say, let’s put a pause on this.

Do you see any cities or states doing this now? I’m trying to get a better understanding of where this came from.

It’s happening at the local level. There was a moratorium in Prince George’s County [in Maryland], where I live, until a task force can be developed and make sure local residents’ concerns are addressed. In Georgia, localities have done this, too.

The idea on its own is simple: States and localities have the authority and should be the ones to implement these moratoriums that no data centers should go forward until baseline protections are in place. There are many protections we go through in our guide, but No. 1, Big Tech should be forced to pay their way. These are some of the most wealthy corporations on the planet, and yet they’re bending backwards to negotiate deals with local utilities and governments to ensure they’re paying as little as possible for the cost of their power infrastructure. Those costs are being put on ratepayers.

The idea of a moratorium is there’s a tension in a data center buildout without any regulations.

Do you have any concerns about pushing for blanket moratoria on new technological infrastructure? We’re seeing this policy thrown at solar and wind and batteries now. Is there any concern it’ll go from data centers to renewables next in some places?

First off, you’re right, and the Trump administration wants to fast-track an expansion that’ll rely on fossil fuels: coal, oil and gas. We’re in a climate crisis, and we’d be better off if these data centers relied entirely on renewable energy.

It’s incredibly important for policymakers to be clear when they’re setting moratoria that they’re not inadvertently halting clean, cheap energy like wind and solar. This is about the unfettered expansion of the data center industry to feed the AI machine. That’s what the focus needs to be on.

Yes, but there’s also this land use techlash going on, and I’m a little concerned advocacy for a moratorium on data centers will help those fighting to institute moratoria on solar and wind. I’m talking about Ohio and Wisconsin and Iowa. Are you at all concerned about a horseshoe phenomenon here, where people are opposing data centers for the same reasons they’re fighting renewable energy projects? What should folks in the advocacy space do to make sure those things aren’t tethered to one another?

That’s a great question. I think it comes down to clear messaging for the public.

People are opportunistic — they want to get their passion projects no matter what. We as advocates need to consistently message that renewable energy is not only the energy of tomorrow, but of today. It’s where the rest of the world is headed and the U.S. is going backwards under the Trump administration.

The data center issue is separate. Data centers are using way more land – these massive hyperscaler data center campuses – are using more land than solar and wind. We can be creative with those energies in a way we can’t with the data center expansion.

We need to make it absolutely clear: This is about corporate expansion at the expense of everyone else in a way that solar and wind aren’t. Those bring costs down and don’t have anywhere near as much of an environmental impact.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

A Giant Data Center Offers a Permitting Reform Test Case

What would happen to Project Jupiter if the Bipartisan American Affordability and Jobs Act is passed?

•
Project Jupiter.
Heatmap Illustration/Project Jupiter, Library of Congress

One of the nation’s largest data centers is struggling under permitting woes. So let’s play a game: would the bipartisan permitting bill in Congress make the path easier, or might the federal legislation be irrelevant to large hyperscalers under development today?

Meet Project Jupiter, a mega project in southern New Mexico in Dona Ana County under development by Oracle and OpenAI, with financial backing from SoftBank and political support from the Trump administration for being a part of Stargate, a major Trump administration public-private initiative boosting AI development. Project Jupiter would be one of the largest data centers in the country if completed and currently is expected to run on a microgrid powered by fuel cells converting gas to electricity, which the developers claim will burn much cleaner than a typical off-grid gas turbine power plant.

Keep reading...Show less
Yellow
Hotspots

The Trump Administration Is Still Messing with Offshore Wind Farms

And more of the week’s top news around project fights.

•
The United States.
Heatmap Illustration/Getty Images

1. New England (and Maryland) – The Trump administration is still messing with offshore wind farms, even while trying to pass a permitting reform deal. Examining the court filings reveals why they may feel empowered to do it — and I’m not sure how this ends.

  • Last Friday, in a legal case brought by anti-wind activists, the Justice Department submitted a motion in federal court to send the construction and operations plan for Orsted’s Revolution Wind project in New England back to the Interior Department for more analysis. On Wednesday, the DOJ entered a similar motion in another case challenging the construction and operations plan for U.S. Wind’s MarWin project off the coast of Maryland in a lawsuit brought by the state’s coastal community of Ocean City.
  • Trump’s actions led some to question whether the president was sabotaging the deal, and others to claim the media coverage itself was an attempt to kill it. Going further, supporters of the bipartisan bill claimed the DOJ's motions were precisely why the bill should become law, implying it would guard offshore wind farms against this sort of maneuver.
  • However, for the bill’s backers, it’s worth considering why the Trump administration believes it has the legal authority to do this. It’s also time to ask whether the bill would actually protect these wind farms against this tactic.
  • To answer those questions, you have to rewind. On May 1, 2025, the Interior Department withdrew a Biden solicitor’s opinion instructing the agency to “strike a rational balance” between wind power and fishing interests. This revocation document is technically not in effect at the moment; one year later, a federal court ruled the opinion was potentially illegal as a part of a preliminary injunction on five anti-renewables actions requested by solar and wind trade groups. The Trump administration is contesting that ruling, and the administration has filed a notice of appeal.
  • In August, despite that opinion being in doubt, a federal judge granted Trump permission under the Outer Continental Shelf Lands Act to remand the construction and operations plan for the now-defunct Atlantic Shores offshore wind farm in the waters of New Jersey. U.S. District Judge Jia Cobb specifically wrote that Atlantic Shores failed to demonstrate the federal government had limitations under OSCLA on revisiting these plans and that the injunction from the litigation on appeal “did not prohibit all reevaluation of agency action.”
  • In the recent Revolution and MarWin filings, Trump’s Justice Department argues the construction and operations plans should be remanded under OSCLA without being vacated. The DOJ motions include claims that previous decision documents did not adequately explain impacts to commercial fishing and other industries that use OSCLA waters. It’s not clear if the administration will win these motions.
  • The bipartisan permitting bill would bar the Interior Department and other federal agencies from taking “any new action that would revoke, rescind, withdraw, terminate, suspend, amend, or alter a federal authorization or permit in effect on or after September 16, 2026,” or “any other action to interfere with or prevent the construction or operation at full capacity of a project that has secured all necessary federal authorizations and permits.” The restriction exempts cases where “the agency is required to take such action by order of a court.” As I wrote in our lengthy piece explaining the bill, this provision has a damages component that allows companies impacted by violations to pursue financial compensation.
  • Here’s the billion-dollar question I expect we won’t have answered unless the bill language is enacted and then litigated: Would the court order exception apply to rulings that grant these motions? Or would the developers be able to sue for damages?

2. Columbia County, N.Y. – New York’s renewable energy permitting office has rejected an upstate solar farm on farmland as a House Democrat representing the area joined hands with the Trump administration in publicly railing against the project.

Keep reading...Show less
Yellow
Q&A

The Developer that Builds Local Support with ‘Right-sized’ Data Centers

A conversation with Harmol Samra of Host Digital

•
The Q&A subject.
Heatmap Illustration

This week’s conversation is with Harmol Samra, CEO of data center developer Host Digital. I asked Samra for a conversation because his team expressed a willingness to offer candid views on the industry’s problems with social license to operate — namely, why is the industry botching this so badly? From his point of view, many could learn a lot from industrial revolutions of the past, and they should be careful not to let mega-project expansions get in the way of broader acceptance of the data center sector.

The following conversation was lightly edited for clarity.

Keep reading...Show less