The Collapse of the Northeast’s Biggest Hydrogen Plant

Has Plug Power pulled the plug on its upstate New York facility?

•
Hydrogen.
Genesee County Economic Development Center / Getty Images / Heatmap

In 2021, top elected officials in New York state promised that Plug Power, a nascent company in the growing hydrogen industry, would build a large hydrogen fuel production facility in the Buffalo-Rochester area. It was supposed to make the state an industry leader.

Today, the project is looking more like a warning sign about the perils of being a first-mover in the unproven hydrogen business.

It wasn’t supposed to be this way. Plug Power, an American hydrogen and fuel cell producer founded in 1997, believed it would capitalize on rising demand for the liquid fuel when it broke ground at its hydrogen production facility at Genesee County’s Science, Technology and Advanced Manufacturing Park in 2021, a project known colloquially as STAMP. Heavy polluting industries like steel and transportation were chomping at the bit to strike supply deals for hydrogen, a liquid fuel that produces no carbon when burned. And this New York plant would on paper be particularly attractive from a climate perspective: It would be powered by hydroelectric dams at Niagara Falls, offering a potential carbon reduction of an estimated 14,000 tons of CO2 per year. It would also be the largest project of its kind in the Northeast.

Three years later and the project appears to be on ice, according to a phone call recording between New York county officials and a real estate developer that was obtained by Heatmap News.

Construction stopped in January, per the call, as did work Plug Power promised to do on an electrical substation that will also power a neighboring semiconductor manufacturing plant. Now energy-hungry data center developers are bidding to pick up the substation work instead in exchange for a spot at STAMP and access to some of the remaining hydroelectricity, and county officials are looking at buying Plug Power’s electrical equipment.

It is unclear whether the hydrogen production plant will ever be completed.

“They’ve put things on hold and now we’re coming to pick up the pieces,” Chris Suozzi, an executive vice president at the Genessee County Economic Development Authority, told one bidder – PRP Real Estate Management – on a call last month. PRP taped the call and shared it with us after it was first reported by local news nonprofit InvestigativePost. Suozzi also said on the call: “They’re not ready to go. They’re on pause. We don’t know what’s going to happen with them at this point.”

The New York Plug Power plant’s problems should be familiar to anyone in the climate tech startup space but for the unfamiliar, the company’s rapid growth seems to have run headlong into struggles with cash. A year ago Plug Power said in an investor filing there was a “substantial” concern the company may not have “sufficient funds to fund [its] operations through the next 12 months.” So problematic are Plug’s financial woes that they’ve become a political target; after the Energy Department offered a $1.6 billion conditional loan commitment to Plug for building hydrogen production plants, Republicans in Congress called for an inspector general investigation into the move.

But the New York production facility won’t benefit from the potential loan either. We’ve learned from two sources familiar with the matter that the project is not included in its potential loan application currently pending before DOE.

Then there has been the rollout of the Inflation Reduction Act. Even though the project relies on carbon-free hydropower, it may not qualify for the IRA’s hydrogen production tax credit because of proposed requirements for fuel to rely on new renewable energy sources (known as “additionality”). This has been a major sticking point in implementation of the credit, and Plug Power is quoted in InvestigativePost last week linking the work stoppage at the production facility on waiting for the final regulation implementing the credit. This is even as the company uses the yet-to-be finalized credit in its financial analyses for other hydrogen facilities in operation today, like this one in Georgia.

Environmental justice issues have also been a drag on development. The native Tonawanda Seneca Nation is opposed to the entire industrial park because of the resulting impacts on wildlife, noise and the visual landscape. In April, the Fish and Wildlife Service revoked a necessary permit for a wastewater treatment pipeline that would be used by companies at the park.

Earthjustice attorney Alex Page – who is working with the Nation to fight the project – told me the tribe was told last year by the Energy Department that Plug Power had withdrawn the New York site from its loan application. The Nation will continue to fight the project and DOE’s loan financing to Plug Power on the chance that money could be reprogrammed to the industrial park. Page said: “The Nation remains very, very much opposed.”

We sent Plug Power multiple requests for comment as well as Suozzi. A representative for Plug Power declined to answer questions about the project. I got a text from a number listed for Suozzi asking to chat later, but I didn’t hear back before publication.

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

Why the Wilderness Society Backs a Data Center Moratorium

Talking with Dan Hartinger, the land conservation group’s senior policy director.

•
The Q&A subject.
Heatmap Illustration

This week’s Q&A is with Dan Hartinger, senior policy director for The Wilderness Society, a prominent land conservation organization in D.C. that this week called for a moratorium on data center development on public land. The public statement was relatively scant on details about the group’s stance, and a decade of reporting on policy in Washington has taught me that its positions are quite influential, especially in more traditional outdoor recreation and conservationist circles that are also often bipartisan. So I reached out and asked if someone could further explain the society’s position, and Dan obliged.

The following chat was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

Data Center Outrage Catches Up to Renewables Outrage in Michigan

Plus more of the week’s biggest development fights.

•
The United States.
Heatmap Illustration/Getty Images

1. Central Michigan – I regret to inform you of this back-and-forth between candidates running for Congress and a would-be constituent because it’s a warning sign for the renewable energy sector (and sort of broke my brain).

  • This week brought the first and likely only debate between Rep. Tom Barrett and Sunrise Movement cofounder Will Lawrence, who are locked in a tight contest over the Michigan 7th congressional district. As I’ve written, their race is a must-watch not only for control of the U.S. House but also the political fortunes of the data center sector.
  • The debate contained a remarkable exchange: Moderators played taped remarks from Paula Caltrider, identified as “a local resident” in the city of Mason to ask the candidates a question about data centers. Instead, she offered a comment. “You know, you can’t be a part of this no data center movement without renouncing the large solar farms and dangerous battery storage facilities that power these data centers.” (Quick TL;DR on Caltrider: She’s been quoted in national media coverage of the data center backlash and last year won a legal settlement after allegedly being fired for refusing a vaccine mandate.)
  • Barrett then ran with Caltrider’s baton. “I appreciate Paula linking these together, the stripping away of local control that took place in pursuit of this Green New Deal agenda in Lansing that took away control from communities” – a reference to the state’s primacy law that other Michigan Republican candidates have opposed.
  • Lawrence, whose support for a federal data center moratorium made him a national political test case, did not take the bait, nor did he criticize renewable energy. Instead, this part of the debate became a tit-for-tat about whether the sitting congressman once backed tax breaks for data centers. “He stuck his finger up into the wind, saw which way it was blowing, did a complete 180 on this issue,” Lawrence said. Then Barrett and Lawrence got into a confusing back-and-forth about whether the Inflation Reduction Act was a giveaway to data centers.
  • To the best of my knowledge, this is the first time the Data Center Trojan Horse has reared its ugly head on any kind of prominent debate stage, but it won’t be the last. For example: The Wisconsin gubernatorial debate is Oct. 21, and we’ve warned you about that one.

2. Doña Ana County, New Mexico – I suggest you pay closer attention to the federal permitting fight playing out over Oracle’s Project Jupiter.

Keep reading...Show less
Yellow
Spotlight

The Data Center Backlash Is Coming for Permitting Reform

The Senate’s compromise bill enters the chat at a moment when federal land and anti-pipeline advocates are already quite activated.

•
The Capitol and a data center.
Heatmap Illustration/Getty Images

The AI data center backlash is getting louder in D.C. ahead of the midterms – and it’s poised to collide head-on with the new permitting reform deal being negotiated in Congress.

This week, major environmental advocacy organizations are taking large public steps to lean in on the data center fight. The League of Conservation Voters and Natural Resources Defense Council, I’ve been told, are imminently announcing a $250,000 ad buy in the Washington, D.C. market focused entirely on decrying fossil fuel-powered data centers and Trump administration policies to speed up their construction. The Wilderness Society, a prominent land conservation organization, announced it now supports a moratorium against data centers on “public lands” focused on the roughly half billion acres under the Interior Department’s stewardship. And Earthjustice on Thursday did a detailed report claiming that 80% of the data centers under development “bringing their own power” are going to rely on gas generation.

Keep reading...Show less
Yellow