This article is exclusively
for Heatmap Plus subscribers.
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.

Sign In or Create an Account.
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Welcome to Heatmap
Thank you for registering with Heatmap. Climate change is one of the greatest challenges of our lives, a force reshaping our economy, our politics, and our culture. We hope to be your trusted, friendly, and insightful guide to that transformation. Please enjoy your free articles. You can check your profile here .
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Subscribe to get unlimited Access
Hey, you are out of free articles but you are only a few clicks away from full access. Subscribe below and take advantage of our introductory offer.
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Create Your Account
Please Enter Your Password
Forgot your password?
Please enter the email address you use for your account so we can send you a link to reset your password:
Just look at Virginia.

Solar and wind projects are getting swept up in the blowback to data center construction, presenting a risk to renewable energy companies who are hoping to ride the rise of AI in an otherwise difficult moment for the industry.
The American data center boom is going to demand an enormous amount of electricity and renewables developers believe much of it will come from solar and wind. But while these types of energy generation may be more easily constructed than, say, a fossil power plant, it doesn’t necessarily mean a connection to a data center will make a renewable project more popular. Not to mention data centers in rural areas face complaints that overlap with prominent arguments against solar and wind – like noise and impacts to water and farmland – which is leading to unfavorable outcomes for renewable energy developers more broadly when a community turns against a data center.
“This is something that we’re just starting to see,” said Matthew Eisenson, a senior fellow with the Renewable Energy Legal Defense Initiative at the Columbia University Sabin Center for Climate Change Law. “It’s one thing for environmentalists to support wind and solar projects if the idea is that those projects will eventually replace coal power plants. But it’s another thing if those projects are purely being built to meet incremental demand from data centers.”
We’ve started to see evidence of this backlash in certain resort towns fearful of a new tech industry presence and the conflicts over transmission lines in Maryland. But it is most prominent in Virginia, ground zero for American hyperscaler data centers. As we’ve previously discussed in The Fight, rural Virginia is increasingly one of the hardest places to get approval for a solar farm in the U.S., and while there are many reasons the industry is facing issues there, a significant one is the state’s data center boom.
I spent weeks digging into the example of Mecklenburg County, where the local Board of Supervisors in May indefinitely banned new solar projects and is rejecting those that were in the middle of permitting when the decision came down. It’s also the site of a growing data center footprint. Microsoft, which already had a base of operations in the county’s town of Boydton, is in the process of building a giant data center hub with three buildings and an enormous amount of energy demand. It’s this sudden buildup of tech industry infrastructure that is by all appearances driving a backlash to renewable energy in the county, a place that already had a pre-existing high opposition risk in the Heatmap Pro database.
It’s not just data centers causing the ban in Mecklenburg, but it’s worth paying attention to how the fight over Big Tech and solar has overlapped in the county, where Sierra Club’s Virginia Chapter has worked locally to fight data center growth with a grassroots citizens group, Friends of the Meherrin River, that was a key supporter of the solar moratorium, too.
In a conversation with me this week, Tim Cywinski, communications director for the state’s Sierra Club chapter, told me municipal leaders like those in Mecklenburg are starting to group together renewables and data centers because, simply put, rural communities enter into conversations with these outsider business segments with a heavy dose of skepticism. This distrust can then be compounded when errors are made, such as when one utility-scale solar farm – Geenex’s Grasshopper project – apparently polluted a nearby creek after soil erosion issues during construction, a problem project operator Dominion Energy later acknowledged and has continued to be a pain point for renewables developers in the county.
“I don’t think the planning that has been presented to rural America has been adequate enough,” the Richmond-based advocate said. “Has solar kind of messed up in a lot of areas in rural America? Yeah, and that’s given those communities an excuse to roll them in with a lot of other bad stuff.”
Cywinski – who describes himself as “not your typical environmentalist” – says the data center space has done a worse job at community engagement than renewables developers in Virginia, and that the opposition against data center projects in places like Chesapeake and Fauquier is more intense, widespread, and popular than the opposition to renewables he’s seeing play out across the Commonwealth.
But, he added, he doesn’t believe the fight against data centers is “mutually exclusive” from conflicts over solar. “I’m not going to tout the gospel of solar while I’m trying to fight a data center for these people because it’s about listening to them, hearing their concerns, and then not telling them what to say but trying to help them elevate their perspective and their concerns,” Cywinski said.
As someone who spends a lot of time speaking with communities resisting solar and trying to best understand their concerns, I agree with Cywinksi: the conflict over data centers speaks to the heart of the rural vs. renewables divide, and it offers a warning shot to anyone thinking AI will help make solar and wind more popular.
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.
It’s now clear that 2026 will be big for American energy, but it’s going to be incredibly tense.
Over the past 365 days, we at The Fight have closely monitored numerous conflicts over siting and permitting for renewable energy and battery storage projects. As we’ve done so, the data center boom has come into full view, igniting a tinderbox of resentment over land use, local governance and, well, lots more. The future of the U.S. economy and the energy grid may well ride on the outcomes of the very same city council and board of commissioners meetings I’ve been reporting on every day. It’s a scary yet exciting prospect.
To bring us into the new year, I wanted to try something a little different. Readers ask me all the time for advice with questions like, What should I be thinking about right now? And, How do I get this community to support my project? Or my favorite: When will people finally just shut up and let us build things? To try and answer these questions and more, I wanted to give you the top five trends in energy development (and data centers) I’ll be watching next year.
The best thing going for American renewable energy right now is the AI data center boom. But the backlash against developing these projects is spreading incredibly fast.
Do you remember last week when I told you about a national environmental group calling for data center moratoria across the country? On Wednesday, Senator Bernie Sanders called for a nationwide halt to data center construction until regulations are put in place. The next day, the Working Families Party – a progressive third party that fields candidates all over the country for all levels of government – called for its candidates to run in opposition to new data center construction.
On the other end of the political spectrum, major figures in the American right wing have become AI skeptics critical of the nascent data center buildout, including Florida Governor Ron DeSantis, Missouri Senator Josh Hawley, and former Trump adviser Steve Bannon. These figures are clearly following the signals amidst the noise; I have watched in recent months as anti-data center fervor has spread across Facebook, with local community pages and groups once focused on solar and wind projects pivoting instead to focus on data centers in development near them.
In other words, I predicted just one month ago, an anti-data center political movement is forming across the country and quickly gaining steam (ironically aided by the internet and algorithms powered by server farms).
I often hear from the clean energy sector that the data center boom will be a boon for new projects. Renewable energy is the fastest to scale and construct, the thinking goes, and therefore will be the quickest, easiest, and most cost effective way to meet the projected spike in energy demand.
I’m not convinced yet that this line of thinking is correct. But I’m definitely sure that no matter the fuel type, we can expect a lot more transmission development, and nothing sparks a land use fight more easily than new wires.
Past is prologue here. One must look no further than the years-long fight over the Piedmont Reliability Project, a proposed line that would connect a nuclear power plant in Pennsylvania to data centers in Virginia by crossing a large swathe of Maryland agricultural land. I’ve been covering it closely since we put the project in our inaugural list of the most at-risk projects, and the conflict is now a clear blueprint.
In Wisconsin, a billion-dollar transmission project is proving this thesis true. I highly recommend readers pay close attention to Port Washington, where the release of fresh transmission line routes for a massive new data center this week has aided an effort to recall the city’s mayor for supporting the project. And this isn’t even an interstate project like Piedmont.
While I may not be sure of the renewable energy sector’s longer-term benefits from data center development, I’m far more confident that this Big Tech land use backlash is hitting projects right now.
The short-term issue for renewables developers is that opponents of data centers use arguments and tactics similar to those deployed by anti-solar and anti-wind advocates. Everyone fighting data centers is talking about ending development on farmland, avoiding changes to property values, stopping excess noise and water use, and halting irreparable changes to their ways of life.
Only one factor distinguishes data center fights from renewable energy fights: building the former potentially raises energy bills, while the latter will lower energy costs.
I do fear that as data center fights intensify nationwide, communities will not ban or hyper-regulate the server farms in particular, but rather will pass general bans that also block the energy projects that could potentially power them. Rural counties are already enacting moratoria on solar and wind in tandem with data centers – this is not new. But the problem will worsen as conflicts spread, and it will be incumbent upon the myriad environmentalists boosting data center opponents to not accidentally aid those fighting zero-carbon energy.
This week, the Bureau of Land Management approved its first solar project in months: the Libra facility in Nevada. When this happened, I received a flood of enthusiastic and optimistic emails and texts from sources.
We do not yet know whether the Libra approval is a signal of a thaw inside the Trump administration. The Interior Department’s freeze on renewables permitting decisions continues mostly unabated, and I have seen nothing to indicate that more decisions like this are coming down the pike. What we do know is that ahead of a difficult midterm election, the Trump administration faces outsized pressure to do more to address “affordability,” Democrats plan to go after Republicans for effectively repealing the Inflation Reduction Act and halting permits for solar and wind projects, and there’s a grand bargain to be made in Congress over permitting reform that rides on an end to the permitting freeze.
I anticipate that ahead of the election and further permitting talks in Congress, the Trump administration will mildly ease its chokehold on solar and wind permits because that is the most logical option in front of them. I do not think this will change the circumstances for more than a small handful of projects sited on federal lands that were already deep in the permitting process when Trump took power.
It’s impossible to conclude a conversation about next year’s project fights without ending on the theme that defined 2025: battery fire fears are ablaze, and they’ll only intensify as data centers demand excess energy storage capacity.
The January Moss Landing fire incident was a defining moment for an energy sector struggling to grapple with the effects of the Internet age. Despite bearing little resemblance to the litany of BESS proposals across the country, that one hunk of burning battery wreckage in California inspired countless communities nationwide to ban new battery storage outright.
There is no sign this trend will end any time soon. I expect data centers to only accelerate these concerns, as these facilities can also catch fire in ways that are challenging to address.
Plus a resolution for Vineyard Wind and more of the week’s big renewables fights.
1. Hopkins County, Texas – A Dallas-area data center fight pitting developer Vistra against Texas attorney general Ken Paxton has exploded into a full-blown political controversy as the power company now argues the project’s developer had an improper romance with a city official for the host community.
2. La Plata County, Colorado – This county has just voted to extend its moratorium on battery energy storage facilities over fire fears.
3. Dane County, Wisconsin – The city of Madison appears poised to ban data centers for at least a year.
4. Goodhue County, Minnesota – The Minnesota Center for Environmental Advocacy, a large environmentalist organization in the state, is suing to block a data center project in the small city of Pine Island.
5. Hall County, Georgia – A data center has been stopped down South, at least for now.
6. Dukes County, Massachusetts – The fight between Vineyard Wind and the town of Nantucket seems to be over.
A catch-up with kWh Analytics’ Jason Kaminsky.
This week’s conversation is a catch-up chat with Jason Kaminsky of kWh Analytics, an insurance firm that works with renewable energy developers. I reached out to Kaminsky ahead of the new year because as someone with an arms-length distance from development, I find he is able to speak more candidly about market dynamics and macro-level trends – as well as the fears many have in rural communities about energy project failures, like battery fires. Seeing as the theme this week felt like “data centers forever,” I also thought it would be good to get up to speed on what he’s most focused on in that space, too.
The following conversation has been lightly edited for clarity.
Okay so, Jason – is renewable energy actually benefiting from the data center boom?
Renewables are supporting our load growth boom. Data centers are about a third of the projected load growth. So it is certainly a key component of what is driving demand broadly, but not the only component. The other pieces worth considering are the electrification of transportation, the reindustrialization of America, and the electrification of residential homes. But data centers are getting enthusiasm because of how quickly people are trying to deploy them.
The unique benefit renewables have is that they’re able to deploy quickly, and you need the benefits that storage has to handle these load centers.
How rapidly is the data center buildout and its associated infrastructure buildout actually happening, and how rapidly is this demand curve actually rising?
Remember, we’re not a developer on the front line, and a developer on the front line might have a better answer to this. But I’d say most of the activity today in the data center space is still quite a ways out. It’s either linked to a new facility or the planning of a new facility. Now, granted, we’re seeing it quite late in the process because we’re the insurance company, and so from an operational perspective, we’re not seeing it in the numbers yet. But it is in the forecasts, which is what you’re seeing, as well.
When it comes to concerns about renewable energy development at the local level, the last time we spoke was about project risk and the extent to which projects face weather risks, fire risks. Do data centers face these same kinds of risks?
The data center development ecosystem parallels very closely with the project development ecosystem with renewables.
What I mean by that is you have a few mega-developers, like the NextEras of the world, but instead it’s Meta and Google building these massive centers, these 800-pound gorillas. Then you have these companies that are equivalent to [independent power producers], a lot of people building mid-size to small-size data centers, and either building them on spec or with long-term contracts. Within that you have very different community engagements and quality, different power generation strategies and siting strategies, but there’s no universal data center approach. It’s a very stratified data center ecosystem.
It probably compounds the problem because you have more land being used. There are stories like the X data centers not getting permits for their generators, and resulting local pollution. There have been concerns in the media about heat effects and the way data centers use so much water.
Before, though, renewables were the focus. Now data centers are the focus and renewables are just kind of along for the ride.
Has the conversation around the renewable energy sector and its project-level business risks evolved in the year since we last spoke? Have data centers changed the conversation?
I would say that from a micro perspective, as you start pairing these facilities with data centers, one of the things you have to think about from a risk management perspective and the insurance perspective is the lost revenue due to a failure.
Generally, that’s electricity sales. There’s something called business income insurance, which, if you have a loss of a facility, you pay for lost revenue. But if you’re paired with a data center and your lost income is now compute income, your business income exposure can be much higher. So the resiliency of an asset or the reliability of an asset becomes that much more valuable and expensive.
I don’t think we’ve seen a lot of that yet in our ecosystem, but I think it’s coming.
What is your biggest prediction in the renewable energy space next year?
I think that the risk of China building more data centers than us and getting ahead of us in the race for AI – and the risk of energy inflation – is going to make some of these problems easier to solve from a risk perspective.
My hope is that the fear of being left behind and the fear of risk associated with energy inflation will lead to legislators allowing for more quick-to-deploy, cheap and clean power going to the grid. Renewables will find a way onto the grid. With just a little bit of legislative guidance and pathway, a lot can happen.