Internal Agency Memo Calls for Political Reviews of Solar, Wind Projects

The widely circulating document lists more than 68 activities newly subject to upper-level review.

Doug Burgum.
Heatmap Illustration/Getty Images

The federal government is poised to put solar and wind projects through strict new reviews that may delay projects across the country, according to a widely circulating document reviewed by Heatmap.

The secretarial order authored by Interior Secretary Doug Burgum’s Deputy Chief of Staff for Policy Gregory Wischer is dated July 15 and states that “all decisions, actions, consultations, and other undertakings” that are “related to wind and solar energy facilities” will now be required to go through multiple layers of political review from Burgum’s office and Interior’s Office of the Deputy Secretary.

This new layer of review would span essentially anything Interior and its many subagencies would ordinarily be consulted on before construction on a project can commence — a milestone crucial for being able to qualify for federal renewable energy tax credits under the One Big Beautiful Bill Act. The order lists more than 68 different activities newly subject to higher-level review, including some basic determinations as to whether projects conform with federal environmental and conservation laws, as well as consultations on compliance with wildlife protection laws such as the Endangered Species Act. The final item in the list sweeps “any other similar or related decisions, actions, consultations, or undertakings” under the order’s purview, in case there was any grey area there.

In other words, this order is so drastic it would impact projects on state and private lands, as well as federal acreage. In some cases, agency staff may now need political sign-offs simply to tell renewables developers whether they need a permit at all.

“This is the way you stall and kill projects. Intentionally red-tape projects to death,” former Biden White House clean energy adviser Avi Zevin wrote on Bluesky in a post with a screenshot of the order.

The department has yet to release the document and it’s unclear whether or when it will be made public. The order’s existence was first reported by Politico; in a statement to that news outlet, the department did not deny the document’s existence but attacked leakers. “Let’s be clear: leaking internal documents to the media is cowardly, dishonest, and a blatant violation of professional standards,” the statement said.

Interior’s press office did not immediately respond to a request for comment from Heatmap about when this document may be made public. We also asked whether this would also apply to transmission connected to solar and wind. You had better believe I’ll be following up with the department to find out, and we’ll update this story if we hear back from them.

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Climate Tech

There’s a Better Way to Mine Lithium — At Least in Theory

In practice, direct lithium extraction doesn’t quite make sense, but 2026 could its critical year.

A lithium worker.
Heatmap Illustration/Getty Images, Standard Lithium

Lithium isn’t like most minerals.

Unlike other battery metals such as nickel, cobalt, and manganese, which are mined from hard-rock ores using drills and explosives, the majority of the world’s lithium resources are found in underground reservoirs of extremely salty water, known as brine. And while hard-rock mining does play a major role in lithium extraction — the majority of the world’s actual production still comes from rocks — brine mining is usually significantly cheaper, and is thus highly attractive wherever it’s geographically feasible.

Keep reading...Show less
Green
Q&A

How Trump’s Renewable Freeze Is Chilling Climate Tech

A chat with CleanCapital founder Jon Powers.

Jon Powers.
Heatmap Illustration

This week’s conversation is with Jon Powers, founder of the investment firm CleanCapital. I reached out to Powers because I wanted to get a better understanding of how renewable energy investments were shifting one year into the Trump administration. What followed was a candid, detailed look inside the thinking of how the big money in cleantech actually views Trump’s war on renewable energy permitting.

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

Indiana Rejects One Data Center, Welcomes Another

Plus more on the week’s biggest renewables fights.

The United States.
Heatmap Illustration/Getty Images

Shelby County, Indiana – A large data center was rejected late Wednesday southeast of Indianapolis, as the takedown of a major Google campus last year continues to reverberate in the area.

  • Real estate firm Prologis was the loser at the end of a five-hour hearing last night before the planning commission in Shelbyville, a city whose municipal council earlier this week approved a nearly 500-acre land annexation for new data center construction. After hearing from countless Shelbyville residents, the planning commission gave the Prologis data center proposal an “unfavorable” recommendation, meaning it wants the city to ultimately reject the project. (Simpsons fans: maybe they could build the data center in Springfield instead.)
  • This is at least the third data center to be rejected by local officials in four months in Indiana. It comes after Indianapolis’ headline-grabbing decision to turn down a massive Google complex and commissioners in St. Joseph County – in the town of New Carlisle, outside of South Bend – also voted down a data center project.
  • Not all data centers are failing in Indiana, though. In the northwest border community of Hobart, just outside of Chicago, the mayor and city council unanimously approved an $11 billion Amazon data center complex in spite of a similar uproar against development. Hobart Mayor Josh Huddlestun defended the decision in a Facebook post, declaring the deal with Amazon “the largest publicly known upfront cash payment ever for a private development on private land” in the United States.
  • “This comes at a critical time,” Huddlestun wrote, pointing to future lost tax revenue due to a state law cutting property taxes. “Those cuts will significantly reduce revenue for cities across Indiana. We prepared early because we did not want to lay off employees or cut the services you depend on.”

Dane County, Wisconsin – Heading northwest, the QTS data center in DeForest we’ve been tracking is broiling into a major conflict, after activists uncovered controversial emails between the village’s president and the company.

Keep reading...Show less