Georgia Just Released Eye-Popping New Energy Demand Estimates

We’ll give you one guess as to what’s behind the huge spike.

A data center.
Heatmap Illustration/Getty Images

Georgia is going to need a lot more electricity than it once thought. Again.

In a filing last week with the state’s utility regulator, Georgia Power disclosed that its projected load growth for the next decade from “economic development projects” has gone up by over 12,000 megawatts, to 36,500 megawatts. Just for 2028 to 2029, the pipeline has more than tripled, from 6,000 megawatts to 19,990 megawatts, destined for so-called “large load” projects like new data centers and factories.

To give you an idea of just how much power Georgia businesses will demand over the next decade, the two new recently booted up nuclear reactors at Vogtle each have a capacity of around 1,000 megawatts. Of the listed projects that may come online, five will require 1,000 megawatts or more.

The culprit is largely data centers. About 3,330 megawatts’ worth of data centers have broken ground in Georgia, and just over 4,100 megawatts are pending construction, vastly outstripping commitments made by industrial customers.

“New load growth, led predominately by data centers, could triple [Georgia Power’s] size, in ten years. This is the second industrial revolution, led by artificial intelligence,” Simon Mahan, the executive director of the Southern Renewable Energy Association, wrote on X.

Georgia Power is used to upgrading load forecasts. The company had to update its three-year planning process (known as an integrated resource plan, or IRP) in October of 2023, just a year after releasing its previous three-year plan, as its five-year load growth projections had grown from 400 megawatts to 6,660 megawatts, a 17-fold increase. Regulators approved the new plan in April of this year, which included adding turbines to an existing gas-fired plant, pushing out the retirement of a coal-fired plant, and more battery storage.

The latest update, Georgia Power said in the filing, “should provide further certainty that Georgia Power’s load forecast is materializing and that the constructive outcome of the 2023 IRP Update is supportive of economic growth in Georgia.”

Yellow

You’re out of free articles.

Use code: LABORDAY to save 20%.
Subscribe to access Heatmap’s exclusive polling and expert analysis of energy, climate change, and sustainability, now just $99/year $79.20/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Sparks

Why SoCal Electricity Customers Are Paying for Utility Reforms

The August Electricity Price Hub data is in.

The Hollywood sign and power lines.
Heatmap Illustration/Getty Images

It’s another hot and expensive summer.

Across the country, average household electricity bills are up 2.7% in the first eight months of the year, according to the latest update to Heatmap and MIT’s Electricity Price Hub, tacking on $4 per month to the typical bill. This level of rise is consistent with the pace set in 2024 and 2025, but faster than 2021 and 2023.

Keep reading...Show less
Blue
Sparks

The Startup Behind Lamppost-Mounted EV Chargers Pulls Into the Garage

Voltpost announced two new models today designed to mount on walls and ceilings.

Voltpost chargers.
Heatmap Illustration/Getty Images

Voltpost, the company putting electric vehicle chargers on lampposts, is now expanding to parking garages.

On Wednesday, the company unveiled two new configurations that can attach to the walls and ceilings of parking garages, lots, and other locations without easy access to streetlights or utility poles. Like Voltpost’s signature pole-mounted design, the ceiling- and wall-mounted options avoid the expensive construction work required by freestanding charging infrastructure. In theory at least, that should allow the company to deploy more chargers faster.

Keep reading...Show less
Blue
Sparks

Trump’s USDA Using Farmland Rule to Go After Energy Companies, Democrats Say

A proposed change in how the agency implements an obscure Cold War-era law would impose onerous reporting requirements on renewables and pipelines.

Wind turbines and a farm.
Heatmap Illustration/Getty Images

Democrats in Congress claim that a new Trump administration proposal will have a chilling effect on the energy sector by subjecting renewables and fossil fuel pipelines alike to an obscure, rarely cited Cold War-era law requiring detailed information on foreign farmland ownership be submitted to the Agriculture Department.

In late June, the Agriculture Department released a proposal to change implementation of the Agricultural Foreign Investment Disclosure Act of 1978, which requires companies to provide information to the federal government on foreign investors in farmland holdings, acquisitions, and sales. If finalized, the new rule would expand the definition of “agricultural land” in regulation to include all renewable energy facilities and pipeline corridors by explicitly tying the term to those industries’ formal codes under the North American Industry Classification System.

Keep reading...Show less
Yellow