You’re out of free articles.
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.
Sign In or Create an Account.
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Welcome to Heatmap
Thank you for registering with Heatmap. Climate change is one of the greatest challenges of our lives, a force reshaping our economy, our politics, and our culture. We hope to be your trusted, friendly, and insightful guide to that transformation. Please enjoy your free articles. You can check your profile here .
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Subscribe to get unlimited Access
Hey, you are out of free articles but you are only a few clicks away from full access. Subscribe below and take advantage of our introductory offer.
subscribe to get Unlimited access
Offer for a Heatmap News Unlimited Access subscription; please note that your subscription will renew automatically unless you cancel prior to renewal. Cancellation takes effect at the end of your current billing period. We will let you know in advance of any price changes. Taxes may apply. Offer terms are subject to change.
Create Your Account
Please Enter Your Password
Forgot your password?
Please enter the email address you use for your account so we can send you a link to reset your password:
The department creates a seemingly impossible new permitting criteria for renewable energy.

The Interior Department released a new secretarial order Friday saying it may no longer issue any permits to a solar or wind project on federal lands unless the agency believes it will generate as much energy per acre as a coal, gas, or nuclear power plant.
Hypothetically, this could kill off any solar or wind project going through permitting that is sited on federal lands, because these facilities would technically be less energy dense than coal, gas, and nuclear plants. This is irrespective of the potential benefits solar and wind may have for the environment or reducing carbon emissions – none of which are mentioned in the order.
“Gargantuan, unreliable, intermittent energy projects hold America back from achieving U.S. Energy Dominance while weighing heavily on the American taxpayer and environment,” Interior Secretary Doug Burgum said in a statement included in a press release announcing the move. “By considering energy generation optimization, the Department will be able to better manage our federal lands, minimize environmental impact, and maximize energy development to further President Donald Trump’s energy goals.”
Here’s how this new regime, which I and many in the energy sector are now suddenly trying to wrap their heads around, is apparently going to work: solar and wind facilities will now be evaluated based on their “capacity density,” which is calculated based on the ratio of acres used for a project compared to its power generation capacity. If a project has a lower “capacity density” than what the department considers to be a “reasonable alternative,” then it may no longer be able to get a permit.
“On a technology-neutral basis,” the order states, “wind and solar projects use disproportionate Federal lands relative to their energy generation when compared to other energy sources, like nuclear, gas, and coal.” The document going on to give an example, claiming that data from the U.S. Energy Information Administration shows an advanced nuclear plant uses less federal acreage than an offshore wind farm and “thus, when there are reasonable alternatives that can generate the same amount of or more energy on far less Federal land, wind and solar projects may unnecessarily and unduly degrade Federal lands.” The order also includes a chart comparing the capacity density of wind and solar facilities to conventional nuclear, gas, and coal, as well as geothermal, and claims that these sources are superior as well. The document does not reference hydropower.
There’s also a whole host of other implications in this order. Crucially, does the Interior expect that by choking off the flow of permits, cities and companies will just pony up to build what the Trump administration considers “reasonable alternatives” instead? Is the federal government going to tell communities in Nevada, for example, that they must suddenly build gas plants in the desert instead of solar farms to meet their increasing energy needs?
In any case, much more is coming, as this order simply built off of a separate secretarial order earlier this week commanding staff to prepare a litany of recommendations on ending alleged “preferential treatment” for solar and wind facilities. In other words hold my beer – and hold onto yours, too.
Log in
To continue reading, log in to your account.
Create a Free Account
To unlock more free articles, please create a free account.
The offshore wind industry is now five-for-five against Trump’s orders to halt construction.
District Judge Royce Lamberth ruled Monday morning that Orsted could resume construction of the Sunrise Wind project off the coast of New England. This wasn’t a surprise considering Lamberth has previously ruled not once but twice in favor of Orsted continuing work on a separate offshore energy project, Revolution Wind, and the legal arguments were the same. It also comes after the Trump administration lost three other cases over these stop work orders, which were issued without warning shortly before Christmas on questionable national security grounds.
The stakes in this case couldn’t be more clear. If the government were to somehow prevail in one or more of these cases, it would potentially allow agencies to shut down any construction project underway using even the vaguest of national security claims. But as I have previously explained, that behavior is often a textbook violation of federal administrative procedure law.
Whether the Trump administration will appeal any of these rulings is now the most urgent question. There have been no indications that the administration intends to do so, and a review of the federal dockets indicates nothing has been filed yet.
I’ve reached out to the administration and will update this story if and when I hear back.
A new PowerLines report puts the total requested increases at $31 billion — more than double the number from 2024.
Utilities asked regulators for permission to extract a lot more money from ratepayers last year.
Electric and gas utilities requested almost $31 billion worth of rate increases in 2025, according to an analysis by the energy policy nonprofit PowerLines released Thursday morning, compared to $15 billion worth of rate increases in 2024. In case you haven’t already done the math: That’s more than double what utilities asked for just a year earlier.
Utilities go to state regulators with its spending and investment plans, and those regulators decide how much of a return the utility is allowed to glean from its ratepayers on those investments. (Costs for fuel — like natural gas for a power plant — are typically passed through to customers without utilities earning a profit.) Just because a utility requests a certain level of spending does not mean that regulators will approve it. But the volume and magnitude of the increases likely means that many ratepayers will see higher bills in the coming year.
“These increases, a lot of them have not actually hit people's wallets yet,” PowerLines executive director Charles Hua told a group of reporters Wednesday afternoon. “So that shows that in 2026, the utility bills are likely to continue to rise, barring some major, sweeping action.” Those could affect some 81 million consumers, he said.
Electricity prices have gone up 6.7% in the past year, according to the Bureau of Labor Statistics, outpacing overall prices, which have risen 2.7%. Electricity is 37% more expensive today than it was just five years ago, a trend researchers have attributed to geographically specific factors such as costs arising from wildfires attributed to faulty utility equipment, as well as rising costs for maintaining and building out the grid itself.
These rising costs have become increasingly politically contentious, with state and local politicians using electricity markets and utilities as punching bags. Newly elected New Jersey Governor Mikie Sherrill’s first two actions in office, for instance, were both aimed at effecting a rate freeze proposal that was at the center of her campaign.
But some of the biggest rate increase requests from last year were not in the markets best known for high and rising prices: the Northeast and California. The Florida utility Florida Power and Light received permission from state regulators for $7 billion worth of rate increases, the largest such increase among the group PowerLines tracked. That figure was negotiated down from about $10 billion.
The PowerLines data is telling many consumers something they already know. Electricity is getting more expensive, and they’re not happy about it.
“In a moment where affordability concerns and pocketbook concerns remain top of mind for American consumers, electricity and gas are the two fastest drivers,” Hua said. “That is creating this sense of public and consumer frustration that we're seeing.”
A federal judge in Massachusetts ruled that construction on Vineyard Wind could proceed.
The Vineyard Wind offshore wind project can continue construction while the company’s lawsuit challenging the Trump administration’s stop work order proceeds, judge Brian E. Murphy for the District of Massachusetts ruled on Tuesday.
That makes four offshore wind farms that have now won preliminary injunctions against Trump’s freeze on the industry. Dominion Energy’s Coastal Virginia offshore wind project, Orsted’s Revolution Wind off the coast of New England, and Equinor’s Empire Wind near Long Island, New York, have all been allowed to proceed with construction while their individual legal challenges to the stop work order play out.
The Department of the Interior attempted to pause all offshore wind construction in December, citing unspecified “national security risks identified by the Department of War.” The risks are apparently detailed in a classified report, and have been shared neither with the public nor with the offshore wind companies.
Vineyard Wind, a joint development between Avangrid Renewables and Copenhagen Infrastructure Partners, has been under construction since 2021, and is already 95% built. More than that, it’s sending power to Massachusetts customers, and will produce enough electricity to power up to 400,000 homes once it’s complete.
In court filings, the developer argued it was urgent the stop work order be lifted, as it would lose access to a key construction boat required to complete the project on March 31. The company is in the process of replacing defective blades on its last handful of turbines — a defect that was discovered after one of the blades broke in 2024, scattering shards of fiberglass into the ocean. Leaving those turbine towers standing without being able to install new blades created a safety hazard, the company said.
“If construction is not completed by that date, the partially completed wind turbines will be left in an unsafe condition and Vineyard Wind will incur a series of financial consequences that it likely could not survive,” the company wrote. The Trump administration submitted a reply denying there was any risk.
The only remaining wind farm still affected by the December pause on construction is Sunrise Wind, a 924-megawatt project being developed by Orsted and set to deliver power to New York State. A hearing for an injunction on that order is scheduled for February 2.