Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Economy

It’s Getting Harder to Close a Coal Plant

Fossil fuel plant retirements are slowing down, and projected load growth is to blame.

It’s Getting Harder to Close a Coal Plant
Illustration by Simon Abranowicz

To fully decarbonize the electricity system will require more than just the rapid deployment of non-carbon-emitting generation capacity, plus the transmission necessary to get that electricity to where it needs to go. It will also require that our existing stock of electricity generation — which is largely natural gas- and coal-powered — get mostly mothballed. So far, this process has been proceeding briskly. Renewable deployment is on the way up and is projected to accelerate, and older electricity generation was sliding quickly but gracefully into retirement — until recently.

Retirements of existing generation have slowed down dramatically in the first half of this year, which is on pace to be the slowest for existing generation retirements since 2011, according to new data from the Energy Information Administration.

In the first half of the year, some 5.1 gigawatts of generating capacity have been retired, and another 2.4 gigawatts are scheduled to be retired by year’s end, for a projected total of 7.5 retired gigawatts. From 2004 to 2023, by contrast, just over 12 gigawatts of capacity were retired each year on average, with almost 15 gigawatts retired per year this decade. Since 2022, according to EIA data, over 90% of retired capacity has been coal or natural gas.

What’s behind the slowdown? “Reliability is threatened because the grid conditions are tightening,” Douglas Giuffre, executive director of gas, power and renewables analysis at S&P Global Commodity Insights, explained in an email. “This is partly due to the recent pace of coal and natural gas retirements in the U.S., which worked off some of the excess capacity in power markets. Now we are seeing tighter reserve margins, and a relatively thin pipeline of new gas-fired projects that can come online quickly.” That’s especially concerning for utilities at a time when projected electricity demand is way, way up.

The wave of retirements was a national phenomenon, often having nothing to do with state-level plans to decarbonize. Coal and gas were being retired so steadily over the past 20 years not just because plants were aging, but also because power use was essentially flat from the early 2000s through, essentially, yesterday. This meant that older plants — especially dirty coal plants — became uneconomic to run, especially as natural gas prices began to fall.

Now, we are in a completely different world. Electricity use is forecast to start growing again, thanks to a buildout of new data centers and manufacturing, plus the ongoing electrification of automobiles and home heating and cooling.

The Southeast offers an example of how these trends have played out on the ground. In December 2020, the Mississippi Public Service Commission determined that the state had “excess reserves … largely due to decreases in projected load” and ordered a 950 megawatt reduction in generating capacity by Mississippi Power by 2027. A consulting firm hired by the commission determined that Plant Daniel, a coal plant, was “relatively inefficient compared to other available resources;” a few months later, the utility said it would decommission Plant Daniel by 2027.

Then Georgia Power, the utility that covers most of the state (and, like Mississippi Power, a subsidiary of Southern Company), rushed out a new three-year plan for its future power usage less than a year after finalizing its old one. Its demand forecast through the end of the decade had jumped from 400 megawatts to 6,600 megawatts, the result of a projected boom in data center construction.

“They came in with a preselected list of ways it wanted to meet that power need,” including buying power from Plant Daniel and new gas, Bob Sherrier, a staff attorney at the Southern Environmental Law Center, told me. Georgia Power told the state’s utility commission that to respond to growing demand it would need to extend contracts with its sister utility in Mississippi — which meant not only that Daniel would remain open for at least another year — and build new new plants that could run on gas or diesel, plans for which regulators approved on Tuesday. The utility also hinted that its existing plans to euthanize, for the most part, its coal-fired generation fleet by the end of 2028 were likely to be revised.

“To meet that projected need, the utilities are reverting to what they know, which is fossil fuels,” Sherrier said.

In vertically integrated markets, where utilities own generating assets and sell power to customers, environmentalists have seen delayed retirements and the building of new fossil plants as examples of utilities slipping into their comfort zone, building and operating expensive projects instead of developing or procuring renewables to handle rising demand.

But it's not just in vertically integrated markets where fossil retirements are being delayed. In Maryland, for instance, Brandon Shores, a coal-fired power plant that was scheduled to close in 2025, is staying open because PJM Interconnection, the regional electricity market, determined that a plan to replace it with battery storage was not a “realistic option at present” nor “technically viable to resolve the reliability violations or avoid the need for an RMR agreement at this time,” PJM president Manu Asthana said in a letter to Paul Pinsky, the director of the Maryland Energy Administration. The transmission investments required to make up the difference, meanwhile, would take several years.

Along with the neighboring Wagner plant, which burns a mix of coal, oil, and natural gas, Brandon Shores will likely stay open more than three years past its planned retirement date thanks to what’s known as a “reliability must run” contract, which “would put Maryland ratepayers on the hook for over $600 million dollars in out-of-market payments,” according to a letter written by several Maryland congressional representatives to PJM.

Environmental advocates have blamed PJM for not doing enough proactive transmission planning to account for predictable and scheduled plant retirements.

The slowing retirements mean that emissions from the electricity sector, which have been falling since the mid-2000s (with occasional bumps up as the economy has recovered from downturns), are expected to plateau over the next year or so. EIA forecasts show carbon dioxide emissions from electricity as essentially flat from 2023 to 2025, with increased natural gas emissions essentially offsetting falling coal emissions.

There is a bright side to the data, however. So far this year, the U.S. has installed just over 20 gigawatts of new generation, 80% of which has been solar and battery storage, including a 600-plus megawatt projects in Nevada and Texas. If added generation comes on in the second half of this year as planned, the EIA projects we’ll have 15 gigawatts of battery storage by year’s end. Along with the large and growing solar generation in states like California, Nevada, and Texas, the U.S. is getting closer to a grid that can, at least, run without carbon emissions day or night.

You’re out of free articles.

Use code: LABORDAY to save 20%.
Subscribe to access Heatmap’s exclusive polling and expert analysis of energy, climate change, and sustainability, now just $99/year $79.20/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Building Transmission Could Lower Electricity Costs

Talking with National Grid’s Matthew Satterwhite about his new report with S&P Global.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Matthew Satterwhite, head of U.S. policy for National Grid. This week National Grid released a report in collaboration with S&P Global I found noteworthy amidst the data center backlash, asserting that building new transmission lines can potentially reduce consumer costs. I reached out asking if we could chat about how this argument leans into the fight over hyperscale infrastructure. I found our conversation illuminating and educational.

The following Q&A was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

The Solar Farm-to-Data Center Switcheroo Hits a Snag

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Clark County, Nevada – The first data center approved on federal lands has hit a legal brick wall.

  • On Monday, the Townsite 2 solar farm-to-data center environmental review swap I’ve previously covered received a stay from the Interior Department’s board of appeals. David Gunter, a Biden appointee, ruled that the Center for Biological Diversity’s appeal of the permit flip was likely to succeed on the merits because a solar farm … is not a data center. Seems logical!
  • As I covered at the time, the Bureau of Land Management approved the environmental review swap claiming that a solar farm and a data center have essentially the same characteristics. It was a bold claim. Both the agency and Townsite said the characteristics would have substantially the same environmental impacts. Gunter shrugged off the claim idea, however, stating that statute requires projects to be both substantially similar and have equally similar impacts under the National Environmental Policy Act.
  • Crucially, Gunter also noted that the federal agency had never done an environmental review of any data centers under NEPA, so there’s not even a proper frame of reference. “BLM has not studied the Townsite data center project, or indeed any other data center project, in any environmental document,” he wrote.

2. Jackson County, Missouri – We have yet another high-profile case of a city councilor losing their job over voting for a data center, and this one’s a doozy.

Keep reading...Show less
Yellow
Spotlight

These 5 States Are Primed for a Data Center Pause

Where temporary moratoria could happen next.

A data center protest.
Heatmap Illustration/Getty Images

Brace yourself for more statewide data center moratoria.

So far there are only two full state-wide blocks on data center permits, in New York and Texas. At least fifteen states have moratorium legislation in the pipeline, but few if any of those bills stand a chance of becoming law in the short term. Here are five states, however, where a broad development pause may gain momentum in the next year or two — and all of them are crucial to watch this November.

Keep reading...Show less
Yellow