Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

America’s Largest Electricity Market Lurches Towards Reform

A conversation with a long-time watcher of the PJM on its new proposals

Auction.
Heatmap Illustration | Unsplash

America’s largest electricity market, the 13-state PJM Interconnection, is being forced to rapidly redesign how it works in order to meet its own reliability goals while trying to meet new demand from data centers and electrification.

The market has been in a multiyear rolling crisis as its auctions for capacity — the commitment generators can make to being available in times of high demand — hit a legal cap, resulting in billions of dollars of payouts from customers, leading to higher electricity prices in states like New Jersey.

Much of these payments are due to current and future demand from data centers, some $29.4 billion in the last four capacity auctions, according to the market’s independent monitor.

At the same time, the system isn’t able to procure enough capacity to meet its reliability goals, leading to tongue lashings and even threats of intervention from the Federal Energy Regulatory Commission, whose chair, Laura Swett, now regularly criticizes PJM in her public appearances.

On Monday, the market released a series of proposed reforms and initiatives to bring on new generation and attempt to make up for its reliability gap. This includes a supposedly one-off procurement of new capacity later this year that had been requested by the region’s governors and the White House, a new registry of large loads, and a kind of connect-and-manage system whereby new large loads that don’t have their own capacity will face curtailment during times of high demand.

In a letter to stakeholders, the PJM board said that new large energy users could be increasing demand by up to 70 gigawatts by 2038 (its all time record demand is around 170 gigawatts) while some 15 gigawatts of generation have been retired in the last few years. This combination has “placed increasing pressure on the region’s resource adequacy position” and “requires decisive action,” the board said.

I spoke to Jon Gordon, senior director at the clean energy trade group Advanced Energy United and a longtime PJM watcher about the proposals.

This interview has been condensed and edited for clarity.

Let’s start from the beginning: what was announced on Monday evening?

Just backing up a little bit, PJM has had two critical issue fast-path processes to try to determine how to protect ratepayers from data center related costs. The first one began in the fall and ended in December inconclusively. Then they started another one, which also ended somewhat inclusively. So that put the ball in the PJM board’s hands to review all the data, all the information that had been proposed, provided, and discussed, and come up with a plan of their own. And so they have officially done so. What we saw announced yesterday was PJM’s plan that they need to file at FERC very shortly in order to allow that September procurement.

And this is the backstop procurement that they agreed to with the White House and the governors?

Yes, in concept. The details needed to be ironed out. This is the board’s official proposal and it’s not going to happen until FERC approves it all, and FERC is under a lot of pressure to approve this.

In the letter to stakeholders, they presented three things: the registry, the procurement, and their version of connect and manage. How do these three ideas interact with each other? Why are they all proposed together?

The backstop procurement is the process whereby data centers can enter into contracts for their own power generation, and once they can demonstrate that they have a contract for power, they can then connect to the grid under this new proposal, connect and manage. And the registry is the tool by which to keep track of all this stuff: who are the data centers contracted that are eligible for this process?

Because you need all this detail to know how to curtail them. They’re going to be subject to involuntary curtailment up until the time that they are able to meet all their own needs with their own power generation. Meanwhile, they’re going to be curtailed by the local distribution companies — but the local distribution companies don’t have all the data they need to know which customers can be curtailed. So that’s where the registry comes in. They’re all part of the same overall package.

Let’s talk through the process here. Say, you’re building a new large load, maybe a 150-megawatt or 200-megawatt data center trying to get started in PJM. Under this process, what are the kinds of the things you have to check through to interconnect, and how will it be different than a few years ago?

Let’s talk about what’s going to happen now under these new rules. They’re going to have to enter into a bilateral contract with a supplier to demonstrate they’re making a good faith effort to secure the generation they need to meet all of their needs at some date in the future. Once they demonstrate that to PJM, they will then go to the registry for the connect-and-manage process. Which means that until their generation is 100% up and running, they will be subject to involuntary curtailment.

Before all this, a data center would connect like any other customer to the grid and start drawing power and any costs PJM would incur to connect them to the grid would be socialized across all PJM customers. That’s what’s been happening for many years. Ratepayers are paying for data centers that have come online previously.

How does this interact with PJM’s interconnection reforms? Would this allow data centers to interact more quickly while protecting customers from price increases? This is the dual goal of the White House and FERC.

Where the interconnection process comes into play is for the generator that wants to enter into a bilateral contract with the data center. They’re the ones that have to interconnect their generation.

So that generator hopefully is already in the queue. If not, it’s going to be a long while before they’re actually serving power to anyone. The queue is still super important here in terms of how long that data center is going to be subject to voluntary curtailment. The slower the interconnection queue is, and the slower that overall process of building this new generation is, the longer those data centers are going to be subject to involuntary curtailment. My understanding is that a lot of data centers are not very happy about that.

Is this set of proposals biased in any way towards a particular type of generation?

On its face, it really isn’t. The data centers are free to contract with whatever generation source they like.

We know that many of the hyperscalers committed to meeting their data center needs with carbon-free energy. I’m hopeful they’re going to make an effort to contract to the extent possible with solar and battery resources.

But I am concerned that just the sheer magnitude of the need means we can’t avoid building a lot of new natural gas to meet all that load. We really had to bring all of that wind and solar online.

Even though those sources are going to be faster and lower cost than gas, their intermittent nature and the sheer size of what’s required is going to make that challenging.

What are the next steps here?

Everything we’ve been discussing is completely unprecedented and is happening in a timeframe that’s unimaginable. Three years ago if PJM tried to take on what they’re taking on, it would be a three or four year stakeholder process and it’s taking months.

With all of that said, everything we’ve just discussed, according to PJM, is temporary. It’s meant to be a stopgap to get this market rolling with data centers that are anxious to connect and move forward.

PJM is calling this reliability backstop a one-time procurement.

A lot of folks have said — and I agree with them — there will probably be more than one of these.

The other thing that’s going on is that PJM has begun a process to redesign their entire market structure, what they’re calling a holistic market review. That’s in acknowledgment that the capacity market is broken and is not functioning as intended.

That’s another stakeholder process underway. That’s another heavy lift, which they hope to have in place in 2027. By the time this whole backup procurement process is over, they hope to have a new market in place. That’s an incredibly heavy lift.

You’re out of free articles.

Use code: LABORDAY to save 20%.
Subscribe to access Heatmap’s exclusive polling and expert analysis of energy, climate change, and sustainability, now just $99/year $79.20/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Building Transmission Could Lower Electricity Costs

Talking with National Grid’s Matthew Satterwhite about his new report with S&P Global.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Matthew Satterwhite, head of U.S. policy for National Grid. This week National Grid released a report in collaboration with S&P Global I found noteworthy amidst the data center backlash, asserting that building new transmission lines can potentially reduce consumer costs. I reached out asking if we could chat about how this argument leans into the fight over hyperscale infrastructure. I found our conversation illuminating and educational.

The following Q&A was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

The Solar Farm-to-Data Center Switcheroo Hits a Snag

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Clark County, Nevada – The first data center approved on federal lands has hit a legal brick wall.

  • On Monday, the Townsite 2 solar farm-to-data center environmental review swap I’ve previously covered received a stay from the Interior Department’s board of appeals. David Gunter, a Biden appointee, ruled that the Center for Biological Diversity’s appeal of the permit flip was likely to succeed on the merits because a solar farm … is not a data center. Seems logical!
  • As I covered at the time, the Bureau of Land Management approved the environmental review swap claiming that a solar farm and a data center have essentially the same characteristics. It was a bold claim. Both the agency and Townsite said the characteristics would have substantially the same environmental impacts. Gunter shrugged off the claim idea, however, stating that statute requires projects to be both substantially similar and have equally similar impacts under the National Environmental Policy Act.
  • Crucially, Gunter also noted that the federal agency had never done an environmental review of any data centers under NEPA, so there’s not even a proper frame of reference. “BLM has not studied the Townsite data center project, or indeed any other data center project, in any environmental document,” he wrote.

2. Jackson County, Missouri – We have yet another high-profile case of a city councilor losing their job over voting for a data center, and this one’s a doozy.

Keep reading...Show less
Yellow
Spotlight

These 5 States Are Primed for a Data Center Pause

Where temporary moratoria could happen next.

A data center protest.
Heatmap Illustration/Getty Images

Brace yourself for more statewide data center moratoria.

So far there are only two full state-wide blocks on data center permits, in New York and Texas. At least fifteen states have moratorium legislation in the pipeline, but few if any of those bills stand a chance of becoming law in the short term. Here are five states, however, where a broad development pause may gain momentum in the next year or two — and all of them are crucial to watch this November.

Keep reading...Show less
Yellow