Scoop: Trump to Permit Largest-Ever Gas Project in Just 7 Months

The facility will power OpenAI’s 10-gigawatt data center in Pike County, Ohio.

•
Donald Trump and rubber stamps.
Heatmap Illustration/Getty Images, Library of Congress

The Trump administration aims to complete its environmental review of what would be the biggest fossil fuel power project in the country in just a few months, Heatmap has learned.

This news follows Monday’s announcement from OpenAI that it intends to lease a new 10-gigawatt data center under development in Pike County, Ohio, financed by a mixture of money from a SoftBank subsidiary and the chip company Nvidia. This AI hyperscale facility — known as the PORTS-Pike project — is expected to draw power from the largest gas power facility ever built in the United States, a 9.2-gigawatt facility sited on federal lands that would be built and owned by the Energy Department.

According to OpenAI, the data center campus will be built and started up in phases, with the first 800 megawatts starting construction this year and operational in 2028. That first phase will rely mostly on existing power infrastructure operated by AEP Ohio. How things progress from there will depend at least in part on the permitting and construction timelines for the new power plant.

Building large infrastructure of any kind on federal land or with significant federal investment typically triggers a review under the National Environmental Policy Act. I’ve been curious to find out what kind of review this particular project was going to get, especially after the administration allowed a NEPA review for a solar project to be repurposed for a data center on federal lands earlier this year.

Turns out some information about the PORTS-Pike permitting process is public. Before OpenAI confirmed its involvement with the site, the Trump administration added the project to the federal FAST-41 permitting dashboard, where it posts regular updates on the timeline for getting federal sign-offs. Per the lone federal notice available about the PORTS-Pike project, it will include “several data center buildings and power plants.” That will require at least two federal greenlights: an Army Corps of Engineers permit and approval from the Fish and Wildlife Service, which is being consulted about potential endangered bats in the project area.

The NEPA permitting work for this historically large data center-plus-fossil fuel power project began on July 10 and will conclude on December 23, the day before Christmas Eve, according to the Trump administration’s estimates. This comes after paperwork to begin the review was submitted to the Army Corps in May, per the federal notice — a total timeline of about seven months.

Those familiar with NEPA and the debate over permitting reform will likely be surprised by the speed of this review. It’s moving fast in part because the project is receiving just an Environmental Assessment, the lesser and smaller type of analysis than the EIS. I do not know why the government decided to take this route because the government’s NEPA review determination is not currently public, but I have asked the Army Corps to explain this move.

I’m not sure exactly how air permitting will fit into this NEPA review, as the Clean Air Act isn’t listed as a review step on the federal dashboard. The Ohio EPA has primary authority over permitting projects like these under the Clean Air Act, and I’ve reached out to them to confirm whether PORTS has submitted a permitting application. The state agency’s permitting database does not have any information on air permitting for the project, though it does include reports from third-party consultants confirming wetlands and protected species warranted reviews from the Army Corps and Fish and Wildlife.

Lastly, these timetables are not sacrosanct. Under the Fiscal Responsibility Act of 2023, agencies are supposed to complete environmental assessments within one year, but nevertheless they regularly fail to meet them. The White House’s Council on Environmental Quality said in a report to Congress last year that from mid-2023 to mid-2025, the Army Corps was the agency that most often missed these statutory NEPA deadlines for environmental assessments.

Still, news of this speedy review for a priority Trump project is sure to excite pro-data center advocates who see expedited construction as an imperative in the global AI arms race. It’s also guaranteed to put a foul taste in the mouths of environmentalists already frustrated by federal revisions to NEPA regulations they say elide analysis of climate impacts.

What’s undebatable in all this is that, as my colleague Robinson Meyer wrote, the PORTS project could ignite a new era of mega-gas plants. This permitting timeline couldn’t be more important for the future of the data center boom — and the nation’s greenhouse gas emissions.

SB Energy, the SoftBank subsidiary behind the data center project, did not provide comment before publication.

🔒

You’ve reached your free article limit

Subscribe to Heatmap News for unlimited access to daily energy and climate coverage.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
AM Briefing

‘Starting to Fray’

On Greenland’s deepsea mining ban, Indonesia floating nuclear, and a solar boom

Data center construction.
Heatmap Illustration/Getty Images

Current conditions: Hurricane Trudy has weakened from its peak as a Category 2 storm but still threatens up to 8 inches of rain as it swirls off Baja California • A nor’easter is howling through the Mid-Atlantic this week, hammering the coast with winds of up to 70 miles per hour • A humid overcast has settled over Paris this week as French authorities struggle to regain control after protests over living costs gave way to anarchic riots.


THE TOP FIVE

1. America’s AI infrastructure boom ‘is starting to fray’

At least 47 major data center projects have been delayed, withdrawn, or blocked so far this year, according to data the regulatory intelligence service RegLayer shared with the Financial Times — and that may be a “conservative estimate.” Just 35% of planned data centers are “credible,” analysts told the newspaper, as more than 1,000 communities across the United States now have restrictions on artificial intelligence infrastructure. The data comes as investors look increasingly jittery about AI following ChatGPT-maker OpenAI’s missing a key revenue metric this year.

Keep reading...Show less
Blue
Spotlight

A Giant Data Center Offers a Permitting Reform Test Case

What would happen to Project Jupiter if the Bipartisan American Affordability and Jobs Act is passed?

Project Jupiter.
Heatmap Illustration/Project Jupiter, Library of Congress

One of the nation’s largest data centers is struggling under permitting woes. So let’s play a game: would the bipartisan permitting bill in Congress make the path easier, or might the federal legislation be irrelevant to large hyperscalers under development today?

Meet Project Jupiter, a mega project in southern New Mexico in Dona Ana County under development by Oracle and OpenAI, with financial backing from SoftBank and political support from the Trump administration for being a part of Stargate, a major Trump administration public-private initiative boosting AI development. Project Jupiter would be one of the largest data centers in the country if completed and currently is expected to run on a microgrid powered by fuel cells converting gas to electricity, which the developers claim will burn much cleaner than a typical off-grid gas turbine power plant.

Keep reading...Show less
Yellow
Hotspots

The Trump Administration Is Still Messing with Offshore Wind Farms

And more of the week’s top news around project fights.

The United States.
Heatmap Illustration/Getty Images

1. New England (and Maryland) – The Trump administration is still messing with offshore wind farms, even while trying to pass a permitting reform deal. Examining the court filings reveals why they may feel empowered to do it — and I’m not sure how this ends.

  • Last Friday, in a legal case brought by anti-wind activists, the Justice Department submitted a motion in federal court to send the construction and operations plan for Orsted’s Revolution Wind project in New England back to the Interior Department for more analysis. On Wednesday, the DOJ entered a similar motion in another case challenging the construction and operations plan for U.S. Wind’s MarWin project off the coast of Maryland in a lawsuit brought by the state’s coastal community of Ocean City.
  • Trump’s actions led some to question whether the president was sabotaging the deal, and others to claim the media coverage itself was an attempt to kill it. Going further, supporters of the bipartisan bill claimed the DOJ's motions were precisely why the bill should become law, implying it would guard offshore wind farms against this sort of maneuver.
  • However, for the bill’s backers, it’s worth considering why the Trump administration believes it has the legal authority to do this. It’s also time to ask whether the bill would actually protect these wind farms against this tactic.
  • To answer those questions, you have to rewind. On May 1, 2025, the Interior Department withdrew a Biden solicitor’s opinion instructing the agency to “strike a rational balance” between wind power and fishing interests. This revocation document is technically not in effect at the moment; one year later, a federal court ruled the opinion was potentially illegal as a part of a preliminary injunction on five anti-renewables actions requested by solar and wind trade groups. The Trump administration is contesting that ruling, and the administration has filed a notice of appeal.
  • In August, despite that opinion being in doubt, a federal judge granted Trump permission under the Outer Continental Shelf Lands Act to remand the construction and operations plan for the now-defunct Atlantic Shores offshore wind farm in the waters of New Jersey. U.S. District Judge Jia Cobb specifically wrote that Atlantic Shores failed to demonstrate the federal government had limitations under OSCLA on revisiting these plans and that the injunction from the litigation on appeal “did not prohibit all reevaluation of agency action.”
  • In the recent Revolution and MarWin filings, Trump’s Justice Department argues the construction and operations plans should be remanded under OSCLA without being vacated. The DOJ motions include claims that previous decision documents did not adequately explain impacts to commercial fishing and other industries that use OSCLA waters. It’s not clear if the administration will win these motions.
  • The bipartisan permitting bill would bar the Interior Department and other federal agencies from taking “any new action that would revoke, rescind, withdraw, terminate, suspend, amend, or alter a federal authorization or permit in effect on or after September 16, 2026,” or “any other action to interfere with or prevent the construction or operation at full capacity of a project that has secured all necessary federal authorizations and permits.” The restriction exempts cases where “the agency is required to take such action by order of a court.” As I wrote in our lengthy piece explaining the bill, this provision has a damages component that allows companies impacted by violations to pursue financial compensation.
  • Here’s the billion-dollar question I expect we won’t have answered unless the bill language is enacted and then litigated: Would the court order exception apply to rulings that grant these motions? Or would the developers be able to sue for damages?

2. Columbia County, N.Y. – New York’s renewable energy permitting office has rejected an upstate solar farm on farmland as a House Democrat representing the area joined hands with the Trump administration in publicly railing against the project.

Keep reading...Show less
Yellow