Q&A

Why Data Centers Need Battery Storage

A chat with Scott Blalock of Australian energy company Wärtsilä.

•
Scott Blalock.
Heatmap Illustration/Getty Images

This week’s conversation is with Scott Blalock of Australian energy company Wärtsilä. I spoke with Blalock this week amidst my reporting on transmission after getting an email asking whether I understood that data centers don’t really know how much battery storage they need. Upon hearing this, I realized I didn’t even really understand how data centers – still a novel phenomenon to me – were incorporating large-scale battery storage at all. How does that work when AI power demand can be so dynamic?

Blalock helped me realize that in some ways, it’s more of the same, and in others, it’s a whole new ballgame.

The following chat was lightly edited for clarity.

So help me understand how the battery storage side of your business is changing due to the rise in data center development.

We’re really in the early stages for energy storage. The boom is really in generation – batteries aren’t generators. They store, they shift, they smooth power, but they don’t generate the power from fuel. In this boom right now, everyone is trying to find either grid connections or on-site power generation. Those are the longest lead time items – they take a while – so we’re still in the early stages of those types of projects coming back and saying, we need to start procuring batteries. We need to start looking at the controls and how everything’s going to work together. That’s still a little bit in the future.

Are you seeing people deploy batteries responsibly, in an integrated way, or is it people unsure what they need?

There’s definitely uncertainty as to what they need. The requirements are still hard to nail down. A lot of the requirements come from the load curve of the AI workloads they’re doing, and that’s still a bit of a moving target. It’s the importance of knowing the whole system and planning that out in the modeling space.

The biggest space of all this is the load profile. Without a load profile, there’s uncertainty about what you’re going to need –

When you say load profile, what do you mean?

The AI workload. The GPUs. The volatility. In a synchronized training load, all of the GPUs are generally doing the same thing at the same time. They all reach a pause state at the same time, and you’re close to full power on the data center, and then they say, okay now we go idle. It has a little bit of a wait and then starts back up again.

It’s that square wave, very sharp changes in power – that’s the new challenge of an AI data center. That’s one of the new uses of BESS that’s being added compared to the traditional data center doing data storage. They’re more stable which use less power and are more stable.

The volatility is where some of the friction comes in, and that has to be handled by some technology.

So what you’re telling me is that data center developers do not know how much they need in terms of battery storage? Simply put, they don’t know how much power they need?

Traditionally, utility-scale batteries – the projects we’ve been doing – come from a PPA, an interconnect agreement. There’s something in place where they know exactly how many batteries they can install. They know how many megawatts they’re allowed to install. Then they come to us and they say, I need a 4-megawatt battery for two hours. Tell me how many batteries you’re going to give me.

In a data center, they don’t know that first number. They don’t know how many megawatts they need. So that’s the first question: well, how big of a battery do you need?

If you have a 1-gigawatt data center that means the load change is 60% of that – 600 megawatts is the step up-and-down. The starting point is 600 megawatts for two hours. That’s the starting point that’ll cover being able to take care of that volatility. The duration is a part of it, too. From there you get into more detailed studies.

When it comes to transmission, how much of a factor is it in how much storage a data center needs?

The first thing is whether it’s connected at all. The battery is a shock absorber for the whole system. If you are grid-connected, the BESS is still a stability asset – it’s still improving the power quality and stability at an interconnect. If you’re doing on-site generation, it becomes vital because you have only one system being controlled.

As far as when you talk about permitting and transmission, the details of that don’t really play that much into the BESS, but it’s tangentially related. The BESS is an important part of how you handle that situation. Whether you get to interconnect or not, it’s an extremely important asset in that mix.

With respect to the overall social license conversation, how does battery storage fit into the conversations around energy bills and strain on the grid?

Bias aside, I think it’s the most important piece.

If you look at the macro scale, it’s like transitioning to renewables where they’re intermittent; batteries turn intermittent generation from renewables into firm, dispatchable power. It’s still not going to be available all the time – you’re not going to turn a solar plant into a 24-hour baseload plant – but a battery allows you to shift the energy. It greatly alleviates the problem.

The other aspect is it’s a stability asset. The short version of that is you have big thermal plants – rotating metal masses that have momentum to them that stabilize everything on the grid. As you take those offline, the coal plants and the gas plants, the grid itself loses that inertia so it is more susceptible to spikes and failures because of small events. Batteries are able to synthesize that inertia.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

GoodPower Is Sussing Out What People Actually Want from Data Centers

Talking with Leah Qusba, the CEO of GoodPower.

•
Leah Qusba.
Heatmap Illustration

This week’s conversation is with Leah Qusba, CEO of GoodPower, which recently released a survey experiment you need to read. Conducted with Data for Progress, the project, published Monday, takes a unique approach to asking people why they opposed data centers for artificial intelligence and whether constructing renewable energy instead of gas power moves the needle at all in their support for AI infrastructure near them. Instead of just asking polling questions, they posed various hypothetical project designs to people — and the results were eye-popping. Turning to solar instead of gas? Might not be a panacea for gaining approval at the local level. Protecting electricity rates from going sky-high? Now that’s a way to get buy-in.

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

A First-Of-Its-Kind State of Emergency — Over a Permitting Pause

And more of the week’s top fights around development.

•
The United States.
Heatmap Illustration/Getty Images

1. Umatilla County, Oregon – A small town in Oregon this week declared a state of emergency over fears that a statewide pause on data center permits will harm its economy.

  • Five of the six people on the Umatilla city council voted to adopt a resolution formally calling for a state of emergency “due to the threat of widespread financial loss.” Umatilla City Manager Dave Stockdale told the council before the vote that the data center pause enacted by Governor Tina Kotek puts millions in tax revenue at risk. Other city staffers told the council that current budget reserves are healthy, but this could complicate a bond for a new police station and delay executing their city’s master plan.
  • Umatilla is home to more than 20 data center projects currently operating or under development, equal to roughly one-fifth of the state’s data center sector. Oregon law expressly grants cities and towns permission to declare a state of emergency over “financial loss.” And the Umatilla resolution is a clear legal threat; its text calls for “immediate reconsideration” of Governor Kotek’s directive pausing data center permits and “authorizes the city manager to coordinate with affected governments and legal counsel to pursue appropriate administrative and judicial remedies.”
  • To the best of our knowledge, this is the first time a municipal government has threatened legal action or declared a state of emergency over a state-wide permitting pause against data center development. It goes to show that what comes around goes around.

2. Saratoga County, New York – Is Trump’s country music superstar-turned-power-project combatant John Rich preparing to debut a new song about solar farms, or something more?

Keep reading...Show less
Yellow
Spotlight

The Most Important Data Center Election You’ve Never Heard Of

The race for the top job in McCracken County, Kentucky, might hinge on the importance of a community benefit agreement.

•
Paducah, Kentucky figures.
Heatmap Illustration/Library of Congress, U.S. Department of Energy

An election-season battle is brewing over what could be the nation’s first massive data center operating on federal land. And you almost certainly have never heard of it.

Come with me to McCracken County, Kentucky, just outside its largest city, Paducah, where the Energy Department is allowing new development at a large brownfield property. First constructed in the 1950s, the Paducah Gaseous Diffusion Plant was once the country’s only uranium enrichment facility, but it closed in 2010. Since then, and after years of cleanup, Paducah city officials and the McCracken County government have sought to revitalize and reindustrialize the site.

Keep reading...Show less
Yellow