Q&A

How the AI Boom Could Come Back Around for Natural Gas

A conversation with Enchanted Rock’s Joel Yu.

The Fight Q & A subject.
Heatmap Illustration

This week’s chat was with Joel Yu, senior vice president for policy and external affairs at the data center micro-grid services company Enchanted Rock. Now, Enchanted Rock does work I usually don’t elevate in The Fight – gas-power tracking – but I wanted to talk to him about how conflicts over renewable energy are affecting his business, too. You see, when you talk to solar or wind developers about the potential downsides in this difficult economic environment, they’re willing to be candid … but only to a certain extent. As I expected, someone like Yu who is separated enough from the heartburn that is the Trump administration’s anti-renewables agenda was able to give me a sober truth: Land use and conflicts over siting are going to advantage fossil fuels in at least some cases.

The following conversation was lightly edited for clarity.

Help me understand where, from your perspective, the generation for new data centers is going to come from. I know there are gas turbine shortages, but also that solar and wind are dealing with headwinds in the United States given cuts to the Inflation Reduction Act.

There are a lot of stories out there about certain technologies coming out to the forefront to solve the problem, whether it’s gas generation or something else. But the scale and the scope of this stuff … I don’t think there is a silver bullet where it’s all going to come from one place.

The Energy Department put out a request for information looking for ways to get to 3 gigawatts quickly, but I don’t think there is any way to do that quickly in the United States. It’s going to take work from generation developers, batteries, thermal generation, emerging storage technologies, and transmission. Reality is, whether it is supply chain issues or technology readiness or the grid’s readiness to accept that load generation profile, none of it is ready. We need investment and innovation on all fronts.

How do conflicts over siting play into solving the data center power problem? Like, how much of the generation that we need for data center development is being held back by those fights?

I do have an intuitive sense that the local siting and permitting concerns around data centers are expanding in scope from the normal noise and water considerations to include impacts to energy affordability and reliability, as well as the selection of certain generation technologies. We’ve seen diesel generation, for example, come into the spotlight. It’s had to do with data center permitting in certain jurisdictions, in places like Maryland and Minnesota. Folks are realizing that a data center comes with a big power plant – their diesel generation. When other power sources fall short, they’ll rely on their diesel more frequently, so folks are raising red flags there. Then, with respect to gas turbines or large cycle units, there’s concerns about viewsheds, noise and cooling requirements, on top of water usage.

How many data center projects are getting their generation on-site versus through the grid today?

Very few are using on-site generation today. There’s a lot of talk about it and interest, but in order to serve our traditional cloud services data center or AI-type loads, they’re looking for really high availability rates. That’s really costly and really difficult to do if you’re off the grid and being serviced by on-site generation.

In the context of policy discussions, co-location has primarily meant baseload resources on sites that are serving the data centers 24/7 – the big stories behind Three Mile Island and the Susquehanna nuclear plant. But to be fair, most data centers operational today have on-site generation. That’s their diesel backup, what backstops the grid reliability.

I think where you’re seeing innovation is modular gas storage technologies and battery storage technologies that try to come in and take the space of the diesel generation that is the standard today, increasing the capability of data centers in terms of on-site power relative to status quo. Renewable power for data centers at scale – talking about hundreds of megawatts at a time – I think land is constraining.

If a data center is looking to scale up and play a balancing act of competing capacity versus land for energy production, the competing capacity is extremely valuable. They’re going to prioritize that first and pack as much as they can into whatever land they have to develop. Data centers trying to procure zero-carbon energy are primarily focused on getting that energy over wires. Grid connection, transmission service for large-scale renewables that can match the scale of natural gas, there’s still very strong demand to stay connected to the grid for reliability and sustainability.

Have you seen the state of conflict around renewable energy development impact data center development?

Not necessarily. There is an opportunity for data center development to coincide with renewable project development from a siting perspective, if they’re going to be co-located or near to each other in remote areas. For some of these multi-gigawatt data centers, the reason they’re out in the middle of nowhere is a combination of favorable permitting and siting conditions for thousands of acres of data center building, substations and transmission –

Sorry, but even for projects not siting generation, if megawatts – if not gigawatts – are held up from coming to the grid over local conflicts, do you think that’s going to impact data center development at all? The affordability conversions? The environmental ones?

Oh yeah, I think so. In the big picture, the concern is if you can integrate large loads reliably and affordably. Governors, state lawmakers are thinking about this, and it’s bubbling up to the federal level. You need a broad set of resources on the grid to provide that adequacy. To the extent you hold up any grid resources, renewable or otherwise, you’re going to be staring down some serious challenges in serving the load. Virginia’s a good example, where local groups have held up large-scale renewable projects in the state, and Dominion’s trying to build a gas peaker plant that’s being debated, too. But in the meantime, it is Data Center Alley, and there are gigawatts of data centers that continue to want to get in and get online as quickly as possible. But the resources to serve that load are not coming online in time.

The push toward co-location probably does favor thermal generation and battery storage technologies over straight renewable energy resources. But a battery can’t cover 24/7 use cases for a data center, and neither will our unit. We’re positioned to be a bridge resource for 24/7 use for a few years until they can get more power to the market, and then we can be a flexible backup resource – not a replacement for the large-scale and transmission-connected baseload power resources, like solar and wind. Texas has benefited from huge deployments of solar and wind. That has trickled down to lower electricity costs. Those resources can’t do it alone, and there’s thermal to balance the system, but you need it all to meet the load growth.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

How a Giant Solar Farm Flopped in Rural Texas

Amarillo-area residents successfully beat back a $600 million project from Xcel Energy that would have provided useful tax revenue.

Texas and solar panels.
Heatmap Illustration/Getty Images

Power giant Xcel Energy just suffered a major public relations flap in the Texas Panhandle, scrubbing plans for a solar project amidst harsh backlash from local residents.

On Friday, Xcel Energy withdrew plans to build a $600 million solar project right outside of Rolling Hills, a small, relatively isolated residential neighborhood just north of the city of Amarillo, Texas. The project was part of several solar farms it had proposed to the Texas Public Utilities Commission to meet the load growth created by the state’s AI data center boom. As we’ve covered in The Fight, Texas should’ve been an easier place to do this, and there were few if any legal obstacles standing in the way of the project, dubbed Oneida 2. It was sited on private lands, and Texas counties lack the sort of authority to veto projects you’re used to seeing in, say, Ohio or California.

Keep reading...Show less
Yellow
Hotspots

A Data Center Is Dead, Long Live a Solar Farm

And more of the most important news about renewable projects fighting it out this week.

The United States.
Heatmap Illustration/Getty Images

1. Racine County, Wisconsin – Microsoft is scrapping plans for a data center after fierce opposition from a host community in Wisconsin.

  • The town of Caledonia was teed up to approve land rezoning for the facility, which would’ve been Microsoft’s third data center in the state. Dubbed “Project Nova,” the data center would have sat near an existing We Energies natural gas power plant.
  • After considerable pushback at community meetings, the tech giant announced Friday that it would either give up on the project or relocate it elsewhere to avoid more fervent opposition.
  • “While we have decided not to proceed with this particular site, we remain fully committed to investing in Southeast Wisconsin. We view this as a healthy step toward building a project that aligns with community priorities and supports shared goals,” Microsoft said in a statement published to its website, adding that it will attempt to “identify a site that supports both community priorities and our long-term development objectives.”
  • A review of the project opponents’ PR materials shows their campaign centered on three key themes: the risk of higher electricity bills, environmental impacts of construction and traffic, and a lack of clarity around how data centers could be a public good. Activists also frequently compared Project Nova to a now-infamous failed project in Wisconsin from the Chinese tech manufacturer Foxconn.

2. Rockingham County, Virginia – Another day, another chokepoint in Dominion Energy’s effort to build more solar energy to power surging load growth in the state, this time in the quaint town of Timberville.

Keep reading...Show less
Yellow
Spotlight

Wind Farm Trump Killed Derails a Major Transmission Line

The collateral damage from the Lava Ridge wind project might now include a proposed 285-mile transmission line initially approved by federal regulators in the 1990s.

The western United States.
Heatmap Illustration/Library of Congress, Getty Images

The same movement that got Trump to kill the Lava Ridge wind farm Trump killed has appeared to derail a longstanding transmission project that’s supposed to connect sought-after areas for wind energy in Idaho to power-hungry places out West.

The Southwest Intertie Project-North, also known as SWIP-N, is a proposed 285-mile transmission line initially approved by federal regulators in the 1990s. If built, SWIP-N is supposed to feed power from the wind-swept plains of southern Idaho to the Southwest, while shooting electrons – at least some generated from solar power – back up north into Idaho from Nevada, Utah, and Arizona. In California, regulators have identified the line as crucial for getting cleaner wind energy into the state’s grid to meet climate goals.

Keep reading...Show less
Yellow