How the AI Boom Could Come Back Around for Natural Gas

A conversation with Enchanted Rock’s Joel Yu.

The Fight Q & A subject.
Heatmap Illustration

This week’s chat was with Joel Yu, senior vice president for policy and external affairs at the data center micro-grid services company Enchanted Rock. Now, Enchanted Rock does work I usually don’t elevate in The Fight – gas-power tracking – but I wanted to talk to him about how conflicts over renewable energy are affecting his business, too. You see, when you talk to solar or wind developers about the potential downsides in this difficult economic environment, they’re willing to be candid … but only to a certain extent. As I expected, someone like Yu who is separated enough from the heartburn that is the Trump administration’s anti-renewables agenda was able to give me a sober truth: Land use and conflicts over siting are going to advantage fossil fuels in at least some cases.

The following conversation was lightly edited for clarity.

Help me understand where, from your perspective, the generation for new data centers is going to come from. I know there are gas turbine shortages, but also that solar and wind are dealing with headwinds in the United States given cuts to the Inflation Reduction Act.

There are a lot of stories out there about certain technologies coming out to the forefront to solve the problem, whether it’s gas generation or something else. But the scale and the scope of this stuff … I don’t think there is a silver bullet where it’s all going to come from one place.

The Energy Department put out a request for information looking for ways to get to 3 gigawatts quickly, but I don’t think there is any way to do that quickly in the United States. It’s going to take work from generation developers, batteries, thermal generation, emerging storage technologies, and transmission. Reality is, whether it is supply chain issues or technology readiness or the grid’s readiness to accept that load generation profile, none of it is ready. We need investment and innovation on all fronts.

How do conflicts over siting play into solving the data center power problem? Like, how much of the generation that we need for data center development is being held back by those fights?

I do have an intuitive sense that the local siting and permitting concerns around data centers are expanding in scope from the normal noise and water considerations to include impacts to energy affordability and reliability, as well as the selection of certain generation technologies. We’ve seen diesel generation, for example, come into the spotlight. It’s had to do with data center permitting in certain jurisdictions, in places like Maryland and Minnesota. Folks are realizing that a data center comes with a big power plant – their diesel generation. When other power sources fall short, they’ll rely on their diesel more frequently, so folks are raising red flags there. Then, with respect to gas turbines or large cycle units, there’s concerns about viewsheds, noise and cooling requirements, on top of water usage.

How many data center projects are getting their generation on-site versus through the grid today?

Very few are using on-site generation today. There’s a lot of talk about it and interest, but in order to serve our traditional cloud services data center or AI-type loads, they’re looking for really high availability rates. That’s really costly and really difficult to do if you’re off the grid and being serviced by on-site generation.

In the context of policy discussions, co-location has primarily meant baseload resources on sites that are serving the data centers 24/7 – the big stories behind Three Mile Island and the Susquehanna nuclear plant. But to be fair, most data centers operational today have on-site generation. That’s their diesel backup, what backstops the grid reliability.

I think where you’re seeing innovation is modular gas storage technologies and battery storage technologies that try to come in and take the space of the diesel generation that is the standard today, increasing the capability of data centers in terms of on-site power relative to status quo. Renewable power for data centers at scale – talking about hundreds of megawatts at a time – I think land is constraining.

If a data center is looking to scale up and play a balancing act of competing capacity versus land for energy production, the competing capacity is extremely valuable. They’re going to prioritize that first and pack as much as they can into whatever land they have to develop. Data centers trying to procure zero-carbon energy are primarily focused on getting that energy over wires. Grid connection, transmission service for large-scale renewables that can match the scale of natural gas, there’s still very strong demand to stay connected to the grid for reliability and sustainability.

Have you seen the state of conflict around renewable energy development impact data center development?

Not necessarily. There is an opportunity for data center development to coincide with renewable project development from a siting perspective, if they’re going to be co-located or near to each other in remote areas. For some of these multi-gigawatt data centers, the reason they’re out in the middle of nowhere is a combination of favorable permitting and siting conditions for thousands of acres of data center building, substations and transmission –

Sorry, but even for projects not siting generation, if megawatts – if not gigawatts – are held up from coming to the grid over local conflicts, do you think that’s going to impact data center development at all? The affordability conversions? The environmental ones?

Oh yeah, I think so. In the big picture, the concern is if you can integrate large loads reliably and affordably. Governors, state lawmakers are thinking about this, and it’s bubbling up to the federal level. You need a broad set of resources on the grid to provide that adequacy. To the extent you hold up any grid resources, renewable or otherwise, you’re going to be staring down some serious challenges in serving the load. Virginia’s a good example, where local groups have held up large-scale renewable projects in the state, and Dominion’s trying to build a gas peaker plant that’s being debated, too. But in the meantime, it is Data Center Alley, and there are gigawatts of data centers that continue to want to get in and get online as quickly as possible. But the resources to serve that load are not coming online in time.

The push toward co-location probably does favor thermal generation and battery storage technologies over straight renewable energy resources. But a battery can’t cover 24/7 use cases for a data center, and neither will our unit. We’re positioned to be a bridge resource for 24/7 use for a few years until they can get more power to the market, and then we can be a flexible backup resource – not a replacement for the large-scale and transmission-connected baseload power resources, like solar and wind. Texas has benefited from huge deployments of solar and wind. That has trickled down to lower electricity costs. Those resources can’t do it alone, and there’s thermal to balance the system, but you need it all to meet the load growth.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

How Trump’s Speed-to-Power Push for Data Centers Could Backfire

Will moving fast and breaking air permits exacerbate tensions with locals?

Donald Trump and Rick Perry.
Heatmap Illustration/Getty Images

The Trump administration is trying to ease data centers’ power permitting burden. It’s likely to speed things up. Whether it’ll kick up more dust for the industry is literally up in the air.

On Tuesday, the EPA proposed a rule change that would let developers of all stripes start certain kinds of construction before getting a historically necessary permit under the Clean Air Act. Right now this document known as a New Source Review has long been required before you can start building anything that will release significant levels of air pollutants – from factories to natural gas plants. If EPA finalizes this rule, it will mean companies can do lots of work before the actual emitting object (say, a gas turbine) is installed, down to pouring concrete for cement pads.

Keep reading...Show less
Yellow
Hotspots

South Carolina County Mulls Lifting Solar Ban

And more of the week’s top fights around development.

The United States.
Heatmap Illustration/Getty Images

1. Berkeley County, South Carolina – Forget about Richland County, Ohio. All eyes in Solar World should be on this county where officials are trying to lift a solar moratorium.

  • Berkeley County instituted a solar moratorium in 2023. Now RWE is asking the county to lift the moratorium and the county’s land use committee voted this week at a hearing to recommend doing so, citing concerns from state utility Santee Cooper about energy prices. The county has seen electricity prices rise roughly 20% over the past three years, according to our Electricity Price Hub.
  • “They flat out said they need more power. They’re not going to have enough power by 2029,” councilmember Amy Stern said at a hearing Monday. “We are going to have more of this [discussion]. The moratorium lift[ing], all it does is allow us to get more information.” RWE wants to rezone land for a utility-scale solar farm the company claims would provide 198 megawatts, enough power for 37,000 homes.
  • Some most vocally supportive of the moratorium packed the hearing room, becoming so boisterous the council threatened local sheriff intervention. This shouldn’t be surprising; public opinion modeling indicates overall support for renewable energy in Berkeley County but the area has a substantial opposition risk score – 62 – in the Heatmap Pro database.
  • I’m closely monitoring whether the outcry overrules concerns about energy prices and Berkeley County supervisor Johnny Cribb told attendees of the hearing he’s against lifting the moratorium: “I’m against large-scale solar farms in this county, because of the reality of our county.”

2. Hill County, Texas – We have our first Texas county trying to ban new data centers and it’s in one of the more conservative pockets of the state.

Keep reading...Show less
Yellow
Q&A

The Biggest Data Center Critic in Utah Politics

A conversation with Utah state senator Nate Blouin.

Nate Blouin.
Heatmap Illustration

This week’s conversation is with Utah state senator Nate Blouin – a candidate for the Democratic nomination to represent the state’s 1st Congressional District, which includes Salt Lake City. I reached out to Blouin amidst the outpouring of public attention on the Box Elder County data center project backed by celebrity investor Kevin O’Leary. His positions on data centers and energy development, including support for a national AI data center moratorium, make him a must-watch candidate for anyone in this year’s Democratic congressional primaries. (It’s worth noting this seat was recently redrawn in ways that made it further left.)

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow