How a Giant Solar Farm Flopped in Rural Texas

Amarillo-area residents successfully beat back a $600 million project from Xcel Energy that would have provided useful tax revenue.

•
Texas and solar panels.
Heatmap Illustration/Getty Images

Power giant Xcel Energy just suffered a major public relations flap in the Texas Panhandle, scrubbing plans for a solar project amidst harsh backlash from local residents.

On Friday, Xcel Energy withdrew plans to build a $600 million solar project right outside of Rolling Hills, a small, relatively isolated residential neighborhood just north of the city of Amarillo, Texas. The project was part of several solar farms it had proposed to the Texas Public Utilities Commission to meet the load growth created by the state’s AI data center boom. As we’ve covered in The Fight, Texas should’ve been an easier place to do this, and there were few if any legal obstacles standing in the way of the project, dubbed Oneida 2. It was sited on private lands, and Texas counties lack the sort of authority to veto projects you’re used to seeing in, say, Ohio or California.

But a full-on revolt from homeowners and realtors apparently created a public relations crisis.

Mere weeks ago, shortly after word of the project made its way through the small community that is Rolling Hills, more than 60 complaints were filed to the Texas Public Utilities Commission in protest. When Xcel organized a public forum to try and educate the public about the project’s potential benefits, at least 150 residents turned out, overwhelmingly to oppose its construction. This led the Minnesota-based power company to say it would scrap the project entirely.

Xcel has tried to put a happy face on the situation. “We are grateful that so many people from the Rolling Hills neighborhood shared their concerns about this project because it gives us an opportunity to better serve our communities,” the company said in a statement to me. “Moving forward, we will ask for regulatory approval to build more generation sources to meet the needs of our growing economy, but we are taking the lessons from this project seriously.”

But what lessons, exactly, could Xcel have learned? What seems to have happened is that it simply tried to put a solar project in the wrong place, prizing convenience and proximity to an existing electrical grid over the risk of backlash in an area with a conservative, older population that is resistant to change.

Just ask John Coffee, one of the commissioners for Potter County, which includes Amarillo, Rolling Hills, and a lot of characteristically barren Texas landscape. As he told me over the phone this week, this solar farm would’ve been the first utility-scale project in the county. For years, he said, renewable energy developers have explored potentially building a project in the area. He’s entertained those conversations for two big reasons – the potential tax revenue benefits he’s seen elsewhere in Texas; and because ordinarily, a project like Oneida 2 would’ve been welcomed in any of the pockets of brush and plain where people don’t actually live.

“We’re struggling with tax rates and increases and stuff. In the proper location, it would be well-received,” he told me. “The issue is, it’s right next to a residential area.”

Indeed, Oneida 2 would’ve been smack dab up against Rolling Hills, occupying what project maps show would be the land surrounding the neighborhood’s southeast perimeter – truly the sort of encompassing adjacency that anti-solar advocates like to describe as a bogeyman.

Cotton also told me he wasn’t notified about the project’s existence until a few weeks ago, at the same time resident complaints began to reach a fever pitch. He recalled hearing from homeowners who were worried that they’d no longer be able to sell their properties. When I asked him if there was any data backing up the solar farm’s potential damage to home prices, he said he didn’t have hard numbers, but that the concerns he heard directly from the head of Amarillo’s Realtors Association should be evidence enough.

Many of the complaints against Oneida 2 were the sort of stuff we’re used to at The Fight, including fears of fires and stormwater runoff. But Cotton said it really boiled down to property values – and the likelihood that the solar farm would change the cultural fabric in Rolling Hills.

“This is a rural area. There are about 300 homes out there. Everybody sitting out there has half an acre, an acre, two acres, and they like to enjoy the quiet, look out their windows and doors, and see some distance,” he said.

Ironically, Cotton opposed the project on the urging of his constituents, but is now publicly asking Xcel to continue to develop solar in the county. “Hopefully they’ll look at other areas in Potter County,” he told me, adding that at least one resident has already come to him with potential properties the company could acquire. “We could really use the tax money from it. But you just can’t harm a community for tax dollars. That’s not what I’m about.”

I asked Xcel how all this happened and what their plans are next. A spokesperson repeatedly denied my requests to discuss Oneida 2 in any capacity. In a statement, the company told me it “will provide updates if the project is moved to another site,” and that “the company will continue to evaluate whether there is another location within Potter County, or elsewhere, to locate the solar project.”

Meanwhile, Amarillo may be about to welcome data center development because of course, and there’s speculation the first AI Stargate facility may be sited near Amarillo, as well.

City officials will decide in the coming weeks on whether to finalize a key water agreement with a 5,600-acre private “hypergrid” project from Fermi America, a new company cofounded by former Texas governor Rick Perry, says will provide upwards of 11 gigawatts to help fuel artificial intelligence services. Fermi claims that at least 1 gigawatt of power will be available by the end of next year – a lot of power.

The company promises that its “hypergrid” AI campus will use on-site gas and nuclear generation, as well as contracted gas and solar capacity. One thing’s for sure – it definitely won’t be benefiting from a large solar farm nearby anytime soon.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Plus

The Promise and Peril of the Blue Wave for Renewables

Talking with Arnab Pal, the executive director of Deploy Action.

•
The Q&A subject.
Heatmap Illustration

This week’s conversation is with Arnab Pal, executive director of Deploy Action, president of Clean Infrastructure Advisors, and former principal advisor at the Energy Department’s Loan Programs Office under the Biden administration alongside Jigar Shah.

I reached out to Pal for guidance on where he saw state-level policy going around renewables development after the 2026 blue wave election. Simply put, few could’ve provided better guidance. We have no idea what could happen next after an unprecedented election result, but he couldn’t have been more clear-eyed and, as he put it to me, focused on the future. I appreciated our conversation and decided it was worthwhile to provide it to you in full.

Keep reading...Show less
Yellow
Spotlight

Was This Really the Data Center Election?

Evidence suggests data center concerns probably didn’t actually flip many votes.

•
Voting signs and a data center.
Heatmap Illustration/Getty Images, Library of Congress

This week’s midterm elections were undeniably horrible for the data center industry. But a closer look indicates dominant media narratives about the impact of AI infrastructure on voting behavior also deserve more scrutiny.

On election night, candidates who railed against data center sprawl during their campaigns won across the country, including statewide races in red areas. The most striking example was Gina Hinojosa, now governor-elect for the data center-centric state of Texas, who ran on instituting a complete pause on projects across the Lone Star State. So striking was her win, it sent AI and data center stocks into freefall. Cleanview, a clean energy news and data site, said Hinojosa’s pause, if put into effect, could affect up to 88.4 gigawatts of “planned” data center development, depending on how it's implemented.

Keep reading...Show less
Yellow
Hotspots

The Place Where a Candidate Promising to Do Less on Data Centers Actually Won

And more of the week’s top fights around development.

•
The United States.
Heatmap Illustration/Getty Images

1. McCracken County, Kentucky – A rare bright spot for the data center sector quietly occurred in deep red Kentucky in a race defined by what’ll likely be the first project built on federal land.

  • As I previously reported, a large data center project became the primary point of conflict in the race for McCracken County’s judge-executive. The incumbent Republican Craig Clymer had welcomed the project, and faced a challenge from independent George Bray, mayor of the county’s largest city of Paducah. Bray also supported the data center but said his city, which is adjacent to the project, should’ve received more demarcated benefits. Bray called for a community benefit agreement.
  • Turns out voters in McCracken County didn’t care enough about this issue to make a change and wanted to keep Clymer in office. He won handily, netting more than 12,000 votes to Bray’s roughly 7,600. It’s one of the few races across the country that went in favor of the candidate promising to do less when it came to data centers.

2. Pulaski County, Arkansas – After a blue wave election in Little Rock, this county government is on a collision course with data center development.

Keep reading...Show less
Yellow