The Trump Administration Is Now Delaying Renewable Projects It Thinks Are Ugly

The Army Corps of Engineers is out to protect “the beauty of the Nation’s natural landscape.”

Donald Trump, wetlands, and renewable energy.
Heatmap Illustration/Getty Images

A new Trump administration policy is indefinitely delaying necessary water permits for solar and wind projects across the country, including those located entirely on private land.

The Army Corps of Engineers published a brief notice to its website in September stating that Adam Telle, the Assistant Secretary of the Army for Civil Works, had directed the agency to consider whether it should weigh a project’s “energy density” – as in the ratio of acres used for a project compared to its power generation capacity – when issuing permits and approvals. The notice ended on a vague note, stating that the Corps would also consider whether the projects “denigrate the aesthetics of America’s natural landscape.”

Prioritizing the amount of energy generation per acre will naturally benefit fossil fuel projects and diminish renewable energy, which requires larger amounts of land to provide the same level of power. The Department of the Interior used this same tactic earlier in the year to delay permits.

Now we know the full extent of the delays wrought by that notice thanks to a copy of the Army Corps’ formal guidance on issuing permits under the Clean Water Act or approvals related to the Rivers and Harbors Act, a 1899 law governing discharges into navigable waters. That guidance was made public for the first time in a lawsuit filed in December by renewable trade associations against Trump’s actions to delay, pause, or deny renewables permits.

The guidance submitted in court by the trade groups states that the Corps will scrutinize the potential energy generation per acre of any permit request from an energy project developer, as well as whether an “alternative energy generation source can deliver the same amount of generation” while making less of an impact on the “aquatic environment.” The Corps is now also prioritizing permit applications for projects “that would generate the most annual potential energy generation per acre over projects with low potential generation per acre.”

Lastly, the Corps will also scrutinize “whether activities related to the projects denigrate the beauty of the Nation’s natural landscape” when deciding whether to issue these permits. That last factor – aesthetics – is in fact a part of the Army Corps’ permitting regulations, but I have not seen any previous administration halt renewable energy permits because officials think solar farms and wind turbines are an eyesore.

Jennifer Neumann, a former career Justice Department attorney who oversaw the agency’s water-related casework with the Army Corps for a decade, told me she had never seen the Corps cite aesthetics in this way. The issue has “never really been litigated,” she said. “I have never seen a situation where the Corps has applied [this].”

The renewable energy industry’s amended complaint in the lawsuit, which is slowly proceeding in federal court, claims the Corps’ guidance will lead to “many costly project redesigns” and delays, “resulting in contract penalties, cost hikes, and deferred revenue.” Other projects “may never get their Corps individual permits and thus will need to be canceled altogether.”

In addition, executives for the trade associations submitted a sworn declaration laying out how they’re being harmed by the Corps guidance, as well as a host of other federal actions against the renewable energy sector. To illustrate those harms they laid out an example: French energy developer ENGIE, they said, was required to “re-engineer” its Empire Prairie wind and solar farm in Missouri because the guidance “effectively precludes” it from getting a permit from the Army Corps. This cost ENGIE millions of dollars, per the declaration, and extended the construction timeline while ultimately also making the project less efficient.

Notably, Empire Prairie is located entirely on private land. It isn’t entirely clear from the declaration why the project had to be redesigned, and there is scant publicly available information about it aside from a basic website. The area where Empire Prairie is being built, however, is tricky for development; segments of the project are located in counties – DeKalb and Andrew – that have 88 and 99 opposition risk scores, respectively, per Heatmap Pro.

Renewable energy developers require these water permits from the Army Corps when their construction zone includes more than half an acre of federally designated wetlands or bodies of water protected under the Rivers and Harbors Act. Neumann told me that developers with impacts of half an acre or less may skirt the need for a permit application if their project qualifies for what’s known as a “nationwide permit,” which only requires verification from the Corps that a company complies with the requirements.

Even the simple verification process for Corps permits has been short-circuited by other actions from the administration. Developers are currently unable to access a crucial database overseen by the Fish and Wildlife Service to determine whether their projects impacts species protected under the Endangered Species Act, which in turn effectively “prevents wind and solar developers from (among other things) obtaining Corps nationwide permits for their projects,” according to the declaration from trade group executives.

But hey, look on the bright side. At least the Trump administration is in the initial phases of trying to pare back federal wetlands protections. So there’s a chance that eliminating federal environmental protections might benefit some solar and wind companies out there. How many? It’s quite unclear given the ever-changing nature of wetlands designations and opaque data available on how many projects are being built within those areas.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Building Transmission Could Lower Electricity Costs

Talking with National Grid’s Matthew Satterwhite about his new report with S&P Global.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Matthew Satterwhite, head of U.S. policy for National Grid. This week National Grid released a report in collaboration with S&P Global I found noteworthy amidst the data center backlash, asserting that building new transmission lines can potentially reduce consumer costs. I reached out asking if we could chat about how this argument leans into the fight over hyperscale infrastructure. I found our conversation illuminating and educational.

The following Q&A was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

The Solar Farm-to-Data Center Switcheroo Hits a Snag

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Clark County, Nevada – The first data center approved on federal lands has hit a legal brick wall.

  • On Monday, the Townsite 2 solar farm-to-data center environmental review swap I’ve previously covered received a stay from the Interior Department’s board of appeals. David Gunter, a Biden appointee, ruled that the Center for Biological Diversity’s appeal of the permit flip was likely to succeed on the merits because a solar farm … is not a data center. Seems logical!
  • As I covered at the time, the Bureau of Land Management approved the environmental review swap claiming that a solar farm and a data center have essentially the same characteristics. It was a bold claim. Both the agency and Townsite said the characteristics would have substantially the same environmental impacts. Gunter shrugged off the claim idea, however, stating that statute requires projects to be both substantially similar and have equally similar impacts under the National Environmental Policy Act.
  • Crucially, Gunter also noted that the federal agency had never done an environmental review of any data centers under NEPA, so there’s not even a proper frame of reference. “BLM has not studied the Townsite data center project, or indeed any other data center project, in any environmental document,” he wrote.

2. Jackson County, Missouri – We have yet another high-profile case of a city councilor losing their job over voting for a data center, and this one’s a doozy.

Keep reading...Show less
Yellow
Spotlight

These 5 States Are Primed for a Data Center Pause

Where temporary moratoria could happen next.

A data center protest.
Heatmap Illustration/Getty Images

Brace yourself for more statewide data center moratoria.

So far there are only two full state-wide blocks on data center permits, in New York and Texas. At least fifteen states have moratorium legislation in the pipeline, but few if any of those bills stand a chance of becoming law in the short term. Here are five states, however, where a broad development pause may gain momentum in the next year or two — and all of them are crucial to watch this November.

Keep reading...Show less