Spotlight

Trump’s Renewables Permitting Thaw Is Also a Legal Strategy

The administration has begun shuffling projects forward as court challenges against the freeze heat up.

Solar panels and Donald Trump.
Heatmap Illustration/Getty Images

The Trump administration really wants you to think it’s thawing the freeze on renewable energy projects. Whether this is a genuine face turn or a play to curry favor with the courts and Congress, however, is less clear.

In the face of pressures such as surging energy demand from artificial intelligence and lobbying from prominent figures on the right, including the wife of Trump’s deputy chief of staff, the Bureau of Land Management has unlocked environmental permitting processes in recent weeks for a substantial number of renewable energy projects. Public documents, media reports, and official agency correspondence with stakeholders on the ground all show projects that had ground to a halt now lurching forward.

What has gone relatively unnoticed in all this is that the Trump administration has used this momentum to argue against a lawsuit filed by renewable energy groups challenging Trump’s permitting freeze. In January, for instance, Heatmap was first to report that the administration had lifted its ban on eagle take permits for wind projects. As we predicted at the time, after easing that restriction, Trump’s Justice Department has argued that the judge in the permitting freeze case should reject calls for an injunction. “Arguments against the so-called Eagle Permit Ban are perhaps the easiest to reject. [The Fish and Wildlife Service] has lifted the temporary pause on the issuance of Eagle take permits,” DOJ lawyers argued in a legal brief in February.

On February 26, E&E News first reported on Interior’s permitting freeze melting, citing three unnamed career agency officials who said that “at least 20 commercial-scale” solar projects would advance forward. Those projects include each of the seven segments of the Esmeralda mega-project that Heatmap was first to report was killed last fall. E&E News also reported that Jove Solar in Arizona, the Redonda and Bajada solar projects in California and three Nevada solar projects – Boulder Solar III, Dry Lake East and Libra Solar – will proceed in some fashion. Libra Solar received its final environmental approval in December but hasn’t gotten its formal right-of-way for construction.

Since then, Heatmap has learned of four other projects on the list, all in Nevada: Mosey Energy Center, Kawich Energy Center, Purple Sage Energy Center and Rock Valley Energy Center.

Things also seem to be moving on the transmission front in ways that will benefit solar. BLM posted the final environmental impact statement for upgrades to NextEra’s GridLance West transmission project in Nevada, which is expected to connect to solar facilities. And NV Energy’s Greenlink North transmission line is now scheduled to receive a final federal decision in June.

On wind, the administration silently advanced the Lucky Star transmission line in Wyoming, which we’ve covered as a bellwether for the state of the permitting process. We were first to report that BLM sent local officials in Wyoming a draft environmental review document a year ago signaling that the transmission line would be approved — then the whole thing inexplicably ground to a halt. Now things are moving forward again. In early February, BLM posted the final environmental review for Lucky Star online without any public notice or press release.

There are certainly reasons why Trump would allow renewables development to move forward at this juncture.

The president is under incredible pressure to get as much energy as possible onto the electric grid to power AI data centers without causing undue harm to consumers’ pocketbooks. According to the Wall Street Journal, the oil industry is urging him to move renewables permitting forward so Democrats come back to the table on a permitting deal.

Then there’s the MAGAverse’s sudden love affair with solar energy. Katie Miller, wife of White House deputy chief of staff Stephen Miller, has suddenly become a pro-solar advocate at the same time as a PR campaign funded by members of American Clean Power claims to be doing paid media partnerships with her. (Miller has denied being paid by ACP or the campaign.) Former Trump senior adviser Kellyanne Conway is now touting polls about solar’s popularity for “energy security” reasons, and Trump pollster Tony Fabrizio just dropped a First Solar-funded survey showing that roughly half of Trump voters support solar farms.

This timing is also conspicuously coincidental. One day before the E&E News story, the Justice Department was granted an extension until March 16 to file updated rebuttals in the freeze case before any oral arguments or rulings on injunctions. In other court filings submitted by the Justice Department, BLM career staff acknowledge they’ve met with people behind multiple solar projects referenced in the lawsuit since it was filed. It wouldn’t be surprising if a big set of solar projects got their permitting process unlocked right around that March 16 deadline.

Kevin Emmerich, co-founder of Western environmental group Basin & Range Watch, told me it’s important to recognize that not all of these projects are getting final approvals; some of this stuff is more piecemeal or procedural. As an advocate who wants more responsible stewardship of public lands and is opposed to lots of this, Emmerich is actually quite troubled by the way Trump is going back on the pause. That is especially true after the Supreme Court’s 2025 ruling in the Seven Counties case, which limited the scope of environmental reviews, not to mention Trump-era changes in regulation and agency leadership.

“They put a lot of scrutiny on these projects, and for a while there we didn’t think they were going to move, period,” Emmerich told me. “We’re actually a little bit bummed out about this because some of these we identified as having really big environmental impacts. We’re seeing this as a perfect storm for those of us worried about public land being taken over by energy because the weakening of NEPA is going to be good for a lot of these people, a lot of these developers.”

BLM would not tell me why this thaw is happening now. When reached for comment, the agency replied with an unsigned statement that the Interior Department “is actively reviewing permitting for large-scale onshore solar projects” through a “comprehensive” process with “consistent standards” – an allusion to the web of review criteria renewable energy developers called a de facto freeze on permits. “This comprehensive review process ensures that projects — whether on federal, state, or private lands — receive appropriate oversight whenever federal resources, permits, or consultations are involved.”

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

The Data Center Transmission Brawls Are Just Getting Started

What happens when one of energy’s oldest bottlenecks meets its newest demand driver?

Power line construction.
Heatmap Illustration/Getty Images

Often the biggest impediment to building renewable energy projects or data center infrastructure isn’t getting government approvals, it’s overcoming local opposition. When it comes to the transmission that connects energy to the grid, however, companies and politicians of all stripes are used to being most concerned about those at the top – the politicians and regulators at every level who can’t seem to get their acts together.

What will happen when the fiery fights on each end of the wire meet the broken, unplanned spaghetti monster of grid development our country struggles with today? Nothing great.

Keep reading...Show less
Yellow
Hotspots

Will Maine Veto the First State-Wide Data Center Ban?

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Franklin County, Maine – The fate of the first statewide data center ban hinges on whether a governor running for a Democratic Senate nomination is willing to veto over a single town’s project.

  • On Wednesday, the Maine legislature passed a total ban on new data center projects through the end of 2027, making it the first legislative body to send such a bill to a governor’s desk. Governor Janet Mills, who is running for Democrats’ nomination to the Senate, opposed the bill prior to the vote on the grounds that it would halt a single data center project in a small town. Between $10 million and $12 million has already been sunk into renovating the site of a former paper mill in Jay, population 4,600, into a future data center. Mills implored lawmakers to put an exemption into the bill for that site specifically, stating it would otherwise cost too many jobs.
  • It’s unclear whether Mills will sign or veto the bill. Her office has not said whether she would sign the bill without the Jay exemption and did not reply to a request for comment. Neither did the campaign for Graham Platner, an Iraq War veteran and political novice running competitively against Mills for the Senate nomination. Platner has said little about data centers so far on the campaign trail.
  • It’s safe to say that the course of Democratic policy may shift if Mills – seen as the more moderate candidate of the two running for this nomination – signs the first state-wide data center ban. Should she do so and embrace that tack, it will send a signal to other Democratic politicians and likely accelerate a further shift into supporting wide-scale moratoria.

2. Jerome County, Idaho – The county home to the now-defunct Lava Ridge wind farm just restricted solar energy, too.

Keep reading...Show less
Yellow
Q&A

Why Data Centers Need Battery Storage

A chat with Scott Blalock of Australian energy company Wärtsilä.

Scott Blalock.
Heatmap Illustration/Getty Images

This week’s conversation is with Scott Blalock of Australian energy company Wärtsilä. I spoke with Blalock this week amidst my reporting on transmission after getting an email asking whether I understood that data centers don’t really know how much battery storage they need. Upon hearing this, I realized I didn’t even really understand how data centers – still a novel phenomenon to me – were incorporating large-scale battery storage at all. How does that work when AI power demand can be so dynamic?

Blalock helped me realize that in some ways, it’s more of the same, and in others, it’s a whole new ballgame.

Keep reading...Show less