Meta’s AI Buildout Will Require More Than 2 Gigawatts of New Gas-Fired Electricity — At Least

CEO Mark Zuckerberg confirmed the company’s expanding ambitions in a Threads post on Monday.

Electrical outlets and a computer chip
Justin Renteria/Getty Images

Meta is going big to power its ever-expanding artificial intelligence ambitions. It’s not just spending hundreds of millions of dollars luring engineers and executives from other top AI labs (including reportedly hundreds of millions of dollars for one engineer alone), but also investing hundreds of billions of dollars for data centers at the multi-gigawatt scale.

“Meta is on track to be the first lab to bring a 1GW+ supercluster online,” Meta founder and chief executive Mark Zuckerberg wrote on the company’s Threads platform Monday, confirming a recent report by the semiconductor and artificial intelligence research service Semianalysis.

That first gigawatt-level project, Semianalysis wrote, will be a data center in New Albany, Ohio, called Prometheus, due to be online in 2026, Ashley Settle, a Meta spokesperson, confirmed to me. Ohio — and New Albany specifically — is the home of several large data center projects, including an existing Meta facility.

At the end of last year, Zuckerberg said that a datacenter project in Northeast Louisiana, now publicly known as Hyperion, would take 2 gigawatts of electricity; in his post on Monday, he said it could eventually be as large as 5 gigawatts. To get a sense of the scale we’re talking about, a new, large nuclear reactor has about a gigawatt of capacity, while a newly built natural gas plant could supply only around 500 megawatts.

As one could perhaps infer from the fact that their size is quoted in gigawatts instead of square feet or number of GPUs, whether or not these data centers get built comes down to the ability to power them.

Citing information from the natural gas company Williams, Semianalysis reported that Meta “went full Elon mode” for the New Albany datacenter, i.e. is installed its own natural gas infrastructure. Specifically, Williams is building two 200-megawatt facilities, according to the gas developer and Semianalysis, for the Ohio project. (Williams did not immediately respond to a Heatmap request for comment.)

Does this mean Meta is violating its commitments to reach net zero? While the data center buildout may make those goals more difficult to achieve, Meta is still investing in new renewables even as it’s also bringing new gas online. Late last month, the company announced that it was procuring almost 800 new megawatts of renewables from projects to be built by Invenergy, including over 400 megawatts of solar in Ohio, roughly matching the on-site generation from the Prometheus project.

But there’s more to a data center’s climate footprint than what a big tech company does — or does not — build on site.

The Louisiana project, Hyperion, will also be served by new natural gas and renewables added to the grid. Entergy, the local utility, has proposed 1.5 gigawatts of natural gas generation near the Meta site and over 2 gigawatts of new natural gas in total, with another plant in the southern part of the state to help balance the addition of significant new load. In December, when the data center was announced, Meta said that it planned to “bring at least 1,500 megawatts of new renewable energy to the grid.” Entergy did not immediately respond to a Heatmap request for comment on its plans for the Hyperion project.

“Meta Superintelligence Labs will have industry-leading levels of compute and by far the greatest compute per researcher. I'm looking forward to working with the top researchers to advance the frontier!” Zuckerberg wrote.

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Sparks

New Jersey Admits Defeat on Offshore Wind (at Least for Now)

The state has terminated an agreement to develop substations and other necessary grid infrastructure to serve the now-canceled developments.

Mike Sherrill and Donald Trump.
Heatmap Illustration/Getty Images, Library of Congress

Crucial transmission for future offshore wind energy in New Jersey is scrapped for now.

The New Jersey Board of Public Utilities on Wednesday canceled the agreement it reached with PJM Interconnection in 2021 to develop wires and substations necessary to send electricity generated by offshore wind across the state. The board terminated this agreement because much of New Jersey’s expected offshore wind capacity has either been canceled by developers or indefinitely stalled by President Donald Trump, including the now-scrapped TotalEnergies projects scrubbed in a settlement with his administration.

Keep reading...Show less
Blue
Sparks

Federal Judge Breaks Trump’s Permitting Blockade

The opinion covered a host of actions the administration has taken to slow or halt renewables development.

Donald Trump, clean energy, and columns.
Heatmap Illustration/Getty Images

A federal court seems to have struck down a swath of Trump administration moves to paralyze solar and wind permits.

U.S. District Judge Denise Casper on Tuesday enjoined a raft of actions by the Trump administration that delayed federal renewable energy permits, granting a request submitted by regional trade groups. The plaintiffs argued that tactics employed by various executive branch agencies to stall permits violated the Administrative Procedures Act. Casper — an Obama appointee — agreed in a 73-page opinion, asserting that the APA challenge was likely to succeed on the merits.

Keep reading...Show less
Blue
Sparks

Exclusive: Data Centers Are Now More Controversial Than Wind Farms

Fights over AI-related developments outnumber those over wind farms in the Heatmap Pro database.

Protest signs.
Heatmap Illustration/Getty Images

Local data center conflicts in the U.S. now outnumber clashes over wind farms.

More than 270 data centers have faced opposition across the country compared to 258 onshore and offshore wind projects, according to a review of data collected by Heatmap Pro. Data center battles only recently overtook wind turbines, driven by the sudden spike in backlash to data center development over the past year. It’s indicative of how the intensity of the angst over big tech infrastructure is surging past current and historic malaise against wind.

Keep reading...Show less