Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

How the Interconnection Queue Could Make Qualifying for Tax Credits Next to Impossible

A renewable energy project can only start construction if it can get connected to the grid.

Power lines, money, the Capitol, and a map.
Heatmap Illustration/Getty Images

The clock is ticking for clean energy developers. With the signing of the One Big Beautiful Bill Act, wind and solar developers have to start construction (whatever that means) in the next 12 months and be operating no later than the end of 2027 to qualify for federal tax credits.

But projects can only get built if they can get connected to the grid. Those decisions are often out of the hands of state, local, or even federal policymakers, and are instead left up to utilities, independent system operators, or regional transmission organizations, which then have to study things like the transmission infrastructure needed for the project before they can grant a project permission to link up.

This process, from requesting interconnection to commercial operation, used to take two years on average as of 2008; by 2023, it took almost five years, according to the National Renewable Energy Laboratory. This creates what we call the interconnection queue, where likely thousands of gigawatts of proposed projects are languishing, unable to start construction. The inability to quickly process these requests adds to the already hefty burden of state, local, and federal permitting and siting — and could mean that developers will be locked out of tax credits regardless of how quickly they move.

There’s no better example of the tension between clean energy goals and the process of getting projects into service than the Mid-Atlantic, home to the 13-state electricity market known as PJM Interconnection. Many states in the region have mandates to substantially decarbonize their electricity systems, whereas PJM is actively seeking to bring new gas-fired generation onto the grid in order to meet its skyrocketing projections of future demand.

This mismatch between current supply and present-and-future demand has led to the price for “capacity” in PJM — i.e. what the grid operator has greed to pay in exchange for the ability to call on generators when they’re most needed — jumping by over $10 billion, leading to utility bill hikes across the system.

“There is definitely tension,” Abe Silverman, a senior research scholar at Johns Hopkins University and former general counsel for New Jersey’s utility regulator, told me.

While Silverman doesn’t think that PJM is “philosophically” opposed to adding new resources, including renewables, to the grid, “they don’t have urgency you might want them to have. It’s a banal problem of administrative competency rather than an agenda to stymie new resources coming on the grid.”

PJM is in the midst of a multiyear project to overhaul its interconnection queue. According to a spokesperson, there are around 44,500 megawatts of proposed projects that have interconnection agreements and could move on to construction. Of these, I calculated that about 39,000 megawatts are solar, wind, or storage. Another 63,000 megawatts of projects are in the interconnection queue without an agreement, and will be processed by the end of next year, the spokesperson said, likely making it impossible for wind and solar projects to be “placed in service” by 2028.

Even among the projects with agreements, “there probably will be some winnowing of that down,” Mark Repsher, a partner at PA Consulting Group, told me. “My guess is, of that 44,000 megawatts that have interconnection agreements, they may have other challenges getting online in the next two years.”

PJM has attempted to place the blame for project delays largely at the feet of siting, permitting, and operations challenges.

“Some [projects] are moving to construction, but others are feeling the headwinds of siting and permitting challenges and supply chain backlogs,” PJM’s executive vice president of operations, planning, and security Aftab Khan said in a June statement giving an update on interconnection reforms.

And on high prices, PJM has been increasingly open about blaming “premature” retirements of fossil fuel power plants.

In May, PJM said in a statement in response to a Department of Energy order to keep a dual-fuel oil and natural gas plant in Pennsylvania open that it “has repeatedly documented and voiced its concerns over the growing risk of a supply and demand imbalance driven by the confluence of generator retirements and demand growth. Such an imbalance could have serious ramifications for reliability and affordability for consumers.”

Just days earlier, in a statement ahead of a Federal Energy Regulatory Commission conference, PJM CEO Manu Asthana had fretted about “growing resource adequacy concerns” based on demand growth, the cost of building new generation, and, in a direct shot at federal and state policies that encouraged renewables and discouraged fossil fuels, “premature, primarily policy-driven retirements of resources continue to outpace the development of new generation.”

The Trump administration has echoed these worries for the whole nation’s electrical grid, writing in a report issued this week that “if current retirement schedules and incremental additions remain unchanged, most regions will face unacceptable reliability risks.” So has the North American Electric Reliability Corporation, which argued in a 2024 report that most of the U.S. and Canada “faces mounting resource adequacy challenges over the next 10 years as surging demand growth continues and thermal generators announce plans for retirement.”

State officials and clean energy advocates have instead placed the blame for higher costs and impending reliability gaps on PJM’s struggles to connect projects, how the electricity market is designed, and the operator’s perceived coolness towards renewables.

Pennsylvania Governor Josh Shapiro told The New York Times in June that the state should “re-examine” its membership in PJM following last year’s steep price hikes. In February, Virginia Governor Glenn Youngkin wrote a letter calling for Asthana to be fired. (He will leave the transmission organization by the end of the year, although PJM says the decision was made before Youngkin’s letter.)

That conflict will likely only escalate as developers rush to start projects — which they can only do if they can get an interconnection services agreement from PJM.

In contrast to Silverman, Tyson Slocum, director of Public Citizen’s energy program, told me that “PJM, internally and operationally, believes that renewables are a drag on the grid and that dispatchable generation, particularly fossil fuels and nuclear, are essential.”

In May, for instance, PJM announced that it had selected 51 projects for its “Reliability Resource Initiative,” a one-time special process for adding generation to the grid over the next five to six years. The winning bids overwhelmingly involved expanding existing gas-fired plants or building new ones.

The main barrier to getting the projects built that have already worked their way through the queue, Repsher told me, is “primarily permitting.” But even with new barriers thrown up by the OBBBA, “there’s going to be appetite for these projects,” thanks to high demand, Repsher said. “It’s really just navigating all the logistical hurdles.”

Some leaders of PJM states are working on the permitting and deployment side of the equation while also criticizing the electricity market. Pennsylvania’s Shapiro has proposed legislation that would set up a centralized state entity to handle siting for energy projects. Maryland Governor Wes Moore signed legislation in May that would accelerate permitting for energy projects, including preempting local regulations for siting solar.

New Jersey, on the other hand, is procuring storage projects directly.

The state has a mandate stemming from its Clean Energy Act of 2018 to add 2,000 megawatts of energy storage by 2030. In June, New Jersey’s utility regulator started a process to procure at least half of that through utility-scale projects, funded through an existing utility-bill-surcharge.

New Jersey regulators described energy storage as “the most significant source of near-term capacity,” citing specifically the fact that storage makes up the “bulk” of proposed energy capacity in New Jersey with interconnection approval from PJM.

While the regulator issued its order before OBBBA passed, the focus on storage ended up being advantageous. The bill treats energy storage far more generously than wind and solar, meaning that New Jersey could potentially expand its generation capacity with projects that are more likely to pencil due to continued access to tax credits. The state is also explicitly working around the interconnection queue, not raging against it: “PJM interconnection delays do not pose a significant obstacle to a Phase 1 transmission-scale storage procurement target of 1,000 MW,” the order said.

In the end, PJM and the states may be stuck together, and their best hope could be finding some way to work together — and they may not have any other choice.

“A well-functioning RTO is the best way to achieve both low rates for consumers and carbon emissions reductions,” Evan Vaughan, the executive director of MAREC Action, a trade group representing Mid-Atlantic solar, wind, and storage developers, told me. “I think governors in PJM understand that, and I think that they’re pushing on PJM.”

“I would characterize the passage of this bill as adding fuel to the fire that was already under states and developers — and even energy offtakers — to get more projects deployed in the region.”

Green

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Energy

Can Private Equity Give Minnesota Carbon-Free Electricity?

An agreement to privatize Minnesota Power has activists activated both for and against.

Can Private Equity Give Minnesota Carbon-Free Electricity?
iStock / Getty Images Plus

For almost as long as utilities have existed, they have attracted suspicion. They enjoy local monopolies over transmission (and, in some places, generation). They charge regulated prices for electricity and make their money through engaging in capital investments with a regulated rate of return. They don’t face competition. Consumer advocates habitually suspect utilities of padding out their investments and of maintaining excessive — if not corrupt — proximity to the regulators and politicians designated to oversee them, suspicions that have proved correct over and over again.

Environmental groups have joined this chorus, accusing utilities of slow-walking the energy transition and preferring investments in new, large gas plants and local transmission as opposed to renewables, demand response, and energy efficiency.

Keep reading...Show less
Blue
Climate Tech

ChemFinity Raises $7 Million For Critical Mineral Recycling

The Berkeley-based startup has a chemical refining method it hopes can integrate with other existing recycling operations.

Minerals and recycling.
Heatmap Illustration/Getty Images

Critical minerals are essential to the world’s most powerful clean energy technologies, from batteries and electric vehicles to power lines, wind turbines, and solar panels. But the vast majority of the U.S. mineral supply comes from countries such as China, putting supply chains for a whole host of decarbonization technologies at geopolitical and economic risk.

Recycling minerals domestically would go a long way toward solving this problem, which is exactly what ChemFinity, a new startup spun out of the University of California, Berkeley, is trying to do. The company claims its critical mineral recovery system will be three times cheaper, 99% cleaner, and 10 times faster than existing approaches found in the mining and recycling industries. And it just got its first big boost of investor confidence, raising a $7 million seed round led by the climate tech firms At One Ventures and Overture Ventures.

Keep reading...Show less
Green
Politics

AM Briefing: Bracing for Blame

On GOP lockstep on renewables, a wind win, and EPA’s battery bashing

Trump’s Energy Chief Braces for Blame Over Price Hikes
Heatmap Illustration/Getty Images

Current conditions: Hurricane Erin’s winds strengthen to 160 miles per hour as the Category 4 storm barrels toward the U.S. East Coast • Temperatures have dropped 20 degrees Fahrenheit in the U.S. Northeast as cooler air and storms sweep in • The death toll in Spain’s wildfires rises to four as the country calls in the military to deal with blazes.


Keep reading...Show less
Yellow