Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

How the Interconnection Queue Could Make Qualifying for Tax Credits Next to Impossible

A renewable energy project can only start construction if it can get connected to the grid.

Power lines, money, the Capitol, and a map.
Heatmap Illustration/Getty Images

The clock is ticking for clean energy developers. With the signing of the One Big Beautiful Bill Act, wind and solar developers have to start construction (whatever that means) in the next 12 months and be operating no later than the end of 2027 to qualify for federal tax credits.

But projects can only get built if they can get connected to the grid. Those decisions are often out of the hands of state, local, or even federal policymakers, and are instead left up to utilities, independent system operators, or regional transmission organizations, which then have to study things like the transmission infrastructure needed for the project before they can grant a project permission to link up.

This process, from requesting interconnection to commercial operation, used to take two years on average as of 2008; by 2023, it took almost five years, according to the National Renewable Energy Laboratory. This creates what we call the interconnection queue, where likely thousands of gigawatts of proposed projects are languishing, unable to start construction. The inability to quickly process these requests adds to the already hefty burden of state, local, and federal permitting and siting — and could mean that developers will be locked out of tax credits regardless of how quickly they move.

There’s no better example of the tension between clean energy goals and the process of getting projects into service than the Mid-Atlantic, home to the 13-state electricity market known as PJM Interconnection. Many states in the region have mandates to substantially decarbonize their electricity systems, whereas PJM is actively seeking to bring new gas-fired generation onto the grid in order to meet its skyrocketing projections of future demand.

This mismatch between current supply and present-and-future demand has led to the price for “capacity” in PJM — i.e. what the grid operator has greed to pay in exchange for the ability to call on generators when they’re most needed — jumping by over $10 billion, leading to utility bill hikes across the system.

“There is definitely tension,” Abe Silverman, a senior research scholar at Johns Hopkins University and former general counsel for New Jersey’s utility regulator, told me.

While Silverman doesn’t think that PJM is “philosophically” opposed to adding new resources, including renewables, to the grid, “they don’t have urgency you might want them to have. It’s a banal problem of administrative competency rather than an agenda to stymie new resources coming on the grid.”

PJM is in the midst of a multiyear project to overhaul its interconnection queue. According to a spokesperson, there are around 44,500 megawatts of proposed projects that have interconnection agreements and could move on to construction. Of these, I calculated that about 39,000 megawatts are solar, wind, or storage. Another 63,000 megawatts of projects are in the interconnection queue without an agreement, and will be processed by the end of next year, the spokesperson said, likely making it impossible for wind and solar projects to be “placed in service” by 2028.

Even among the projects with agreements, “there probably will be some winnowing of that down,” Mark Repsher, a partner at PA Consulting Group, told me. “My guess is, of that 44,000 megawatts that have interconnection agreements, they may have other challenges getting online in the next two years.”

PJM has attempted to place the blame for project delays largely at the feet of siting, permitting, and operations challenges.

“Some [projects] are moving to construction, but others are feeling the headwinds of siting and permitting challenges and supply chain backlogs,” PJM’s executive vice president of operations, planning, and security Aftab Khan said in a June statement giving an update on interconnection reforms.

And on high prices, PJM has been increasingly open about blaming “premature” retirements of fossil fuel power plants.

In May, PJM said in a statement in response to a Department of Energy order to keep a dual-fuel oil and natural gas plant in Pennsylvania open that it “has repeatedly documented and voiced its concerns over the growing risk of a supply and demand imbalance driven by the confluence of generator retirements and demand growth. Such an imbalance could have serious ramifications for reliability and affordability for consumers.”

Just days earlier, in a statement ahead of a Federal Energy Regulatory Commission conference, PJM CEO Manu Asthana had fretted about “growing resource adequacy concerns” based on demand growth, the cost of building new generation, and, in a direct shot at federal and state policies that encouraged renewables and discouraged fossil fuels, “premature, primarily policy-driven retirements of resources continue to outpace the development of new generation.”

The Trump administration has echoed these worries for the whole nation’s electrical grid, writing in a report issued this week that “if current retirement schedules and incremental additions remain unchanged, most regions will face unacceptable reliability risks.” So has the North American Electric Reliability Corporation, which argued in a 2024 report that most of the U.S. and Canada “faces mounting resource adequacy challenges over the next 10 years as surging demand growth continues and thermal generators announce plans for retirement.”

State officials and clean energy advocates have instead placed the blame for higher costs and impending reliability gaps on PJM’s struggles to connect projects, how the electricity market is designed, and the operator’s perceived coolness towards renewables.

Pennsylvania Governor Josh Shapiro told The New York Times in June that the state should “re-examine” its membership in PJM following last year’s steep price hikes. In February, Virginia Governor Glenn Youngkin wrote a letter calling for Asthana to be fired. (He will leave the transmission organization by the end of the year, although PJM says the decision was made before Youngkin’s letter.)

That conflict will likely only escalate as developers rush to start projects — which they can only do if they can get an interconnection services agreement from PJM.

In contrast to Silverman, Tyson Slocum, director of Public Citizen’s energy program, told me that “PJM, internally and operationally, believes that renewables are a drag on the grid and that dispatchable generation, particularly fossil fuels and nuclear, are essential.”

In May, for instance, PJM announced that it had selected 51 projects for its “Reliability Resource Initiative,” a one-time special process for adding generation to the grid over the next five to six years. The winning bids overwhelmingly involved expanding existing gas-fired plants or building new ones.

The main barrier to getting the projects built that have already worked their way through the queue, Repsher told me, is “primarily permitting.” But even with new barriers thrown up by the OBBBA, “there’s going to be appetite for these projects,” thanks to high demand, Repsher said. “It’s really just navigating all the logistical hurdles.”

Some leaders of PJM states are working on the permitting and deployment side of the equation while also criticizing the electricity market. Pennsylvania’s Shapiro has proposed legislation that would set up a centralized state entity to handle siting for energy projects. Maryland Governor Wes Moore signed legislation in May that would accelerate permitting for energy projects, including preempting local regulations for siting solar.

New Jersey, on the other hand, is procuring storage projects directly.

The state has a mandate stemming from its Clean Energy Act of 2018 to add 2,000 megawatts of energy storage by 2030. In June, New Jersey’s utility regulator started a process to procure at least half of that through utility-scale projects, funded through an existing utility-bill-surcharge.

New Jersey regulators described energy storage as “the most significant source of near-term capacity,” citing specifically the fact that storage makes up the “bulk” of proposed energy capacity in New Jersey with interconnection approval from PJM.

While the regulator issued its order before OBBBA passed, the focus on storage ended up being advantageous. The bill treats energy storage far more generously than wind and solar, meaning that New Jersey could potentially expand its generation capacity with projects that are more likely to pencil due to continued access to tax credits. The state is also explicitly working around the interconnection queue, not raging against it: “PJM interconnection delays do not pose a significant obstacle to a Phase 1 transmission-scale storage procurement target of 1,000 MW,” the order said.

In the end, PJM and the states may be stuck together, and their best hope could be finding some way to work together — and they may not have any other choice.

“A well-functioning RTO is the best way to achieve both low rates for consumers and carbon emissions reductions,” Evan Vaughan, the executive director of MAREC Action, a trade group representing Mid-Atlantic solar, wind, and storage developers, told me. “I think governors in PJM understand that, and I think that they’re pushing on PJM.”

“I would characterize the passage of this bill as adding fuel to the fire that was already under states and developers — and even energy offtakers — to get more projects deployed in the region.”

Green

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

GOP Lawmaker Asks FAA to Rescind Wind Farm Approval

And more on the week’s biggest fights around renewable energy.

The United States.
Heatmap Illustration/Getty Images

1. Benton County, Washington – The Horse Heaven wind farm in Washington State could become the next Lava Ridge — if the Federal Aviation Administration wants to take up the cause.

  • On Monday, Dan Newhouse, Republican congressman of Washington, sent a letter to the FAA asking them to review previous approvals for Horse Heaven, claiming that the project’s development would significantly impede upon air traffic into the third largest airport in the state, which he said is located ten miles from the project site. To make this claim Newhouse relied entirely on the height of the turbines. He did not reference any specific study finding issues.
  • There’s a wee bit of irony here: Horse Heaven – a project proposed by Scout Clean Energy – first set up an agreement to avoid air navigation issues under the first Trump administration. Nevertheless, Newhouse asked the agency to revisit the determination. “There remains a great deal of concern about its impact on safe and reliable air operations,” he wrote. “I believe a rigorous re-examination of the prior determination of no hazard is essential to properly and accurately assess this project’s impact on the community.”
  • The “concern” Newhouse is referencing: a letter sent from residents in his district in eastern Washington whose fight against Horse Heaven I previously chronicled a full year ago for The Fight. In a letter to the FAA in September, which Newhouse endorsed, these residents wrote there were flaws under the first agreement for Horse Heaven that failed to take into account the full height of the turbines.
  • I was first to chronicle the risk of the FAA grounding wind project development at the beginning of the Trump administration. If this cause is taken up by the agency I do believe it will send chills down the spines of other project developers because, up until now, the agency has not been weaponized against the wind industry like the Interior Department or other vectors of the Transportation Department (the FAA is under their purview).
  • When asked for comment, FAA spokesman Steven Kulm told me: “We will respond to the Congressman directly.” Kulm did not respond to an additional request for comment on whether the agency agreed with the claims about Horse Heaven impacting air traffic.

2. Dukes County, Massachusetts – The Trump administration signaled this week it will rescind the approvals for the New England 1 offshore wind project.

Keep reading...Show less
Yellow
Q&A

How Rep. Sean Casten Is Thinking of Permitting Reform

A conversation with the co-chair of the House Sustainable Energy and Environment Coalition

Rep. Sean Casten.
Heatmap Illustration

This week’s conversation is with Rep. Sean Casten, co-chair of the House Sustainable Energy and Environment Coalition – a group of climate hawkish Democratic lawmakers in the U.S. House of Representatives. Casten and another lawmaker, Rep. Mike Levin, recently released the coalition’s priority permitting reform package known as the Cheap Energy Act, which stands in stark contrast to many of the permitting ideas gaining Republican support in Congress today. I reached out to talk about the state of play on permitting, where renewables projects fit on Democrats’ priority list in bipartisan talks, and whether lawmakers will ever address the major barrier we talk about every week here in The Fight: local control. Our chat wound up immensely informative and this is maybe my favorite Q&A I’ve had the liberty to write so far in this newsletter’s history.

The following conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Spotlight

How to Build a Wind Farm in Trump’s America

A renewables project runs into trouble — and wins.

North Dakota and wind turbines.
Heatmap Illustration/Getty Images

It turns out that in order to get a wind farm approved in Trump’s America, you have to treat the project like a local election. One developer working in North Dakota showed the blueprint.

Earlier this year, we chronicled the Longspur wind project, a 200-megawatt project in North Dakota that would primarily feed energy west to Minnesota. In Morton County where it would be built, local zoning officials seemed prepared to reject the project – a significant turn given the region’s history of supporting wind energy development. Based on testimony at the zoning hearing about Longspur, it was clear this was because there’s already lots of turbines spinning in Morton County and there was a danger of oversaturation that could tip one of the few friendly places for wind power against its growth. Longspur is backed by Allete, a subsidiary of Minnesota Power, and is supposed to help the utility meet its decarbonization targets.

Keep reading...Show less
Yellow