PJM Is Paralyzed by Its Data Center Dilemma

Members of the nation’s largest grid couldn’t agree on a recommendation for how to deal with the surge of incoming demand.

Power lines.
Heatmap Illustration/Getty Images

The members of PJM Interconnection, the country’s largest electricity market, held an advisory vote Wednesday to help decide how the grid operator should handle the tidal wave of incoming demand from data centers. Twelve proposals were put forward by data center companies, transmission companies, power companies, utilities, state legislators, advocates, PJM’s market monitor, and PJM itself.

None of them passed.

“There was no winner here,” PJM chief executive Manu Asthana told the meeting following the announcement of the vote tallies. There was, however, “a lot of information in these votes,” he added. “We’re going to study them closely.”

The PJM board was always going to make the final decision on what it would submit to federal regulators, and will try to get something to the Federal Energy Regulatory Commission by the end of the year, Asthana said — just before he plans to step down as CEO.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort. The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development,” a PJM spokesperson said in a statement. “This vote is advisory to PJM’s independent Board. The Board can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.”

The surge in data center development — actual and planned — has thrown the 13-state PJM Interconnection into a crisis, with utility bills rising across the network due to the billions of dollars in payments required to cover the additional costs.

Those rising bills have led to cries of frustration from across the PJM member states — and from inside the house.

“The current supply of capacity in PJM is not adequate to meet the demand from large data center loads and will not be adequate in the foreseeable future,” PJM’s independent market monitor wrote in a memo earlier this month. “Customers are already bearing billions of dollars in higher costs as a direct result of existing and forecast data center load,” it said in a quarterly report released just a few days letter, pegging the added charges to ensure that generators will be available in times of grid stress due to data center development at over $16 billion.

PJM’s initial proposal to deal with the data center swell would have created a category for new large sources of demand on the system to interconnect without the backing of capacity; in return, they’d agree to have their power supply curtailed when demand got too high. The proposal provoked outrage from just about everyone involved in PJM, including data center developers and analysts who were open to flexibility in general, who said that the grid operator was overstepping its responsibilities.

PJM’s subsequent proposal would allow for voluntary participation in a curtailment program, but was lambasted by environmental groups like Evergreen Collaborative for not having “any semblance of ambition.” PJM’s own market monitor said that voluntary schemes to curtail power “are not equivalent to new generation,” and that instead data centers should “be required to bring their own new generation” — essentially to match their own demand with new supply.

A coalition of environmental groups, including the Natural Resources Defence Council and state legislators in PJM, said in their proposal that data centers should be required to bring their own capacity — crucially counting demand response (being paid to curtail power) as a source of capacity.

“The growth of data centers is colliding with the reality of the power grid,” Tom Rutigliano, who works on grid issues for the Natural Resources Defense Council, said in a statement. “PJM members weren’t able to see past their commercial interests and solve a critical reliability threat. Now the board will need to stand up and make some hard decisions.”

Those decisions will come without any consensus from members about what to do next.

“Just because none of these passed doesn’t mean that the board will not act,” David Mills, the chairman of PJM’s board of managers, said at the conclusion of the meeting. “We will make our best efforts to put something together that will address the issues.”

Blue

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Climate Tech

Lunar Energy Raises $232 Million to Scale Virtual Power Plants

The startup — founded by the former head of Tesla Energy — is trying to solve a fundamental coordination problem on the grid.

A Lunar Energy module.
Heatmap Illustration/Lunar Energy

The concept of virtual power plants has been kicking around for decades. Coordinating a network of distributed energy resources — think solar panels, batteries, and smart appliances — to operate like a single power plant upends our notion of what grid-scale electricity generation can look like, not to mention the role individual consumers can play. But the idea only began taking slow, stuttering steps from theory to practice once homeowners started pairing rooftop solar with home batteries in the past decade.

Now, enthusiasm is accelerating as extreme weather, electricity load growth, and increased renewables penetration are straining the grid and interconnection queue. And the money is starting to pour in. Today, home battery manufacturer and VPP software company Lunar Energy announced $232 million in new funding — a $102 million Series D round, plus a previously unannounced $130 million Series C — to help deploy its integrated hardware and software systems across the U.S.

Keep reading...Show less
Blue
Adaptation

Why Driverless Cars Still Can’t Handle Snow

Black ice is dangerous, even for the robots.

A robotaxi in the snow.
Heatmap Illustration/Getty Images

If all the snow and ice over the past week has you fed up, you might consider moving to San Francisco, Los Angeles, Phoenix, Austin, or Atlanta. These five cities receive little to no measurable snow in a given year; subtropical Atlanta technically gets the most — maybe a couple of inches per winter, though often none. Even this weekend’s bomb cyclone, which dumped 7 inches across parts of northeastern Georgia, left the Atlanta suburbs with too little accumulation even to make a snowman.

San Francisco and the aforementioned Sun Belt cities are also the five pilot locations of the all-electric autonomous-vehicle company Waymo. That’s no coincidence. “There is no commercial [automated driving] service operating in winter conditions or freezing rain,” Steven Waslander, a University of Toronto robotics professor who leads WinTOR, a research program aimed at extending the seasonality of self-driving cars, told me. “We don’t have it completely solved.”

Keep reading...Show less
Yellow
AM Briefing

Courting a Win

On the FREEDOM Act, Siemens’ bet, and space data centers

Doug Burgum.
Heatmap Illustration/Getty Images

Current conditions: After a brief reprieve of temperatures hovering around freezing, the Northeast is bracing for a return to Arctic air and potential snow squalls at the end of the week • Cyclone Fytia’s death toll more than doubled to seven people in Madagascar as flooding continues • Temperatures in Mongolia are plunging below 0 degrees Fahrenheit for the rest of the workweek.

THE TOP FIVE

1. Interior Secretary suggests Supreme Court could step in to kill offshore wind

Secretary of the Interior Doug Burgum suggested the Supreme Court could step in to overturn the Trump administration’s unbroken string of losses in all five cases where offshore wind developers challenged its attempts to halt construction on turbines. “I believe President Trump wants to kill the wind industry in America,” Fox Business News host Stuart Varney asked during Burgum’s appearance on Tuesday morning. “How are you going to do that when the courts are blocking it?” Burgum dismissed the rulings by what he called “court judges” who “were all at the district level,” and said “there’s always the possibility to keep moving that up through the chain.” Burgum — who, as my colleague Robinson Meyer noted last month, has been thrust into an ideological crisis over Trump’s actions toward Greenland — went on to reiterate the claims made in a Department of Defense report in December that sought to justify the halt to all construction on offshore turbines on the grounds that their operation could “create radar interference that could represent a tremendous threat off our highly populated northeast coast.” The issue isn’t new. The Obama administration put together a task force in 2011 to examine the problem of “radar clutter” from wind turbines. The Department of Energy found that there were ways to mitigate the issue, and promoted the development of next-generation radar that could see past turbines.

Keep reading...Show less
Red