The Fight

Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Spotlight

Is North Dakota Turning on Wind?

The state formerly led by Interior Secretary Doug Burgum does not have a history of rejecting wind farms – which makes some recent difficulties especially noteworthy.

•
Doug Burgum.
Heatmap Illustration/Getty Images, Library of Congress

A wind farm in North Dakota – the former home of Interior Secretary Doug Burgum – is becoming a bellwether for the future of the sector in one of the most popular states for wind development.

At issue is Allete’s Longspur project, which would see 45 turbines span hundreds of acres in Morton County, west of Bismarck, the rural state’s most populous city.

Sited amid two already operating wind farms, the project will feed power not only to North Dakotans but also to Minnesotans, who, in the view of Allete, lack the style of open plains perfect for wind farms found in the Dakotas. Allete subsidiary Minnesota Power announced Longspur in August and is aiming to build and operate it by 2027, in time to qualify for clean electricity tax benefits under a hastened phase-out of the Inflation Reduction Act.

On paper, this sounds achievable. North Dakota is one of the nation’s largest producers of wind-generated power and not uncoincidentally boasts some of cheapest electricity in the country at a time when energy prices have become a potent political issue. Wind project rejections have happened, but they’ve been rare.

Yet last week, zoning officials in Morton County bucked the state’s wind-friendly reputation and voted to reject Longspur after more than an hour of testimony from rural residents who said they’d had enough wind development – and that officials should finish the job Donald Trump and Doug Burgum started.

Across the board, people who spoke were neighbors of existing wind projects and, if built, Longspur. It wasn’t that they didn’t want any wind turbines – or “windmills,” as they called them, echoing Trump’s nomenclature. But they didn’t want more of them. After hearing from the residents, zoning commission chair Jesse Kist came out against the project and suggested the county may have had enough wind development for now.

“I look at the area on this map and it is plum full of wind turbines, at this point,” Kist said, referencing a map where the project would be situated. “And we have a room full of people and we heard only from landowners, homeowners in opposition. Nobody in favor.”

This was a first for the county, zoning staff said, as public comment periods weren’t previously even considered necessary for a wind project. Opposition had never shown up like this before. This wasn’t lost on Andy Zachmeier, a county commissioner who also sits on the zoning panel, who confessed during the hearing that the county was approaching the point of overcrowding. “Sooner or later, when is too many enough?” he asked.

Zachmeier was ultimately one of the two officials on the commission to vote against rejecting Longspur. He told me he was looking to Burgum for a signal.

“The Green New Deal – I don’t have to like it but it’s there,” he said. “Governor Burgum is now our interior secretary. There’s been no press conferences by him telling the president to change the Green New Deal.” Zachmeier said it was not the county’s place to stop the project, but rather that it was up to the state government, a body Burgum once led. “That’s probably going to have to be a legislative question. There’s been nothing brought forward where the county can say, We’ve been inundated and we’ve had enough,” he told me.

The county commission oversees the zoning body, and on Wednesday, Zachmeier and his colleagues voted to deny Longspur’s rejection and requested that zoning officials reconsider whether the denial was a good idea, or even legally possible. Unlike at the hearing last week, landowners whose property includes the wind project area called for it to proceed, pointing to the monetary benefits its construction would provide them.

“We appreciate the strong support demonstrated by landowners at the recent Commission meeting,” Allete’s corporate communications director Amy Rutledge told me in an email. “This region of North Dakota combines exceptional wind resources, reliable electric transmission infrastructure, and a strong tradition of coexisting seamlessly with farming and ranching activities.”

I personally doubt that will be the end of Longspur’s problems before the zoning board, and I suspect this county will eventually restrict or even ban future wind projects. Morton County’s profile for renewables development is difficult, to say the least; Heatmap Pro’s modeling gives the county an opposition risk score of 92 because it’s a relatively affluent agricultural community with a proclivity for cultural conservatism – precisely the kind of bent that can be easily swayed by rhetoric from Trump and his appointees.

Morton County also has a proclivity for targeting advanced tech-focused industrial development. Not only have county officials instituted a moratorium on direct air capture facilities, they’ve also banned future data center and cryptocurrency mining projects.

Neighboring counties have also restricted some forms of wind energy infrastructure. McClean County to the north, for example, has instituted a mandatory wind turbine setback from the Missouri River, and Stark County to the west has a 2,000-foot property setback from homes and public buildings.

In other words, so goes Burgum, may go North Dakota? I suppose we’ll find out.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Hotspots

Meta Data Center Federal Pipeline Review Due Early Next Year

And more of the week’s top fights around development.

•
The United States.
Heatmap Illustration/Getty Images

1. Richland Parish, Louisiana – Gird your loins for the coming fight over the Meta Hyperion data center’s gas pipeline.

  • On Wednesday, the Federal Energy Regulatory Commission laid out plans for an environmental assessment of the Entergy pipeline for the Meta data center under the National Environmental Policy Act and stated it’ll be issued in early January 2027. Federal agencies have been ordered by the panel to complete any remaining decisions on authorizations by April.
  • The decision to do an environmental assessment under NEPA will be controversial. The Sierra Club filed comments to FERC stating they wanted an environmental impact statement instead that took into account the environmental impacts of the data center being fed by the pipeline, as well as a review of the project’s cumulative impacts, as the activist group said they’re explicitly linked to the data center’s operations. “The power stations and data center are not remote or speculative developments unrelated to the proposed action,” their comments read.
  • This is quite similar to what’s playing out with the Green Chile pipeline in New Mexico for Oracle and OpenAI’s Project Jupiter, which we recently explained could turn into litigation with high stakes for future gas pipelines linked to data centers. But to me, this conflict with Meta feels like it has more at stake for this individual project, as it’s playing out while construction on gas power plants for the data center has been underway for almost a year after earlier being blessed by state regulators.
  • I asked Sierra Club what could happen next. Eric Huber, one of their managing attorneys, told me on Thursday, “I heard the EA is expected in January, but we are in wait and see mode and will decide on further steps when it comes out.” Meta and Entergy did not respond to a request for comment.

2. Spartanburg County, South Carolina – I have one last data center race to tell you to watch on Tuesday: South Carolina’s 4th, on the northern rim of the state.

Keep reading...Show less
Yellow
Plus

Is the Election Really About Data Centers?

Talking with Kevin Gundersen, the head of public affairs for Digital Realty.

•
Kevin Gundersen
Heatmap Illustration

This week’s conversation is with Kevin Gundersen, head of public affairs for data center developer Digital Realty. On Wednesday, Digital Realty released a fascinating poll as part of Infrastructure for America, a pro-data center organization that also includes Compass, Vantage Data Centers, and QTS. The poll pushed back on the idea that we’re currently in the middle of a “data center election”; instead, it found most voters are not expected to choose their national elected officials based on a politician’s stance on data centers.

I reached out to folks involved in the poll's release, and they put me in touch with Gundersen, whom I’ve met before and consider to be a straight shooter. He accepted my invitation to do a candid hot-seat chat about the findings, his thoughts on all the data center attack ads, and whether his industry’s actually recovering any ground with the American people.

Keep reading...Show less
Yellow
Spotlight

Trump Hasn’t Been Advancing New Wind Farms During Permitting Talks

Only upgrades for pre-existing wind projects have been approved.

••
Donald Trump.
Heatmap Illustration/Getty Images

In September, the Trump administration told a reporter that the president directed the Pentagon to finally process wind projects through routine airspace approvals as required under a court order. By doing this, it created the appearance of real headway and good faith in talks with Democrats in Congress on energy permitting legislation before the November midterm elections.

But the White House’s assurances are not what they seem.

Keep reading...Show less