How a Carbon Pipeline Is Turning Iowa Against Wind

Long Islanders, meanwhile, are showing up in support of offshore wind, and more in this week’s edition of The Fight.

Iowa.
Heatmap Illustration/Getty Images, Library of Congress

Local renewables restrictions are on the rise in the Hawkeye State – and it might have something to do with carbon pipelines.

Iowa’s known as a renewables growth area, producing more wind energy than any other state and offering ample acreage for utility-scale solar development. This has happened despite the fact that Iowa, like Ohio, is home to many large agricultural facilities – a trait that has often fomented conflict over specific projects. Iowa has defied this logic in part because the state was very early to renewables, enacting a state portfolio standard in 1983, signed into law by a Republican governor.

But something else is now on the rise: Counties are passing anti-renewables moratoria and ordinances restricting solar and wind energy development. We analyzed Heatmap Pro data on local laws and found a rise in local restrictions starting in 2021, leading to nearly 20 of the state’s 99 counties – about one fifth – having some form of restrictive ordinance on solar, wind or battery storage.

What is sparking this hostility? Some of it might be counties following the partisan trend, as renewable energy has struggled in hyper-conservative spots in the U.S. But it may also have to do with an outsized focus on land use rights and energy development that emerged from the conflict over carbon pipelines, which has intensified opposition to any usage of eminent domain for energy development.

The central node of this tension is the Summit Carbon Solutions CO2 pipeline. As we explained in a previous edition of The Fight, the carbon transportation network would cross five states, and has galvanized rural opposition against it. Last November, I predicted the Summit pipeline would have an easier time under Trump because of his circle’s support for oil and gas, as well as the placement of former North Dakota Governor Doug Burgum as interior secretary, as Burgum was a major Summit supporter.

Admittedly, this prediction has turned out to be incorrect – but it had nothing to do with Trump. Instead, Summit is now stalled because grassroots opposition to the pipeline quickly mobilized to pressure regulators in states the pipeline is proposed to traverse. They’re aiming to deny the company permits and lobbying state legislatures to pass bills banning the use of eminent domain for carbon pipelines. One of those states is South Dakota, where the governor last month signed an eminent domain ban for CO2 pipelines. On Thursday, South Dakota regulators denied key permits for the pipeline for the third time in a row.

Another place where the Summit opposition is working furiously: Iowa, where opposition to the CO2 pipeline network is so intense that it became an issue in the 2020 presidential primary. Regulators in the state have been more willing to greenlight permits for the project, but grassroots activists have pressured many counties into some form of opposition.

The same counties with CO2 pipeline moratoria have enacted bans or land use restrictions on developing various forms of renewables, too. Like Kossuth County, which passed a resolution decrying the use of eminent domain to construct the Summit pipeline – and then three months later enacted a moratorium on utility-scale solar.

I asked Jessica Manzour, a conservation program associate with Sierra Club fighting the Summit pipeline, about this phenomenon earlier this week. She told me that some counties are opposing CO2 pipelines and then suddenly tacking on or pivoting to renewables next. In other cases, counties with a burgeoning opposition to renewables take up the pipeline cause, too. In either case, this general frustration with energy companies developing large plots of land is kicking up dust in places that previously may have had a much lower opposition risk.

“We painted a roadmap with this Summit fight,” said Jess Manzour, a campaigner with Sierra Club involved in organizing opposition to the pipeline at the grassroots level, who said zealous anti-renewables activists and officials are in some cases lumping these items together under a broad umbrella. ”I don’t know if it’s the people pushing for these ordinances, rather than people taking advantage of the situation.”

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

The Trump Administration Is Now Delaying Renewable Projects It Thinks Are Ugly

The Army Corps of Engineers is out to protect “the beauty of the Nation’s natural landscape.”

Donald Trump, wetlands, and renewable energy.
Heatmap Illustration/Getty Images

A new Trump administration policy is indefinitely delaying necessary water permits for solar and wind projects across the country, including those located entirely on private land.

The Army Corps of Engineers published a brief notice to its website in September stating that Adam Telle, the Assistant Secretary of the Army for Civil Works, had directed the agency to consider whether it should weigh a project’s “energy density” – as in the ratio of acres used for a project compared to its power generation capacity – when issuing permits and approvals. The notice ended on a vague note, stating that the Corps would also consider whether the projects “denigrate the aesthetics of America’s natural landscape.”

Keep reading...Show less
Yellow
Hotspots

A Data Center Dies in Wisconsin

Plus more of the week’s biggest renewable energy fights.

The United States.
Heatmap Illustration/Getty Images

Dane County, Wisconsin – The QTS data center project we’ve been tracking closely is now dead, after town staff in the host community of DeForest declared its plans “unfeasible.”

  • As I previously explained to Fight readers, this QTS project was a quintessential data center conflict. Not only was it situated in a blue county inside of a purple state, but a recent imbroglio over emails between the village mayor and QTS have made it a key example of how private conversations between tech companies and local governments can tarnish the odds of getting a data center permitted.
  • Late Tuesday, DeForest town staff issued a public statement disclosing they would recommend rejecting QTS’ petition to annex land for construction, without which the developer can’t build. A vote on whether to formally deny the petition was scheduled for February 3.
  • If the town rejects the project, the statement reads, DeForest staff expect QTS to “formally withdraw” its request for changes to land zoning plans and the annexation application. The town also cited vociferous opposition to the project, declaring: “The Village of DeForest appreciates the dedicated engagement of our community. Engagement is at the core of democracy. Reviewing public information, participating in public meetings, and discussing potential opportunities and impacts are all important civic activities.”
  • I was prepared to wait and see what happened at the public meeting before declaring this project dead in the water, but QTS itself has gone and done it : “Through our engagement, it has become clear that now is not the right time for our proposed project to move forward in DeForest.”

Marathon County, Wisconsin – Elsewhere in Wisconsin, this county just voted to lobby the state’s association of counties to fight for more local control over renewable energy development.

Keep reading...Show less
Yellow
Q&A

How Data Centers Became an Election Issue in Georgia

A conversation with Georgia Conservation Voters’ Connie Di Cicco.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Connie Di Cicco, legislative director for Georgia Conservation Voters. I reached out to Connie because I wanted to best understand last November’s Public Service Commission elections which, as I explained at the time, focused almost exclusively on data center development. I’ve been hearing from some of you that you want to hear more about how and why opposition to these projects has become so entrenched so quickly. Connie argues it’s because data centers are a multi-hit combo of issues at the top of voters’ minds right now.