Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Sparks

The Mega Freeze of 2022 Is Still Haunting Power Plants

We’re still coming to terms with Winter Storm Elliot.

Winter Storm Elliott.
Heatmap Illustration/Getty Images

It’s been almost 10 months since deadly Winter Storm Elliot left a deep freeze over much of the country, resulting in widespread blackouts right before Christmas.

And ever since, electricity companies have been squabbling over the fallout with PJM Interconnection, the sprawling electricity market that stretches from the mid-Atlantic coast to the Midwest. About a quarter of the market’s capacity fell offline during the storm, with most of the blame falling on natural gas plants that were unable to deliver power. Penalties that PJM extracted from these plants drove some to bankruptcy while others went to federal energy regulators to say the penalties were too high.

Finally, on Friday, the parties told the Federal Energy Regulatory Commission that they were ready to settle. The settlement, if approved, would reduce the penalties from $1.8 billion to around $1.2 billion, which also means shaving payments to generators who were able to stay online during the storm by about a third.

But it probably won’t be the end of the story. Both the widespread failure during Elliott and the resulting tussle over how to pay for it underline just how hard it is to guarantee reliability, especially as the country becomes more electrified.

Generally, reliability on the electric grid is guaranteed by natural gas plants, which are supposed to be able to easily switch on and off to generate power when they’re needed most. In fact, about 40% of our electricity comes from natural gas. But you see the problem: When the gas system goes down, households lose access to heating, provided by natural gas directly via furnaces or by electricity via heat pumps. In the winter this means people will die.

And natural gas really did fall to pieces during the storm. According to a PJM report, “outages on gas units were primarily attributed to physical plant issues,” both because the cold made power plants inoperable and because the distribution network itself seized up, leaving gas plants unable to access the fuel they needed to produce power. This is similar to what happened during 2021’s Winter Storm Uri, a deep freeze that led to days of power outages in Texas that claimed over 200 lives.

Both situations suggest a few things: First, we need better forecasting. FERC said in its own review of the power outages that forecasts by grip operators underestimated how much electricity would be needed at peak times during the storm, in some cases by more than 10 percent.

Second, natural gas plants might not be as reliable as they’re supposed to be — and it’s unclear where the money will come from to make them more resilient.

And third, that merely incentivizing energy markets and individual generators to get this right only goes so far — huge portions of the generation fleet were unable to cope with the high demand for power, even at the risk of massive (if slightly reduced) penalties.

Electricity markets might need a little more oversight.

Yellow

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Sparks

New York’s Largest Battery Project Has Been Canceled

Fullmark Energy quietly shuttered Swiftsure, a planned 650-megawatt energy storage system on Staten Island.

Curtis Sliwa.
Heatmap Illustration/Getty Images

The biggest battery project in New York has been canceled in a major victory for the nascent nationwide grassroots movement against energy storage development.

It’s still a mystery why exactly the developer of Staten Island’s Swiftsure project, Fullmark Energy (formerly known as Hecate), pulled the plug. We do know a few key details: First, Fullmark did not announce publicly that it was killing the project, instead quietly submitting a short, one-page withdrawal letter to the New York State Department of Public Service. That letter, which is publicly available, is dated August 18 of this year, meaning that the move formally occurred two months ago. Still, nobody in Staten Island seems to have known until late Friday afternoon when local publication SI Advance first reported the withdrawal.

Keep reading...Show less
Blue
Sparks

Major Renewables Nonprofit Cuts a Third of Staff After Trump Slashes Funding

The lost federal grants represent about half the organization’s budget.

The DOE wrecking ball.
Heatmap Illustration/Getty Images

The Interstate Renewable Energy Council, a decades-old nonprofit that provides technical expertise to cities across the country building out renewable clean energy projects, issued a dramatic plea for private donations in order to stay afloat after it says federal funding was suddenly slashed by the Trump administration.

IREC’s executive director Chris Nichols said in an email to all of the organization’s supporters that it has “already been forced to lay off many of our high-performing staff members” after millions of federal dollars to three of its programs were eliminated in the Trump administration’s shutdown-related funding cuts last week. Nichols said the administration nixed the funding simply because the nonprofit’s corporation was registered in New York, and without regard for IREC’s work with countless cities and towns in Republican-led states. (Look no further than this map of local governments who receive the program’s zero-cost solar siting policy assistance to see just how politically diverse the recipients are.)

Keep reading...Show less
Yellow
Sparks

Esmeralda 7 Solar Project Has Been Canceled, BLM Says

It would have delivered a gargantuan 6.2 gigawatts of power.

Donald Trump, Doug Burgum, and solar panels.
Heatmap Illustration/Getty Images, Library of Congress

The Bureau of Land Management says the largest solar project in Nevada has been canceled amidst the Trump administration’s federal permitting freeze.

Esmeralda 7 was supposed to produce a gargantuan 6.2 gigawatts of power – equal to nearly all the power supplied to southern Nevada by the state’s primary public utility. It would do so with a sprawling web of solar panels and batteries across the western Nevada desert. Backed by NextEra Energy, Invenergy, ConnectGen and other renewables developers, the project was moving forward at a relatively smooth pace under the Biden administration, albeit with significant concerns raised by environmentalists about its impacts on wildlife and fauna. And Esmeralda 7 even received a rare procedural win in the early days of the Trump administration when the Bureau of Land Management released the draft environmental impact statement for the project.

Keep reading...Show less
Blue