Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

PJM Is Paralyzed by Its Data Center Dilemma

Members of the nation’s largest grid couldn’t agree on a recommendation for how to deal with the surge of incoming demand.

•
Power lines.
Heatmap Illustration/Getty Images

The members of PJM Interconnection, the country’s largest electricity market, held an advisory vote Wednesday to help decide how the grid operator should handle the tidal wave of incoming demand from data centers. Twelve proposals were put forward by data center companies, transmission companies, power companies, utilities, state legislators, advocates, PJM’s market monitor, and PJM itself.

None of them passed.

“There was no winner here,” PJM chief executive Manu Asthana told the meeting following the announcement of the vote tallies. There was, however, “a lot of information in these votes,” he added. “We’re going to study them closely.”

The PJM board was always going to make the final decision on what it would submit to federal regulators, and will try to get something to the Federal Energy Regulatory Commission by the end of the year, Asthana said — just before he plans to step down as CEO.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort. The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development,” a PJM spokesperson said in a statement. “This vote is advisory to PJM’s independent Board. The Board can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.”

The surge in data center development — actual and planned — has thrown the 13-state PJM Interconnection into a crisis, with utility bills rising across the network due to the billions of dollars in payments required to cover the additional costs.

Those rising bills have led to cries of frustration from across the PJM member states — and from inside the house.

“The current supply of capacity in PJM is not adequate to meet the demand from large data center loads and will not be adequate in the foreseeable future,” PJM’s independent market monitor wrote in a memo earlier this month. “Customers are already bearing billions of dollars in higher costs as a direct result of existing and forecast data center load,” it said in a quarterly report released just a few days letter, pegging the added charges to ensure that generators will be available in times of grid stress due to data center development at over $16 billion.

PJM’s initial proposal to deal with the data center swell would have created a category for new large sources of demand on the system to interconnect without the backing of capacity; in return, they’d agree to have their power supply curtailed when demand got too high. The proposal provoked outrage from just about everyone involved in PJM, including data center developers and analysts who were open to flexibility in general, who said that the grid operator was overstepping its responsibilities.

PJM’s subsequent proposal would allow for voluntary participation in a curtailment program, but was lambasted by environmental groups like Evergreen Collaborative for not having “any semblance of ambition.” PJM’s own market monitor said that voluntary schemes to curtail power “are not equivalent to new generation,” and that instead data centers should “be required to bring their own new generation” — essentially to match their own demand with new supply.

A coalition of environmental groups, including the Natural Resources Defence Council and state legislators in PJM, said in their proposal that data centers should be required to bring their own capacity — crucially counting demand response (being paid to curtail power) as a source of capacity.

“The growth of data centers is colliding with the reality of the power grid,” Tom Rutigliano, who works on grid issues for the Natural Resources Defense Council, said in a statement. “PJM members weren’t able to see past their commercial interests and solve a critical reliability threat. Now the board will need to stand up and make some hard decisions.”

Those decisions will come without any consensus from members about what to do next.

“Just because none of these passed doesn’t mean that the board will not act,” David Mills, the chairman of PJM’s board of managers, said at the conclusion of the meeting. “We will make our best efforts to put something together that will address the issues.”

Blue
🔒

You’ve reached your free article limit

Subscribe to Heatmap News for unlimited access to daily energy and climate coverage.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Politics

Miners Struck Gold With the Senate Permitting Bill

The proposal resolves an issue that has bedeviled the industry since 2022.

American mining.
Heatmap Illustration/Getty Images

Is Rosemont about to be BAAJA blasted away?

In a 2022 decision formally titled Center for Biological Diversity v. U.S. Fish & Wildlife Service, the Ninth Circuit Court of Appeals ruled that Rosemont Copper Company its claim under the General Mining Act of 1872 did not give the company license to dump literally millions of tons of waste rock on adjacent Forest Service land. Though Rosemont argued that the use fell under the law’s provisions for “mill sites” on public lands used for mining, the court found that because the parcel in question lacked valid mining claims of its own, the Mining Act did not justify its use under its own permissive regime.

Keep reading...Show less
Yellow
Spotlight

The New Push for Underwater Data Centers

Exploratory projects are making a splash in Maine and Alaska.

Wires and water.
Heatmap Illustration/Getty Images

A legal brawl is brewing over what could be the nation’s first underwater data centers.

Two subsidiaries of a new LLC named DeepGreen have applied for “preliminary” permits from the Federal Energy Regulatory Commission that would give four years of permission for studies and analysis towards constructing underwater data centers off remote coastlines in Maine and Alaska. The data centers as proposed would be powered entirely by tidal energy, as in, the power of waves themselves – a technological innovation from hydropower still being piloted around the world. Project descriptions submitted to FERC lay out what these data centers would look like in broad strokes: hundreds of hydrokinetic turbines, dozens of underwater “data center pods,” and miles of subsea cable. The permits would not authorize construction, which would need its own lengthy review process. But these early green lights would tee both areas up for years of potential conflict over hypotheticals that feel real to those on the ground.

Keep reading...Show less
Yellow
Hotspots

The Solar Opponents Begging Trump to Intervene in Michigan

And more of the week’s biggest fights around project development

The United States.
Heatmap Illustration/Getty Images

1. Ottawa County, Michigan – A congressional district House Democrats are targeting for control of the Lower Chamber is now a battleground over solar development on farmland, and I’m waiting to see if President Trump gets involved.

  • On Sept. 24, the Michigan township of Zeeland wrote a letter to the president – and reportedly Agriculture Secretary Brooke Rollins – requesting the federal government intervene in the development of RWE’s utility-scale Silver Maple Solar project. The letter to Trump which is public requests the president visit Zeeland and the project site to “provide an opportunity to meet directly with local farmers, business owners, elected officials, and residents who are living with the consequences of the poor policies you are fighting against.”
  • Shortly thereafter, Zeeland Township supervisor Kerri Bosma, who authored the letter, met with Rep. Bill Huizenga and presented him with a copy of the letter. “Thank you for reaching out Kerri and keep up the fight against this Lansing big government takeover!” Huizenga said on Facebook. Huizenga’s office did not respond to a request for comment on how they would support this request further.
  • This is remarkable because local officials are beckoning for Trump to arrive at a time when he’s historically unpopular and Huizenga’s congressional district is one being targeted by the Democratic Congressional Campaign Committee in this year’s midterm elections as a priority. Maybe this is about ginning up partisan red meat, as Huizenga’s opponent, State Sen. Sean McCann, has been publicly supportive of more solar development in agricultural communities.
  • Locals appear most irate with the state permitting primacy law which allows the state regulator, Michigan Public Service Commission, to supersede local opposition toward renewable energy projects. So far, the legality of that power is withstanding court challenges, and it’s unclear to me how the federal government could in any way stall this large solar farm aside from helping out in that legal effort on behalf of localities.
  • Clearly, RWE is confident they can go ahead – they just resubmitted their application to build the project with the MPSC, citing the primacy law’s survival in the courts.

2. Texas – The Lone Star State sure is action-packed right now, huh? Let’s break down a few of the most important fights.

Keep reading...Show less
Yellow