This Virginia Election Was a Warning for Data Centers

John McAuliff ran his campaign almost entirely on data centers — and won.

John McAuliff.
Heatmap Illustration/Getty Images, Library of Congress, John4VA.com

A former Biden White House climate adviser just won a successful political campaign based on opposing data centers, laying out a blueprint for future candidates to ride frustrations over the projects into seats of power.

On Tuesday John McAuliff, a progressive Democrat, ousted Delegate Geary Higgins, a Republican representing the slightly rural 30th District of Virginia in Loudoun and Fauquier Counties. The district is a mix of rural agricultural communities and suburbs outside of the D.C. metro area – and has been represented by Republicans in the state House of Delegates going back decades. McAuliff reversed that trend, winning a close election with a campaign almost entirely focused on data centers and “protecting” farmland from industrial development.

“I realized that the biggest energy crisis in the country was right here in my backyard,” McAuliff told me in an interview. “We are simply the tip of the iceberg of the enormous land rush AI has created.”

Virginia is the top data center destination in the U.S., with the bulk of operations in tech-centric Northern Virginia. As tech companies have found a home in the Commonwealth, communities have been pushing back against what they see as a drain on electricity and water supplies. As I’ve previously chronicled in The Fight, this pushback is also turning into opposition to renewable energy as part of a broader backlash to land use for advanced technological infrastructure.

Enter McAuliff who, until recently, was serving in key climate policy leadership roles during the Biden administration. He joined the Agriculture Department in 2022 after enactment of the Inflation Reduction Act and helped shepherd the expansion of the Rural Energy for America Program. He began advising the White House on climate policy in 2023 and served in the administration until the start of the current Trump administration.

Other factors contributed to McAuliff’s victory, which was certainly slim – the race was decided by less than a single percentage point. McAuliff undoubtedly benefited from a Democratic wave election in an off year during an unpopular GOP presidency that has slashed federal government employment, shattering the job market in northern Virginia. There’s also the convenient fact that McAuliff's last name is nearly identical to a recent former governor of Virginia.

But it’s impossible to ignore how much McAuliff’s campaign focused on data centers. His website had an entire page dedicated to his positions on the subject. His attack ads against Higgins focused on previous support and campaign contributions from data center developers – so much so that the Republican candidate began countering McAuliff by claiming that a Democratic victory would only lead to new solar projects.

Turns out, in this close race, the data center attacks worked and the solar rebuttal did not. McAuliff told me the day after his victory that the data center attacks resonate because yes, there’s an environmental impact from these projects, but also a “cultural” effect from the fact data centers are large, hulking complexes.

“There’s something folks are more willing to take a look at, and there’s something folks are less likely to look at, electorally speaking,” he said.

Chris Miller, president of the conservationist group Piedmont Environmental Council, told me you can see flickers of evidence that data centers shaped the results of other races in Virginia, too. One example he pointed to was in Prince William County, where Republican Delegate Ian Lovejoy lost his seat to a Democrat who campaigned on stricter scrutiny of the data center sector. Lovejoy also told voters he wanted to address the projects and authored legislation to put some minimum regulation in place on data center siting but it died in subcommittee, and when the House of Delegates passed legislation mirroring his proposal, it was vetoed by outgoing Republican Gov. Glenn Youngkin. This, to Miller, meant Lovejoy had nothing to show voters: “That may have been a factor, because he couldn’t deliver to his constituents.”

I wouldn’t be surprised if these races in Virginia are also turning heads in nearby Washington, D.C. — particularly those of the lawmakers in Congress debating whether to change our country’s permitting processes to meet growing power demand for artificial intelligence. Back home, permitting reform that makes it easier to build data centers could be a tough sell.

Yellow

This article is exclusively
for Heatmap Plus subscribers.

Go deeper inside the politics, projects, and personalities
shaping the energy transition.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Spotlight

The Data Center Transmission Brawls Are Just Getting Started

What happens when one of energy’s oldest bottlenecks meets its newest demand driver?

Power line construction.
Heatmap Illustration/Getty Images

Often the biggest impediment to building renewable energy projects or data center infrastructure isn’t getting government approvals, it’s overcoming local opposition. When it comes to the transmission that connects energy to the grid, however, companies and politicians of all stripes are used to being most concerned about those at the top – the politicians and regulators at every level who can’t seem to get their acts together.

What will happen when the fiery fights on each end of the wire meet the broken, unplanned spaghetti monster of grid development our country struggles with today? Nothing great.

Keep reading...Show less
Yellow
Hotspots

Will Maine Veto the First State-Wide Data Center Ban?

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Franklin County, Maine – The fate of the first statewide data center ban hinges on whether a governor running for a Democratic Senate nomination is willing to veto over a single town’s project.

  • On Wednesday, the Maine legislature passed a total ban on new data center projects through the end of 2027, making it the first legislative body to send such a bill to a governor’s desk. Governor Janet Mills, who is running for Democrats’ nomination to the Senate, opposed the bill prior to the vote on the grounds that it would halt a single data center project in a small town. Between $10 million and $12 million has already been sunk into renovating the site of a former paper mill in Jay, population 4,600, into a future data center. Mills implored lawmakers to put an exemption into the bill for that site specifically, stating it would otherwise cost too many jobs.
  • It’s unclear whether Mills will sign or veto the bill. Her office has not said whether she would sign the bill without the Jay exemption and did not reply to a request for comment. Neither did the campaign for Graham Platner, an Iraq War veteran and political novice running competitively against Mills for the Senate nomination. Platner has said little about data centers so far on the campaign trail.
  • It’s safe to say that the course of Democratic policy may shift if Mills – seen as the more moderate candidate of the two running for this nomination – signs the first state-wide data center ban. Should she do so and embrace that tack, it will send a signal to other Democratic politicians and likely accelerate a further shift into supporting wide-scale moratoria.

2. Jerome County, Idaho – The county home to the now-defunct Lava Ridge wind farm just restricted solar energy, too.

Keep reading...Show less
Yellow
Q&A

Why Data Centers Need Battery Storage

A chat with Scott Blalock of Australian energy company Wärtsilä.

Scott Blalock.
Heatmap Illustration/Getty Images

This week’s conversation is with Scott Blalock of Australian energy company Wärtsilä. I spoke with Blalock this week amidst my reporting on transmission after getting an email asking whether I understood that data centers don’t really know how much battery storage they need. Upon hearing this, I realized I didn’t even really understand how data centers – still a novel phenomenon to me – were incorporating large-scale battery storage at all. How does that work when AI power demand can be so dynamic?

Blalock helped me realize that in some ways, it’s more of the same, and in others, it’s a whole new ballgame.

Keep reading...Show less