Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Politics

Scoop: Trump Administration Refuses to Allow Safety Fixes at Vineyard Wind

The offshore wind developer was in the process of completing necessary repairs when the administration issued its stop work order, according to court filings.

Trump grabbing a turbine blade.
Heatmap Illustration/Getty Images

In the Atlantic ocean south of Massachusetts, 10 wind turbine towers, each 500 feet tall, stand stripped of their rotary blades. Stuck in this bald state due to the Trump administration’s halt on offshore wind construction, the towers are susceptible to lightning strikes and water damage. This makes them a potential threat to public safety, according to previously unreported court filings from the project developer, Vineyard Wind.

The company filed for an injunction against Trump’s stop work order last week. The order posed a unique threat to Vineyard Wind, as the project is 95% complete and its contract with a key construction boat is set to expire on March 31, the filing said. “If construction is not completed by that date, the partially completed wind turbines will be left in an unsafe condition and Vineyard Wind will incur a series of financial consequences that it likely could not survive,” the company wrote.

One of the final tasks the company was working on was replacing faulty blades on nearly two dozen turbine towers. In July 2024, one of the installed blades snapped in two, sending fiberglass and other debris crashing into the sea and eventually onto the beaches of Nantucket. The incident revealed a manufacturing defect at the Canadian factory where the blades were made. After multiple investigations into the incident, the company reached an agreement with the Bureau of Ocean Energy Management and the Bureau of Safety and Environmental Enforcement to replace the defective equipment with blades produced at a different factory in France.

Trump’s construction freeze contained an exception for activities “necessary to respond to emergency situations and/or to prevent impacts to health, safety, and the environment.” So after the order came down on December 22, Vineyard Wind reached out to the relevant regulators and asked permission to continue its blade replacement process on safety grounds, the company explained in court filings. BSEE responded that the company could remove the faulty blades on the 10 remaining towers, but could not replace them.

The decision highlights an apparent double standard in the administration’s considerations of public safety. The stop work order itself was intended to “protect the American people,” according to Secretary of the Interior Doug Burgum. Yet the agency has refused to let construction move forward to mitigate risks created by the stoppage.

Testimony submitted by Steven Simkins, Vineyard Wind’s Wind turbine team lead, describes the dangers of leaving the towers bladeless for an extended period of time — a risk compounded by the ticking clock on the company’s construction boat contract. “The wind turbine was designed to be constructed completely and only be in a hammerhead state, without blades, for a brief amount of time during installation,” Simkins wrote.

He warned of three main liabilities. First, the towers are equipped with a lightning protection system, but the system’s receptors and conductors extend along the blades. Without the blades, the towers are essentially lightning rods, at risk of igniting an electrical fire, Simkins explained.

The three giant holes where the blades would be installed are also sitting open, with tarps covering them as temporary protection. That means that water, ice, and humidity could get into the nacelle, the top part of the tower that houses all of the electrical and mechanical systems, which are not designed to weather this kind of exposure. “Not only will this lead to prolonged offshore work replacing damaged equipment but it also puts the safety of the workers at risk,” Simkins wrote. “Electrical cabinets that have experienced some level of corrosion become less safe and increase the risk of an arc flash event.”

Lastly, the 500-foot towers are being roiled by winter wind and waves, which causes them to sway. The blades are designed to capture that wind, reducing its force on the towers. Without them, the “fatigue” on the towers will be exacerbated, “and the design has accounted for a limited amount of such fatigue over the total life of the structure.”

Court documents show that Vineyard Wind — the last of five affected companies to file for an injunction against Trump’s stop work order — held off on litigation as it made multiple attempts to convince the administration that completing blade installation was necessary to mitigate safety risks.

Vineyard Wind also sent BSEE verification of its safety claims by DNV Energy Systems, a Danish company it was required to retain to “ensure that the Project is installed in accordance with accepted engineering practices and, when necessary, to provide reports to BSEE regarding incidents affecting Critical Safety Systems.” But BSEE disagreed and denied Vineyard Wind’s request.

The Trump administration filed a response in the case on Tuesday, with BSEE’s Principal Deputy Director Kenneth Stevens testifying that the bureau’s technical personnel had “determined that there should be no structural issues associated with the tower and nacelle-only configuration if they were installed correctly.” He noted that the towers had been “routinely left in this configuration repeatedly” while the project was under construction over the past year and a half “with no reported adverse impacts to safety.”

Vineyard Wind did not respond to a request for comment on that assertion. A hearing in the case is scheduled for Friday. Three separate district judges have already granted injunctions to offshore projects affected by the stop work order: Revolution Wind, Empire Wind, and Dominion Energy’s Coastal Virginia offshore wind project. Each judge found that the companies were “likely” to succeed in showing that the stop work order violated the Administrative Procedures Act, and allowing them to continue construction.

Jael Holzman contributed reporting.

Blue

You’re out of free articles.

Subscribe to access Heatmap’s expert analysis of climate change, clean energy, and sustainability. Save $57 on an annual subscription, just $156 $99/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Sparks

5 Things to Keep in Mind When It’s Smoky Outside

What are the health risks? How can I protect myself? And will my plants be okay?

Smoky days.
Heatmap Illustration/Getty Images

If you live anywhere near the Great Lakes or Mid-Atlantic (or certain parts of the Mountain West), odds are it’s smoky where you live. Wildfires raging in western Ontario are sending smoke cascading south and east across the U.S., prompting widespread air quality alerts affecting millions of Americans.

The good and — very bad — news is that we’ve been here before. Here’s a look back at some of Heatmap’s coverage from the summer of 2023, when smoke produced by forest fires in Quebec blanketed 128 million people in a murky haze and turned the New York City skyline an ominous shade of orange.

Keep reading...Show less
AM Briefing

La Brega de Agua

On Hungary’s BYD scandal, seawater uranium, and saving styrofoam

The Puerto Rico water shortage.
Heatmap Illustration/Getty Images

Current conditions: Wildfire smoke tinted the skies orange across the Northeastern United States, rendering the air on New York’s Long Island thick and hazy all afternoon • London is a balmy 83 degrees Fahrenheit today, but new research shows that the number of days topping 86 degrees has quadrupled since the 1980s • Chile declared a state of emergency across 10 regions ahead of a series of major storms.

THE TOP FIVE

1. Oil traders issue a stark warning as Trump ramps up Iran War

The resumption of fighting between the United States and Iran over the Strait of Hormuz could hammer energy markets harder than the previous phase of the conflict, as the crude stockpiles governments tapped at a record volumes to avert the worst economic impact of the war are now depleted. That’s the warning oil traders issued to the Financial Times on Wednesday. “We’ve burned through all of the buffers we had. Everything,” one trader said. “All of that’s now gone.” The gloomy assessment came as The Wall Street Journal reported that President Donald Trump has weighed expanding the U.S. military operation in Iran.

Keep reading...Show less
Yellow
Carbon Removal

The Carbon Removal Buyer the World Has Been Waiting For

Proposed reforms to Europe’s Emissions Trading System could see the EU itself become a carbon credit customer.

The EU flag and DAC.
Heatmap Illustration/Getty Images

The European Union is on the verge of making major changes to its carbon market, including integrating carbon removals into the scheme for the first time.

The bloc’s highest governing body, the European Commission, is expected to publish a proposal on Friday to reform the EU Emissions Trading System, or ETS, to align it with the EU’s 2040 emissions target. Under the current rules, companies cannot use carbon credits of any kind to comply with the regulations. But as 2040 grows closer, the EU plans to rely on carbon removal to offset some of the residual emissions from industries that are the most difficult to decarbonize.

Keep reading...Show less
Yellow