Would You Like a Gas-Fired Power Plant With That Data Center?

CoreWeave signed a deal for a new facility in New Jersey, behind-the-meter power on the side.

A gas plant and retro loading.
Heatmap Illustration/Getty Images

The cloud computing company CoreWeave announced Monday that it is leasing a former medical research facility and turning it into a data center. Along with it comes a 25-megawatt power plant that once provided power and steam directly to the former Merck headquarters in Kenilworth, New Jersey, but began to sell more and more power to the grid, the plant’s owner said in a filing with the Federal Energy Regulatory Commission. In 2023, the facility was purchased by Onyx, a real estate firm, and Machine Investment Group, with the intention to market the site to another life sciences or biotechnology company.

Then the AI revolution happened.

CoreWeave, which started as a miner of cryptocurrency, is now raising and spending billions of dollars to acquire and install the chips necessary to train and run artificial intelligence systems for companies that rent out access to them. According to the deal announcement, the company plans to pour $1.2 billion of investment into the 280,000 square foot facility, along with electrical upgrades from the utility PSE&G and investments from Onyx. The power plant will stop serving the grid and go “behind the meter,” the plant’s owner Atlantic Power said in a letter to PJM Interconnection, the regional electricity market, in September.

The deal confirms that when it comes to power, data centers will take what they can get — and that the long timelines necessary to bring on new power in much of the country may end up benefiting existing owners of generation, especially natural gas.

Data centers require both large amounts of power — sometimes 100 megawatts or more — and the ability to surge up and down quickly. “Renewable power generation is well placed to capture mounting demand from data centers and AI in the long term,” analysts at BNEF wrote in a report in September, “but time constraints for grid interconnection and intermittency issues could support natural gas-fired output.”

Goldman Sachs analysts expect data center power demand to rise from about 3% of the U.S. total to 8% by 2030, with growth running at 15% annually. They assume that capacity will be met mostly by natural gas, but actually finding — let alone building — new natural gas generation is a challenge.

“The hyperscalers are evolving from single data centers dependent on 60 to 100 megawatts to starting to look at multiple gigawatt-size data center parks that support a number of data centers in one location,” GE Vernova chief executive Scott Strazik said on a recent earnings call with analysts.

Building a new natural gas plant on the grid — and especially the transmission infrastructure to serve it — can be a prospect well beyond the build-it-now timelines of big technology companies with a desperate need for computing power.

“Thanks to 10-year delays in permitting for new transmission lines and connecting generation capacity to the grid, the most viable near-term option is behind-the-meter,” Tim Fist and Arnab Datta wrote in a report for the Institute for Progress, a technology and science policy think tank. In other words, one way to get around grid interconnection and intermittency issues is to have your own power plant.

“The economics of developing the power on site don't really hurt the data center economics that much. These things are just really profitable,” Carson Kearl, an analyst at Enverus, told me.

Some data centers have developed their own natural gas generation on site, such as XAi’s cluster in Memphis, Tennessee, which is powered by gas generators.

CoreWeave, meanwhile, is one of the most talked-about and well-funded companies in cloud computing, with access to a huge number of chips made by Nvidia, the leading designer of high-end processors, and which is also an investor in CoreWeave. But the chips can only perform when they’re powered, turning the data center business into a hunt for electricity wherever it can be found.

“Access to reliable power could be a roadblock towards the timely buildout” for a data center, Francois Poirier, the chief executive of TC Energy, the Canadian pipeline company, told analysts on an earnings call in August. “We’re seeing a shift in siting preferences from regions where big telecom infrastructure is in place to regions where energy and supply infrastructure is in place.”

CoreWeave, PSE&G, Onyx, and Atlantic Power’s owner, I Squared Capital, did not respond to requests for comment.

This situation has not come about for lack of effort on the part of the several electricity markets that have been trying to get new natural gas generation on the grid. PJM, for example, has been working to entice new supply, but even following a record auction for power capacity that paid out billions to natural gas plants, few producers have indicated their willingness to make large new investments. Texas has established a multibillion-dollar loan fund to provide low-cost financing to new natural gas plants.

While several large technology companies have announced their intention to buy nuclear power from refurbished or new plants, those deals will take at least several years to actually get any new electrons on the grid.

That leads data center developers like CoreWeave scrambling to find what power they can. In interviews, the company’s chief strategy officer Brian Venturo told Wired that they are avoiding Northern Virginia’s “data center alley” precisely because it’s “a food fight to get power.”

“There's a lot of growing backlash in that market around power usage,” he told Bloomberg. “We're kind of siting our plants and markets where our data centers and markets where we think the grid infrastructure is capable of handling it.”

And what better place than where the power already is.

Blue

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Politics

How the Shutdown Could Remake the Trump Administration

Republicans have blamed Democrats for unleashing Russ Vought on federal spending. But it doesn’t take much to see a bigger plan at work.

Russ Vought with scissors.
Heatmap Illustration/Getty Images

Russ Vought, the director of the Office of Management and Budget, has been waiting for this moment his whole adult life — or that’s what President Trump and the Republican Congressional leadership would like you to believe. As they put it, Vought is a fanatical budget cutter who, once unleashed, cannot be controlled. Who knows what he’ll cut if the Democrats continue to keep the government shut down?

Substantial staffing cuts that go beyond the typical shutdown furloughs are “the risk of shutting down the government and handing the keys to Russ Vought,” Senate Majority Leader John Thune told Politico on Thursday. “We don’t control what he’s going to do.”

Keep reading...Show less
Spotlight

44% of Data Centers Proposed in Indiana Are in Counties that Restrict Renewables

A review of Heatmap Pro data reveals a troubling new trend in data center development.

A data center and a backyard.
Heatmap Illustration/Getty Images

Data centers are being built in places that restrict renewable energy. There are significant implications for our future energy grid – but it’s unclear if this behavior will lead to tech companies eschewing renewables or finding novel ways to still meet their clean energy commitments.

In the previous edition of The Fight, I began chronicling the data center boom and a nascent backlash to it by talking about Google and what would’ve been its second data center in southern Indianapolis, if the city had not rejected it last Monday. As I learned about Google’s practices in Indiana, I focused on the company’s first project – a $2 billion facility in Fort Wayne, because it is being built in a county where officials have instituted a cumbersome restrictive ordinance on large-scale solar energy. The county commission recently voted to make the ordinance more restrictive, unanimously agreeing to institute a 1,000-foot setback to take effect in early November, pending final approval from the county’s planning commission.

Keep reading...Show less
Yellow
AM Briefing

H2 No

On Tesla’s record, Britain’s backtracking, and an Antarctic ice warning

A hydrogen plant.
Heatmap Illustration/Getty Images

Current conditions: After walloping Bermuda with winds of up to 100 miles per hour, Hurricane Imelda is veering northeast away from the United States • While downgraded from a hurricane, Humberto is set to soak Ireland and the United Kingdom as Storm Amy in the coming days and bring winds of up to 90 miles per hour • Typhoon Matmo is strengthening as it hits the Philippines and barrels toward China.

THE TOP FIVE

1. Energy Department kills West Coast hydrogen hubs

The Department of Energy is canceling two regional hydrogen hubs in California and the Pacific Northwest as part of a broader rescinding of 321 grants worth $7.5 billion for projects nationwide. Going after the hydrogen hubs, which the oil and gas industry lobbied to keep open after President Donald Trump came back to office, “leaves the agency’s intentions for the remaining five hubs scattered throughout the Midwest, Midatlantic, Appalachia, the Great Plains, and Texas unclear,” Heatmap’s Emily Pontecorvo wrote yesterday.

Keep reading...Show less
Green