Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

One Weird Trick for Getting More Data Centers on the Grid

Just turn them off sometimes, according to new research from Duke University.

Wires and power lines.
Heatmap Illustration/Getty Images

Grid planners have entered a new reality. After years of stagnant growth, utilities are forecasting accelerating electricity demand from artificial intelligence and other energy-intense industries and using it to justify building out more natural gas power plants and keep old coal plants online. The new administration has declared that the United States is in an “energy emergency,” bemoaning that the country’s generating capacity is “far too inadequate to meet our Nation’s needs.” Or, as President Trump put it at the Republican National Convention, “AI needs tremendous — literally, twice the electricity that’s available now in our country, can you imagine?”

The same logic also works the other way — the projected needs of data centers and manufacturing landed some power producers among the best performing stocks of 2024. And when it looked like artificial intelligence might not be as energy intensive as those producers assumed thanks to the efficiency of DeepSeek’s open source models, shares in companies that own power plants and build gas turbines crashed.

Both industry and policymakers seem convinced that the addition of new, large sources of power demand must be met with more generation and expensive investments to upgrade the grid.

But what if it doesn’t?

That’s the question Tyler Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell of the Nicholas Institute of Energy, Environment and Stability at Duke University tried to answer in a paper released Tuesday.

Their core finding: that the United States could add 76 gigawatts of new load — about a tenth of the peak electricity demand across the whole country — without having to upgrade the electrical system or add new generation. There’s just one catch: Those new loads must be “curtailed” (i.e. not powered) for up to one-quarter-of-one-percent of their maximum time online. That’s it — that’s the whole catch.

“We were very surprised,” Norris told me, referring to the amount of power freed up by data centers if they could curtail their usage at high usage times.

“It goes against the grain of the current paradigm,” he said, “that we have no headroom, and that we have to make massive expansion of the system to accommodate new load and generation.”

The electricity grid is built to accommodate the peak demand of the system, which often occurs during the hottest days of summer or the coldest days of winter. That means much grid infrastructure is built out solely to accommodate power demand that occurs over just a few days of the year, and even then for only part of those days. Thus it follows that if those peaks can be shaved by demand being reduced, then the existing grid can accommodate much more new demand.

This is the logic of longstanding “demand response” programs, whether they involve retail consumers agreeing not to adjust their thermostats outside a certain range or factories shuttering for prescribed time periods in exchange for payments from the grid authority. In very flexible markets, such as Texas’ ERCOT, some data center customers (namely cryptominers) get a substantial portion of their overall revenue by agreeing to curtail their use of electricity during times of grid stress.

While Norris cautioned that readers of the report shouldn’t think this means we won’t need any new grid capacity, he argued that the analysis “can enable more focus of limited resources on the most valuable upgrades to the system.”

Instead of focusing on expensive upgrades needed to accommodate the new demand on the grid, the Duke researchers asked what new sources of demand could do for the grid as a whole. Ask not what the grid can do for you, ask what you can do for the grid.

“By strategically timing or curtailing demand, these flexible loads can minimize their impact on peak periods,” they write. “In doing so, they help existing customers by improving the overall utilization rate — thereby lowering the per-unit cost of electricity — and reduce the likelihood that expensive new peaking plants or network expansions may be needed.” urtailment of large loads, they argue, can make the grid more efficient by utilizing existing equipment more fully and avoiding expensive upgrades that all users might have to pay for.

They found that when new large loads are curtailed for up to 0.25% of their maximum uptime, the average time offline amounts to just over an hour-and-a-half at a go, with 85 hours of load curtailment per year on average.

“You’re able to add incremental load to accept flexibility in most stressed periods,” Norris said. “Most hours of the year we’re not that close to the maximum peaks.”

In the nation’s largest electricity trading market, PJM Interconnection, this quarter-percent of total uptime curtailment would enable the grid to bring online over 13 gigawatts of new data centers — about the capacity of 13 new, large nuclear reactors — while maintaining PJM’s planners’ desired amount of generation capacity. In other words, that’s up to 13 gigawatts of reactors PJM no longer has to build, as long as that new load can be curtailed for 0.25% of its maximum uptime.

But why would data center developers agree to go offline when demand for electricity rises?

It’s not just because it could help the developers maintain their imperiled sustainability goals. It also presents an opportunity to solve the hardest problem for building out new data centers. One of the key limiting factors to getting data centers online is so-called “time to power,” i.e. how long it takes for the grid to be upgraded, either with new transmission equipment or generation, so that a data center can get up and running. According to estimates from the consulting firm McKinsey, a data center project can be developed in as little as a year and a half — but only if there’s already power available. Otherwise the timeline can run several years.

“There’s a clear value add,” Norris said. There are “very few locations to interconnect multi-hundred megawatt or gigawatt load in near-term fashion. If they accept flexibility for provision interim period, that allows them to get online more quickly.”

This “time to power” problem has motivated a flowering of unconventional ideas to power data centers, whether it’s large-scale deployment of on-site solar power (with some gas turbines) in the Southwest, renewables adjacent to data centers, co-located natural gas, or buying whole existing nuclear power plants.

But there may be a far simpler answer.

Yellow

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Climate

Does Microsoft’s Clean Energy Pullback Actually Matter?

Giving up on hourly matching by 2030 doesn’t mean giving up on climate ambition — necessarily.

Clean energy and the Microsoft logo.
Heatmap Illustration/Getty Images

Microsoft celebrated a “milestone achievement” earlier this year, when it announced that it had successfully matched 100% of its 2025 electricity usage with renewable energy. This past week, however, Bloomberg reported that the company was considering delaying or abandoning its next clean energy target set for 2030.

What comes after achieving 100% renewable energy, you might ask? What Microsoft did in 2025 was tally its annual energy consumption and purchase an equal amount of solar and wind power. By 2030, the company aspired to match every kilowatt it consumes with carbon-free electricity hour by hour. That means finding clean power for all the hours when the sun isn’t shining and the wind isn’t blowing.

Keep reading...Show less
Blue
Energy

Regulatory Reform Is Headed for the Nation’s Largest Grid

PJM Interconnection has some ideas, as does the state of New Jersey.

Josh Shapiro and Mikie Sherrill.
Heatmap Illustration/Getty Images

We’ve already talked this week about Pennsylvania asking whether the modern “regulatory compact,” which grants utilities monopoly geographical franchises and regulated returns from their capital investments, is still suitable in this era of rising prices and data-center-driven load growth.

Now America’s biggest electricity market and another one of that market’s biggest states are considering far-reaching, fundamental reforms that could alter how electricity infrastructure is planned and paid for over 65 million Americans.

Keep reading...Show less
Green
Climate Tech

Funding Friday: Robots Want Fast-Charging Batteries

Big fundraises for Nyobolt and Skeleton Technologies, plus more of the week’s biggest money moves.

A Skeleton factory.
Heatmap Illustration/Getty Images, Skeleton

Following a quiet week for new deals, the industry is back at it with a bunch of capital flowing into some of the industry’s most active areas. My colleague Alexander C. Kaufman already told you about one of the more buzzworthy announcements from data center-land in Wednesday’s AM newsletter: Wave energy startup Panthalassa raised $140 million in a round led by Peter Thiel to “perform AI inference computing at sea” using nodes powered by the ocean’s waves.

This week also saw fresh funding for more conventional data center infrastructure, as Nyobolt and Skeleton Technologies both announced later-stage rounds for data center backup power solutions. Meanwhile, it turns out Redwood Materials is not the only company bringing in significant capital for second-life EV battery systems — Moment Energy just raised $40 million to pursue a similar approach. Elsewhere, investors backed an effort to rebuild domestic magnesium production, and, in a glimmer of hope for a sector on the outs, gave a boost to green cement startup Terra CO2.

Keep reading...Show less
Green