Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

One Weird Trick for Getting More Data Centers on the Grid

Just turn them off sometimes, according to new research from Duke University.

Wires and power lines.
Heatmap Illustration/Getty Images

Grid planners have entered a new reality. After years of stagnant growth, utilities are forecasting accelerating electricity demand from artificial intelligence and other energy-intense industries and using it to justify building out more natural gas power plants and keep old coal plants online. The new administration has declared that the United States is in an “energy emergency,” bemoaning that the country’s generating capacity is “far too inadequate to meet our Nation’s needs.” Or, as President Trump put it at the Republican National Convention, “AI needs tremendous — literally, twice the electricity that’s available now in our country, can you imagine?”

The same logic also works the other way — the projected needs of data centers and manufacturing landed some power producers among the best performing stocks of 2024. And when it looked like artificial intelligence might not be as energy intensive as those producers assumed thanks to the efficiency of DeepSeek’s open source models, shares in companies that own power plants and build gas turbines crashed.

Both industry and policymakers seem convinced that the addition of new, large sources of power demand must be met with more generation and expensive investments to upgrade the grid.

But what if it doesn’t?

That’s the question Tyler Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell of the Nicholas Institute of Energy, Environment and Stability at Duke University tried to answer in a paper released Tuesday.

Their core finding: that the United States could add 76 gigawatts of new load — about a tenth of the peak electricity demand across the whole country — without having to upgrade the electrical system or add new generation. There’s just one catch: Those new loads must be “curtailed” (i.e. not powered) for up to one-quarter-of-one-percent of their maximum time online. That’s it — that’s the whole catch.

“We were very surprised,” Norris told me, referring to the amount of power freed up by data centers if they could curtail their usage at high usage times.

“It goes against the grain of the current paradigm,” he said, “that we have no headroom, and that we have to make massive expansion of the system to accommodate new load and generation.”

The electricity grid is built to accommodate the peak demand of the system, which often occurs during the hottest days of summer or the coldest days of winter. That means much grid infrastructure is built out solely to accommodate power demand that occurs over just a few days of the year, and even then for only part of those days. Thus it follows that if those peaks can be shaved by demand being reduced, then the existing grid can accommodate much more new demand.

This is the logic of longstanding “demand response” programs, whether they involve retail consumers agreeing not to adjust their thermostats outside a certain range or factories shuttering for prescribed time periods in exchange for payments from the grid authority. In very flexible markets, such as Texas’ ERCOT, some data center customers (namely cryptominers) get a substantial portion of their overall revenue by agreeing to curtail their use of electricity during times of grid stress.

While Norris cautioned that readers of the report shouldn’t think this means we won’t need any new grid capacity, he argued that the analysis “can enable more focus of limited resources on the most valuable upgrades to the system.”

Instead of focusing on expensive upgrades needed to accommodate the new demand on the grid, the Duke researchers asked what new sources of demand could do for the grid as a whole. Ask not what the grid can do for you, ask what you can do for the grid.

“By strategically timing or curtailing demand, these flexible loads can minimize their impact on peak periods,” they write. “In doing so, they help existing customers by improving the overall utilization rate — thereby lowering the per-unit cost of electricity — and reduce the likelihood that expensive new peaking plants or network expansions may be needed.” urtailment of large loads, they argue, can make the grid more efficient by utilizing existing equipment more fully and avoiding expensive upgrades that all users might have to pay for.

They found that when new large loads are curtailed for up to 0.25% of their maximum uptime, the average time offline amounts to just over an hour-and-a-half at a go, with 85 hours of load curtailment per year on average.

“You’re able to add incremental load to accept flexibility in most stressed periods,” Norris said. “Most hours of the year we’re not that close to the maximum peaks.”

In the nation’s largest electricity trading market, PJM Interconnection, this quarter-percent of total uptime curtailment would enable the grid to bring online over 13 gigawatts of new data centers — about the capacity of 13 new, large nuclear reactors — while maintaining PJM’s planners’ desired amount of generation capacity. In other words, that’s up to 13 gigawatts of reactors PJM no longer has to build, as long as that new load can be curtailed for 0.25% of its maximum uptime.

But why would data center developers agree to go offline when demand for electricity rises?

It’s not just because it could help the developers maintain their imperiled sustainability goals. It also presents an opportunity to solve the hardest problem for building out new data centers. One of the key limiting factors to getting data centers online is so-called “time to power,” i.e. how long it takes for the grid to be upgraded, either with new transmission equipment or generation, so that a data center can get up and running. According to estimates from the consulting firm McKinsey, a data center project can be developed in as little as a year and a half — but only if there’s already power available. Otherwise the timeline can run several years.

“There’s a clear value add,” Norris said. There are “very few locations to interconnect multi-hundred megawatt or gigawatt load in near-term fashion. If they accept flexibility for provision interim period, that allows them to get online more quickly.”

This “time to power” problem has motivated a flowering of unconventional ideas to power data centers, whether it’s large-scale deployment of on-site solar power (with some gas turbines) in the Southwest, renewables adjacent to data centers,co-located natural gas, or buying whole existing nuclear power plants.

But there may be a far simpler answer.

Yellow

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Electric Vehicles

Tesla’s Robo-Future Is Still Pretty Far Off

The company says its first Optimus robots will start rolling off the line in “2026.”

Hailing a Robotaxi.
Heatmap Illustration/Getty Images, Tesla

Tesla is a car company everywhere except Wall Street. It delivered some 1.7 million cars in 2024, which were built in factories in Texas, California, Germany, and China. These car sales (and leases and sales of regulatory credits) generated some $77 billion in revenue. Its gross margin on these cars is about 18.5%, or around $14 billion.

When Tesla reported its first quarter earnings, it announced a more than 70% decline in profits, continued falling sales, and ahit to its business from the trade war with China. But its stock climbed the next day, and is now trading at around $350 a share, from $238 before the report, giving it an overall value of over $1 trillion. By some metrics, Tesla makes up more than half of the overall value of the automotive industry.

Keep reading...Show less
Green
Politics

The Energy Department’s Possibly Illegal Move to Fund a Fossil-Fired Steel Furnace

At least one target of Chris Wright’s grant review may run into some sticky statutory issues.

Flags and steel.
Heatmap Illustration/Getty Images

The Department of Energy announced on Thursday that it’s reviewing some 179 awards made by the Biden administration worth $15 billion to ensure they were “consistent with Federal law and this Administration’s policies and priorities.”

But what happens when federal law and Trump’s priorities are at odds?

Keep reading...Show less
Blue
Climate

AM Briefing: Republicans Waver Over Cost, Energy Ahead of Budget Vote

On budget negotiations, Climeworks, and DOE grants

Republicans Waver Over Cost, Energy Ahead of Budget Vote
Heatmap Illustration/Getty Images

Current conditions: It’s peak storm season in the U.S., with severe weather in the forecast for at least the next six days in the Midwest and EastSan Antonio, Texas, is expected to hit 108 degrees Fahrenheit todayMonsoon rains have begun in Sri Lanka.

THE TOP FIVE

1. Republicans waver on budget ahead of possible floor vote next week

The House Budget Committee meeting to prepare the reconciliation bill for a floor vote as early as next week appears to be a go for Friday, despite calls from some Republicans to delay the session. At least three GOP House members, including two members of the Freedom Caucus, have threatened to vote no on the budget because a final score for the Energy and Commerce portion of the bill, which includes cuts to Medicaid, won’t be ready from the Congressional Budget Office until next week. That is causing a “math problem” for Republicans, Politico writes, because the Budget Committee “is split 21-16 in favor of Republicans, and Democrats are expecting full attendance,” meaning Republicans can “only lose two votes if they want to move forward with the megabill Friday.” Republican Brandon Gill of Texas is currently out on paternity leave, further reducing the margin for disagreement.

Keep reading...Show less
Yellow