Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Economy

Offshore Wind Is in Trouble — And That Might Be Okay (For Now)

Does America actually need the renewable energy source to hit its decarbonization goals by 2030?

A wind turbine.
Heatmap Illustration/Getty Images

The Biden administration wants 30 gigawatts of offshore wind power capacity by the end of the decade and East Coast states have taken it upon themselves to do much of the work to get there. But as wind projects up and down the East Coast face problems — developers threatening to pull the plug unless they get more subsidies, higher costs, supply chain issues, local opposition, and possibly astroturfed concerns about whales — experts have questioned whether this goal can really be hit.

But it may not even be necessary to substantially decarbonize the American economy — or at least not by 2030.

The recent stream of news about offshore wind has been bad. Developers up and down the East Coast have been asking states for more money in order to continue deals they struck years ago, citing higher costs throughout the supply chain. A recent auction for offshore wind rights in the Gulf of Mexico was almost a total flop, with only two companies participating in the bidding.

The Danish wind developer Orsted said a few weeks ago that three of its U.S. offshore wind projects were “adversely impacted by a handful of supplier delays” and that “there is a continuously increasing risk in these suppliers’ ability to deliver on their commitments and contracted schedules,” adding up to a lengthening timeline and increased costs that could lead to billions of dollars of write-offs.

The company’s chief executive Mads Nipper, who is in a standoff with the Biden administration over its eligibility for further subsidies, has said they are willing to “walk away” from wind projects. The company said that its Ocean Wind 1 project, planned for the New Jersey coast, would be delayed from 2025 to 2026.

So what happens if offshore wind doesn’t materialize at the level once expected?

There are any number of reports and projections showing how the United States can transition to 100% carbon-free electricity and even a whole economy that contributes net zero greenhouse gas emissions, and they’re typically less optimistic about offshore wind than the Biden administration. Princeton’s Net-Zero America Project, for instance, forecast offshore wind capacity would be between three and 10 gigawatts by 2030 in five scenarios for reaching zero emissions by midcentury. It largely sees additional onshore wind and solar making up the difference.

In fact, the government’s own forecasts don’t really envision the U.S. hitting the 30 gigawatt figure either. The National Renewable Energy Lab’s analysis of how to reach 100% carbon-free electricity by 2035, which is the Biden administration’s nominal goal, projects that in the “mid-range” case, offshore wind production would hit 24 gigawatts by 2030. Both the Net-Zero Project and the NREL foresee massive offshore wind installation, just on a slower timeline than the administration.

“The 30 GW by 2030 offshore wind goal is definitely still within striking distance, thanks in part to investments like the Inflation Reduction Act and Bipartisan Infrastructure Law , as well as state-level policies,” Jocelyn Brown-Saracino, the Department of Energy's Wind Energy Lead, said in an emailed statement. “The actual size and speed of U.S. offshore wind build-out will depend on continued regulatory efficiency, the availability of installation vessels and port infrastructure, proactive onshore and offshore grid planning and upgrades, the successful commercialization of 15-MW wind turbine platforms, and sustained market demand. DOE and other federal agencies are working on a number of initiatives to accelerate efforts in these areas.”

And, at least until we build the grid of our dreams, eastern seaboard states need to get carbon-free energy from somewhere. They have collectively set goals for some 50 gigawatts of offshore wind capacity over the coming decades. In the Northeast especially, the desire for large amounts of offshore wind generation reflects a combination of ambition to decarbonize the states’ electricity systems and lack of other politically palatable options. New York, for instance, shut down its Indian Point nuclear power plant in 2021, taking 2,000 megawatts of carbon-free power off the grid, with the promise that offshore wind would soon replace it. It hasn’t yet.

Those states are not in the wind corridor that is the Great Plains or the sunny expanse of the Southwest. While residential and business solar has been more widespread than anticipated in New England, offshore wind has consistently been the energy source that was promised from the New York Bight to the Gulf of Maine.

And it makes sense why. The East Coast’s population centers are, well, near the coast, meaning the Atlantic’s shallow and windy waters an attractive option for energy development. And by building offshore, these states can avoid grueling fights over land use that accompany wind farm developments in rural areas far from where most of the states’ residents actually live. Offshore wind can also complement solar, as winds can pick up in the afternoon and evening as solar power falls off.

This has all added up to an odd situation, where the country’s immediate goals for decarbonization may actually be overserved by ambitious development plans that, as of now, seem to be imperiled.

According to the Department of Energy, over 50 gigawatts of offshore wind is in the so-called pipeline, but there are only a few projects that have been approved or are under construction.

“The Biden-Harris administration is using every legally available tool to advance American offshore wind opportunities and achieve the goal of 30 GW by 2030, including by approving the nation’s first major offshore wind projects and leveraging historic resources from the President’s Investing in America agenda to support offshore wind infrastructure and supply chain buildout,” White House spokesperson Michael Kikuawa said in an email when asked about the 30 gigawatt target.

BloombergNEF recently marked down its own projection for offshore wind capacity by the end of decade to just over 23 gigawatts of offshore wind capacity by 2030.

In New York, New Jersey, Massachusetts, and Connecticut, out of 13 gigawatts of planned offshore wind, developers for 10 gigawatts of it are seeking to get their contracts amended.

“Never say never,” Allegra Dawes, an associate fellow at the Center for Strategic and International Studies, responded when I asked if these state targets — or the national target — were plausible. “I wouldn’t say they’re impossible. They’re highly unlikely at state level and federal level.”

In those four states, which Dawes said were the furthest along in their planning (the Vineyard Wind project in Massachusetts is actually under construction), the current wrangling over contracts could end up delaying everything.

“Even if that means those projects don’t get cancelled, there will be significant delays,” Dawes told me. “Those delays add up. We’re talking about a short amount of time until 2030 and that pushes back the entire timeline.”

Blue

You’re out of free articles.

Use code: LABORDAY to save 20%.
Subscribe to access Heatmap’s exclusive polling and expert analysis of energy, climate change, and sustainability, now just $99/year $79.20/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

How Building Transmission Could Lower Electricity Costs

Talking with National Grid’s Matthew Satterwhite about his new report with S&P Global.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Matthew Satterwhite, head of U.S. policy for National Grid. This week National Grid released a report in collaboration with S&P Global I found noteworthy amidst the data center backlash, asserting that building new transmission lines can potentially reduce consumer costs. I reached out asking if we could chat about how this argument leans into the fight over hyperscale infrastructure. I found our conversation illuminating and educational.

The following Q&A was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

The Solar Farm-to-Data Center Switcheroo Hits a Snag

Plus more of the week’s biggest development fights.

The United States.
Heatmap Illustration/Getty Images

1. Clark County, Nevada – The first data center approved on federal lands has hit a legal brick wall.

  • On Monday, the Townsite 2 solar farm-to-data center environmental review swap I’ve previously covered received a stay from the Interior Department’s board of appeals. David Gunter, a Biden appointee, ruled that the Center for Biological Diversity’s appeal of the permit flip was likely to succeed on the merits because a solar farm … is not a data center. Seems logical!
  • As I covered at the time, the Bureau of Land Management approved the environmental review swap claiming that a solar farm and a data center have essentially the same characteristics. It was a bold claim. Both the agency and Townsite said the characteristics would have substantially the same environmental impacts. Gunter shrugged off the claim idea, however, stating that statute requires projects to be both substantially similar and have equally similar impacts under the National Environmental Policy Act.
  • Crucially, Gunter also noted that the federal agency had never done an environmental review of any data centers under NEPA, so there’s not even a proper frame of reference. “BLM has not studied the Townsite data center project, or indeed any other data center project, in any environmental document,” he wrote.

2. Jackson County, Missouri – We have yet another high-profile case of a city councilor losing their job over voting for a data center, and this one’s a doozy.

Keep reading...Show less
Yellow
Spotlight

These 5 States Are Primed for a Data Center Pause

Where temporary moratoria could happen next.

A data center protest.
Heatmap Illustration/Getty Images

Brace yourself for more statewide data center moratoria.

So far there are only two full state-wide blocks on data center permits, in New York and Texas. At least fifteen states have moratorium legislation in the pipeline, but few if any of those bills stand a chance of becoming law in the short term. Here are five states, however, where a broad development pause may gain momentum in the next year or two — and all of them are crucial to watch this November.

Keep reading...Show less
Yellow