How Electricity Prices Fuel Data Center Opposition

Comparing data from the Electricity Price Hub with analysis from Heatmap Pro reveals a complicated story.

A data cabinet.
Heatmap Illustration/Getty Images

The timing was terrible. In December, just as the Canadian developer Hut 8 was preparing to ask regulators in a rural county of central Illinois to rezone an open stretch of land to make way for a data center, Americans’ support for the computing infrastructure expansion was plummeting, with voters blaming the big tech projects for driving up electricity costs.

The optics turned out to be even worse. The location Hut 8 selected was right next to the local electricity substation, making it easy to see the project as an industrial parasite glugging down electricity at the source and letting what remained trickle out to Logan County’s roughly 28,000 residents. When the county held a public hearing on the rezoning proposal in January, 250 residents showed up in protest and repeatedly cited the data center’s potential location next to the substation.

“It immediately raised red flags. You can picture this massive thing sitting next to the substation, sucking up all the power before it gets to the community,” Charlie Clynes, a data analyst for Heatmap Pro who has tracked the project, told me. “Obviously that’s not exactly how things work, but the imagery there was arresting.”

It also wasn’t entirely off base. Data center development can hike electricity bills in a variety ways, including by stressing existing generation resources and by demanding costly new infrastructure buildouts. Data from Heatmap and MIT’s Electricity Price Hub shows that the price of electricity in the county may, indeed, have played a role in hiking prices enough to spur a movement against the project: Between 2020 and 2026, generation costs roughly doubled.

Scenes like the one in Logan County are playing out across the country as the advent of artificial intelligence coincides with rising electricity prices and threatens to create a demand crisis.

But opposition to AI doesn’t always correlate with rising electricity prices.

Logan County earned a score of 69 on Heatmap Pro’s data center opposition index, which incorporates everything from real-world project outcomes to about 100 input variables, including economic, demographic, and geographic characteristics to quantify the likelihood that a project will face pushback in a given area. Nearly 70 might sound high, but it puts Logan County just outside the 100 counties most opposed to data center development.

In Botetourt County, Virginia, which topped the data center opposition index with a score of 101, residents are engaged in an active fight against a planned Google data center. Data from the Electricity Price Hub shows that the cost of generation surged 45% from 2020 to 2026, transmission spiked 29%, and distribution surged roughly 90%. The broad category of “other” — a category that includes miscellaneous expenses such as taxes, regulatory fees, insurance, and payroll (as Heatmap’s Jeva Lange explained here) — rocketed up by more than 104%. But here’s the rub: Botetourtians cite water usage as a top concern about data center development, not necessarily electricity prices.

In Bartow County, Georgia, which tied with Rogers County, Oklahoma, for second place on the index, generating costs rose by more than a third from 2020 to 2026, from $0.07 per kilowatt-hour to $0.09, leading to a total bill increase of nearly 30%. (You can find out more on the difference between electricity prices and bills from my colleague Emily Pontecorvo.) Rogers County, similarly, saw a roughly 50% spike in generation costs and an increase in transmission and distribution costs of more than a third each.

Hendricks County, Indiana, where residents unsuccessfully battled to stop a 600-megawatt AI data center from coming to fruition, came in ninth place on Heatmap Pro’s opposition index. Sure enough, the data shows a roughly 140% surge in distribution costs on ratepayers’ bills from 2020 and 2026, from $0.10 to $0.30 per kilowatt-hour.

In Cass County, Michigan, by contrast, distribution costs ticked up only slightly in recent years. Yet the county, which ranked seventh on the opposition index, is facing fierce opposition to a 340-megawatt AI data center proposed in the area, highlighting the inconsistent role electricity prices play in opposition movements.

Heatmap Pro also tracks opposition to renewables development, which is often the cheapest and fastest way to add power to the grid amid surging demand. The top of the list is a 63-way tie, mostly involving counties in the Central and Upper Midwest.

Then there’s Somerset County in Maine, which has been home to various utility-scale wind and solar developments in recent years. The cost of distributing power there has roughly doubled for customers of the three utilities serving the county, from $0.35 per kilowatt-hour at the start of 2020 to more than $0.63 by this January. Many Mainers blamed the state’s renewable energy goals for the spike in prices, but price hub data confirms the conclusions of a report from The Brattle Group released in February, which blamed the state’s reliance on natural gas, as well as the cost of repairs and upgrades to an aging grid.

Yellow

You’re out of free articles.

Subscribe to access Heatmap's exclusive climate and energy polling, award-winning journalism, and subscriber-only events. Save $57 on an annual subscription, just $156 $99/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Energy

Exclusive: Nuclear Recycling Startup Project Omega to File for License

The company is attempting to commercialize a novel processing method, with the help of a former NRC commissioner.

A Project Omega rendering and the NRC logo.
Heatmap Illustration/Project Omega, Getty Images

If you were born the year the United States gave up on finding a place to store its spent nuclear fuel, you’d almost be eligible to vote. Since 2009, when the Obama administration halted work on Yucca Mountain, the Nevada site designated under federal law as the nation’s first nuclear waste repository, the country has had no formal plan in place.

Russia, France, China, and Japan all reprocess highly radioactive spent fuel that comes out of reactors to extract usable materials and recycle them into more fuel. The process still leaves behind some nasty, dangerous radioisotopes that form during fission, but there remains a lot less that needs to be stored for centuries. The U.S. attempted to set up a commercial nuclear recycling industry in the 1970s, before President Jimmy Carter pulled the plug as a sop to the nonproliferation movement. No one has really attempted to invest in the industry since.

Keep reading...Show less
Green
AM Briefing

Huang’s Win

On Mary Barra’s heir, Quaise’s first customer, and the VPP surge

Nvidia headquarters.
Heatmap Illustration/Getty Images

Current conditions: Tropical Cyclone Xavier has strengthened into a Category 5 storm after battering the Cook Islands with winds of up to 184 miles per hour • In the Bay of Bengal, Cyclone Akvan is barreling toward India’s Andhra Pradesh just weeks after the state suffered another deadly cyclone • Today is the last day of any sunlight in Utqiaġvik, Alaska, which enters polar night until January 23.


THE TOP FIVE

1. Nvidia earnings doubled

On Tuesday afternoon, Jensen Huang, Nvidia’s disgraced founder who stepped down from his chief executive role last week amid a ballooning scandal over his extramarital affairs with multiple employees and a Chinese spy, began mounting his comeback. “Nvidia is a once-in-a-generation company,” he wrote in a post on X. “If the Board of Directors decides that my return is in the best interest of our shareholders, our employees, the company, and America, I would be honored to answer these calls and return as CEO.” A new website launched late last week, purportedly built by some of the investors and supporters who have been blowing up Huang’s phone with encouragement in recent days, calls on the board to “stand with Jensen.” When the market closed yesterday evening, Huang’s camp got yet more ammunition to bring to the battle: The company doubled its earnings in the third quarter of this year compared to the same time last year, it reported Tuesday. The chip designer reported revenue of $116 billion for the three months that ended in October, a year-over-year increase of 103%, besting Wall Street’s estimates of $109 billion. The earnings may help quell concerns over the soaring debt hyperscalers are incurring to build out data centers, which, as I wrote last month, investors worry may not pay for itself.

Keep reading...Show less
Blue
Politics

How Tribal Rights Became Central to the Permitting Debate

Proposed changes to the National Historic Preservation Act risk disturbing the fragile relationship between the U.S. and Native governments.

The plains.
Heatmap Illustration/Getty Images

In spite of some loud voices both for and against it, the Bipartisan American Affordability and Jobs Act has so far cruised through the Senate. That could change as soon as today as lawmakers begin to consider amendments ahead of a final vote.

One of the main outstanding issues is how the bill’s changes to the National Historic Preservation Act would affect tribal sovereignty. Nevada Senator Catherine Cortez Masto, a Democrat, warned before the initial motion to proceed on the proposed legislation last week that she would not vote for the final bill unless lawmakers struck that section entirely. Since then, nearly 30 Democrats have signed onto an amendment proposed by California Senator Adam Schiff that would do just that.

Keep reading...Show less