Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

Everyone Wants to Know PJM’s Data Center Plan

How will America’s largest grid deal with the influx of electricity demand? It has until the end of the year to figure things out.

Power lines and a data center.
Heatmap Illustration/Getty Images

As America’s largest electricity market was deliberating over how to reform the interconnection of data centers, its independent market monitor threw a regulatory grenade into the mix. Just before the Thanksgiving holiday, the monitor filed a complaint with federal regulators saying that PJM Interconnection, which spans from Washington, D.C. to Ohio, should simply stop connecting new large data centers that it doesn’t have the capacity to serve reliably.

The complaint is just the latest development in a months-long debate involving the electricity market, power producers, utilities, elected officials, environmental activists, and consumer advocates over how to connect the deluge data centers in PJM’s 13-state territory without further increasing consumer electricity prices.

The system has been pushed into crisis by skyrocketing capacity auction prices, in which generators get paid to ensure they’re available when demand spikes. Those capacity auction prices have been fueled by high-octane demand projections, with PJM’s summer peak forecasted to jump from 154 gigawatts to 210 gigawatts in a decade. The 2034-35 forecast jumped 17% in just a year.

Over the past two two capacity auctions, actual and forecast data center growth has been responsible for over $16.6 billion in new costs, according to PJM’s independent market monitor; by contrast, the previous year’s auction generated a mere $2.2 billion. This has translated directly to higher retail electricity prices, including 20% increases in some parts of PJM’s territory, like New Jersey. It has also generated concerns about reliability of the whole system.

PJM wants to reform how data centers interconnect before the next capacity auction in June, but its members committee was unable to come to an agreement on a recommendation to PJM’s board during a November meeting. There were a dozen proposals, including one from the monitor; like all the others, it failed to garner the necessary two-thirds majority vote to be adopted formally.

So the monitor took its ideas straight to the top.

The market monitor’s complaint to the Federal Energy Regulatory Commission tracks closely with its plan at the November meeting. “PJM is currently proposing to allow the interconnection of large new data center loads that it cannot serve reliably and that will require load curtailments (black outs) of the data centers or of other customers at times. That result is not consistent with the basic responsibility of PJM to maintain a reliable grid and is therefore not just and reasonable,” the filing said. “Interconnecting large new data center loads when adequate capacity is not available is not providing reliable service.”

A PJM spokesperson told me, “We are still reviewing the complaint and will reserve comment at this time.”

But can its board still get a plan to FERC and avoid another blowout capacity auction?

“PJM is going to make a filing in December, no matter what. They have to get these rules in place to get to that next capacity auction in June,” Jon Gordon, policy director at Advanced Energy United, told me. “That’s what this has been about from the get-go. Nothing is going to stop PJM from filling something.”

The PJM spokesperson confirmed to me that “the board intends to act on large load additions to the system and is expected to provide an indication of its next steps over the next few weeks.” But especially after the membership’s failure to make a unified recommendation, what that proposal will be remains unclear. That has been a source of agita for the organizations’ many stakeholders.

“The absence of an affirmative advisory recommendation from the Members Committee creates uncertainty as to what reforms PJM’s Board of Managers may submit to the Federal Energy Regulatory Commission (FERC), and when stakeholders can expect that submission,” analysts at ClearView Energy Partners wrote in a note to clients. In spite of PJM’s commitments, they warned that the process could “slip into January,” which would give FERC just enough time to process the submission before the next capacity auction.

One idea did attract a majority vote from PJM’s membership: Southern Maryland Electric Cooperative’s, which largely echoed the PJM board’s own plan with some amendments. That suggestion called for a “Price Responsive Demand” system, in which electricity customers would agree to reduce their usage when wholesale prices spike. The system would be voluntary, unlike an earlier PJM proposal, which foresaw forcing large customers to curtail their power. “The load elects to not take on a capacity obligation, therefore does not pay for capacity, and is required to reduce demand during stressed system conditions,” PJM explained in an update. The Southern Maryland plan tweaks the PRD system to adjust its pricing mechanism. but largely aligns with what PJM’s staff put forward.

“There’s almost no real difference between the PJM proposal and that Southern Maryland proposal,” Gordon told me.

That might please restive stakeholders, or at least be something PJM’s board could go forward with knowing that the balance of its voting membership agreed with something similar.

“We maintain our view that a final proposal could resemble the proposed solution package from PJM staff,” the ClearView note said. “We also think the Board could propose reforms to PJM’s PRD program. Indeed, as noted above, SMECO’s revisions to the service gained majority support.”

The PJM plan also included relatively uncontroversial reforms to load forecasting to cut down on duplicated requests and better share information, and an “expedited interconnection track” on which new, large-scale generation could be fast-tracked if it were signed off on by a state government “to expedite consideration of permitting and siting.”

Gordon said that the market monitor’s complaint could be read as the organization “desperately trying to get FERC to weigh in” on its side, even if PJM is more likely to go with something like its own staff-authored submission.

“The key aspect of the market monitor’s proposal was that PJM should not allow a data center to interconnect until there was enough generation to supply them,” Gordon explained. During the meeting preceding the vote, “PJM said they didn’t think they had the authority to deny someone interconnection.”

This dispute over whether the electricity system has an obligation to serve all customers has been the existential question making the debate about how to serve data centers extra angsty.

But PJM looks to be trying to sidestep that big question and nibble around the edges of reform.

“Everybody is really conflicted here,” Gordon told me. “They’re all about protecting consumers. They don’t want to see any more increases, obviously, and they want to keep the lights on. Of course, they also want data center developers in their states. It’s really hard to have all three.”

Green

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Climate Tech

Exclusive: Octopus Energy Launches Battery-Powered Electricity Plan With Lunar

The companies are offering Texas ratepayers a three-year fixed-price contract that comes with participation in a virtual power plant.

Octopus and Lunar Energy.
Heatmap Illustration/Getty Images

Customers get a whole lot of choice in Texas’ deregulated electricity market — which provider to go with, fixed-rate or variable-rate plan, and contract length are all variables to consider. If a customer wants a home battery as well, that’s yet another exercise in complexity, involving coordination with the utility, installers, and contractors.

On Wednesday, residential battery manufacturer and virtual power plant provider Lunar Energy and U.K.-based retail electricity provider Octopus Energy announced a partnership to simplify all this. They plan to offer Texas electricity ratepayers a single package: a three-year fixed-rate contract, a 30-kilowatt-hour battery, and automatic participation in a statewide network of distributed energy resources, better known as a virtual power plant, or VPP.

Keep reading...Show less
Blue
AM Briefing

Blowing the Whistle

On Trump’s renewables embargo, Project Vault, and perovskite solar

Pollution.
Heatmap Illustration/Getty Images

Current conditions: Illinois far outpaces every other state for tornadoes so far this year, clocking 80, with Mississippi in a distant second with 43 • Western North Carolina’s Blue Ridge Mountains face high wildfire risk during the day and frost at night • A magnitude 7.4 earthquake off the coast of Honshu, Japan, has raised the risk of a tsunami.

THE TOP FIVE

1. Whistleblowers allege big problems with corporate carbon standards-setter

The nonprofit that sets the standards against which tens of thousands of companies worldwide measure their greenhouse gas emissions is secretive and ideologically tilted toward industry. That’s the conclusion of a new whistleblower report on which Heatmap’s Emily Pontecorvo got her hands yesterday. The problems at the Greenhouse Gas Protocol “are systemic,” and the nonprofit “seems to be moving further away from its commitment to accountability,” the report said. Danny Cullenward, the economist and lawyer focused on scientific integrity in climate science at the University of Pennsylvania’s Kleinman Center for Energy Policy who authored the report, sits on the Protocol’s Independent Standards Board. Due to a restrictive non-disclosure agreement preventing him from talking about what he has witnessed, he instead relied on publicly available information to illustrate the report. “Not only does the nonprofit community not have a voice on the board,” Cullenward wrote, but the absence of those voices “risks politicizing the work of scientist Board members.” Emily added: “While the Protocol’s official decision-making hierarchy deems scientific integrity as its top priority, in practice, scientists are left to defend the science to the business community.” The report follows a years-long process meant to bolster the group’s scientific credibility. “Critics have long faulted the Protocol for allowing companies to look far better on paper than they do to the atmosphere,” Emily explains. But creating standards that are both scientifically robust and feasible to implement is no easy feat.

Keep reading...Show less
Red
Carbon Removal

Leading Climate Standards Group Fraught With Secrecy and Bias, Whistleblowers Say

A new report shared exclusively with Heatmap documents failures of transparency and governance at the Greenhouse Gas Protocol.

Pollution and trees.
Heatmap Illustration/Getty Images

It is something of a miracle that tens of thousands of companies around the world voluntarily report their greenhouse gas emissions each year. In 2025, more than 22,100 businesses, together worth more than half the global stock market, disclosed this data. Unfortunately, it’s an open secret that many of their calculations are far off the mark.

This is not exactly their fault. To aid in the tedious process of tallying up carbon and to encourage a basic level of uniformity in how it’s done, companies rely on standards created by a nonprofit called the Greenhouse Gas Protocol. The group’s central challenge is ensuring that its standards are both credible and feasible — two qualities often in tension in greenhouse gas accounting. The method that produces the most accurate emissions inventory may not always be feasible, while the method that’s easy to implement may produce wildly inaccurate results.

Keep reading...Show less
Yellow