Sign In or Create an Account.

By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy

Energy

Everyone Wants to Know PJM’s Data Center Plan

How will America’s largest grid deal with the influx of electricity demand? It has until the end of the year to figure things out.

Power lines and a data center.
Heatmap Illustration/Getty Images

As America’s largest electricity market was deliberating over how to reform the interconnection of data centers, its independent market monitor threw a regulatory grenade into the mix. Just before the Thanksgiving holiday, the monitor filed a complaint with federal regulators saying that PJM Interconnection, which spans from Washington, D.C. to Ohio, should simply stop connecting new large data centers that it doesn’t have the capacity to serve reliably.

The complaint is just the latest development in a months-long debate involving the electricity market, power producers, utilities, elected officials, environmental activists, and consumer advocates over how to connect the deluge data centers in PJM’s 13-state territory without further increasing consumer electricity prices.

The system has been pushed into crisis by skyrocketing capacity auction prices, in which generators get paid to ensure they’re available when demand spikes. Those capacity auction prices have been fueled by high-octane demand projections, with PJM’s summer peak forecasted to jump from 154 gigawatts to 210 gigawatts in a decade. The 2034-35 forecast jumped 17% in just a year.

Over the past two two capacity auctions, actual and forecast data center growth has been responsible for over $16.6 billion in new costs, according to PJM’s independent market monitor; by contrast, the previous year’s auction generated a mere $2.2 billion. This has translated directly to higher retail electricity prices, including 20% increases in some parts of PJM’s territory, like New Jersey. It has also generated concerns about reliability of the whole system.

PJM wants to reform how data centers interconnect before the next capacity auction in June, but its members committee was unable to come to an agreement on a recommendation to PJM’s board during a November meeting. There were a dozen proposals, including one from the monitor; like all the others, it failed to garner the necessary two-thirds majority vote to be adopted formally.

So the monitor took its ideas straight to the top.

The market monitor’s complaint to the Federal Energy Regulatory Commission tracks closely with its plan at the November meeting. “PJM is currently proposing to allow the interconnection of large new data center loads that it cannot serve reliably and that will require load curtailments (black outs) of the data centers or of other customers at times. That result is not consistent with the basic responsibility of PJM to maintain a reliable grid and is therefore not just and reasonable,” the filing said. “Interconnecting large new data center loads when adequate capacity is not available is not providing reliable service.”

A PJM spokesperson told me, “We are still reviewing the complaint and will reserve comment at this time.”

But can its board still get a plan to FERC and avoid another blowout capacity auction?

“PJM is going to make a filing in December, no matter what. They have to get these rules in place to get to that next capacity auction in June,” Jon Gordon, policy director at Advanced Energy United, told me. “That’s what this has been about from the get-go. Nothing is going to stop PJM from filling something.”

The PJM spokesperson confirmed to me that “the board intends to act on large load additions to the system and is expected to provide an indication of its next steps over the next few weeks.” But especially after the membership’s failure to make a unified recommendation, what that proposal will be remains unclear. That has been a source of agita for the organizations’ many stakeholders.

“The absence of an affirmative advisory recommendation from the Members Committee creates uncertainty as to what reforms PJM’s Board of Managers may submit to the Federal Energy Regulatory Commission (FERC), and when stakeholders can expect that submission,” analysts at ClearView Energy Partners wrote in a note to clients. In spite of PJM’s commitments, they warned that the process could “slip into January,” which would give FERC just enough time to process the submission before the next capacity auction.

One idea did attract a majority vote from PJM’s membership: Southern Maryland Electric Cooperative’s, which largely echoed the PJM board’s own plan with some amendments. That suggestion called for a “Price Responsive Demand” system, in which electricity customers would agree to reduce their usage when wholesale prices spike. The system would be voluntary, unlike an earlier PJM proposal, which foresaw forcing large customers to curtail their power. “The load elects to not take on a capacity obligation, therefore does not pay for capacity, and is required to reduce demand during stressed system conditions,” PJM explained in an update. The Southern Maryland plan tweaks the PRD system to adjust its pricing mechanism. but largely aligns with what PJM’s staff put forward.

“There’s almost no real difference between the PJM proposal and that Southern Maryland proposal,” Gordon told me.

That might please restive stakeholders, or at least be something PJM’s board could go forward with knowing that the balance of its voting membership agreed with something similar.

“We maintain our view that a final proposal could resemble the proposed solution package from PJM staff,” the ClearView note said. “We also think the Board could propose reforms to PJM’s PRD program. Indeed, as noted above, SMECO’s revisions to the service gained majority support.”

The PJM plan also included relatively uncontroversial reforms to load forecasting to cut down on duplicated requests and better share information, and an “expedited interconnection track” on which new, large-scale generation could be fast-tracked if it were signed off on by a state government “to expedite consideration of permitting and siting.”

Gordon said that the market monitor’s complaint could be read as the organization “desperately trying to get FERC to weigh in” on its side, even if PJM is more likely to go with something like its own staff-authored submission.

“The key aspect of the market monitor’s proposal was that PJM should not allow a data center to interconnect until there was enough generation to supply them,” Gordon explained. During the meeting preceding the vote, “PJM said they didn’t think they had the authority to deny someone interconnection.”

This dispute over whether the electricity system has an obligation to serve all customers has been the existential question making the debate about how to serve data centers extra angsty.

But PJM looks to be trying to sidestep that big question and nibble around the edges of reform.

“Everybody is really conflicted here,” Gordon told me. “They’re all about protecting consumers. They don’t want to see any more increases, obviously, and they want to keep the lights on. Of course, they also want data center developers in their states. It’s really hard to have all three.”

Green

You’re out of free articles.

Subscribe to access Heatmap’s expert analysis of climate change, clean energy, and sustainability. Save $57 on an annual subscription, just $156 $99/year.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Q&A

The Health Researcher Diving into Data Center Policy

A conversation with Emma Uridge of the Kansas Health Institute.

The Q&A subject.
Heatmap Illustration

This week’s conversation is with Emma Uridge, analyst with the Kansas Health Institute. Uridge spent copious hours analyzing state and local laws on data center development to best understand how policymakers are responding to the potential environmental public health impacts of large AI infrastructure, including power and water. The report, which came out this week, also goes in depth into those health impacts. I reached out to her to discuss what she sees as must-watch territory for our readers on this emerging policy arena.

Our conversation was lightly edited for clarity.

Keep reading...Show less
Yellow
Hotspots

Anti-Solar Protests Are the Cool New Campaign Move in Wisconsin

Plus more of the week’s big development fights.

The United States.
Heatmap Illustration/Getty Images

1. Laramie County, Wyoming — Meta is fighting the fine it received in the Cheyenne data center water pollution controversy, and the conflict between the tech giant and the city’s small board of public utilities is continuing to spill out into the public.

  • Meta this week appealed the $10,000 fine that the board of public utilities issued over a rare bacteria found in Cheyenne’s sewer system. Meta is contesting any responsibility for the contaminant, claiming the board should’ve fined the construction company Fortis instead. You can read the full appeal here.
  • Afterwards, the board publicly released hundreds of pages of emails revealing how and why government employees linked the bacteria to Meta, specifically, including that officials tied the bacteria’s presence to the usage of closed-loop cooling systems for data centers. The emails also show local officials knew the water pollution was linked to the data center months earlier than previously thought. All the emails are available here.
  • Meanwhile, Cheyenne residents are attempting a long-shot bid to undo the annexation for the Microsoft data center I told you about. It’s unlikely to succeed because petitioners need to get about 10% of the last election cycle’s voting population to sign within 20 days… which at more than 2,000 people sounds all but impossible without a massive grassroots campaign.

2. Niagara County, New York — This county just rejected a solar project’s highway work permits in a show of retaliation against the state’s Office of Renewable Energy Siting.

Keep reading...Show less
Yellow
Spotlight

How the Trump Administration Turned a Solar Farm Into a Data Center

The local government of Boulder City, Nevada had previously rejected a proposal for the computing facility, which would draw power from the existing electricity supply.

Donald Trump and Nevada.
Heatmap Illustration/Getty Images

The U.S. government for the first time approved a data center on federal lands. What the Trump administration is pitching as a demonstration of bureaucratic speed and ambition in the era of artificial intelligence, however, is turning into the same sort of mysterious backroom deal that’s upsetting other communities.

On Monday, the Bureau of Land Management announced that it would allow a large AI data center to be built on a plot of federal land technically within the limits of Boulder City, Nevada. The approval was initially granted as a right-of-way in 2023 for the second phase of a solar project known as Townsite Solar, to be built by a joint venture between Skylar Opportunities LLC, a subsidiary of Houston energy trader Bill Perkins’ investment firm, and renewables developer Arevon. (Ironically, Perkins also just launched an ETF to profit from higher electricity demand.)

Keep reading...Show less
Yellow