Trump Loses Another Case Against Offshore Wind

A federal judge in Massachusetts ruled that construction on Vineyard Wind could proceed.

Offshore wind.
Heatmap Illustration/Getty Images

The Vineyard Wind offshore wind project can continue construction while the company’s lawsuit challenging the Trump administration’s stop work order proceeds, judge Brian E. Murphy for the District of Massachusetts ruled on Tuesday.

That makes four offshore wind farms that have now won preliminary injunctions against Trump’s freeze on the industry. Dominion Energy’s Coastal Virginia offshore wind project, Orsted’s Revolution Wind off the coast of New England, and Equinor’s Empire Wind near Long Island, New York, have all been allowed to proceed with construction while their individual legal challenges to the stop work order play out.

The Department of the Interior attempted to pause all offshore wind construction in December, citing unspecified “national security risks identified by the Department of War.” The risks are apparently detailed in a classified report, and have been shared neither with the public nor with the offshore wind companies.

Vineyard Wind, a joint development between Avangrid Renewables and Copenhagen Infrastructure Partners, has been under construction since 2021, and is already 95% built. More than that, it’s sending power to Massachusetts customers, and will produce enough electricity to power up to 400,000 homes once it’s complete.

In court filings, the developer argued it was urgent the stop work order be lifted, as it would lose access to a key construction boat required to complete the project on March 31. The company is in the process of replacing defective blades on its last handful of turbines — a defect that was discovered after one of the blades broke in 2024, scattering shards of fiberglass into the ocean. Leaving those turbine towers standing without being able to install new blades created a safety hazard, the company said.

“If construction is not completed by that date, the partially completed wind turbines will be left in an unsafe condition and Vineyard Wind will incur a series of financial consequences that it likely could not survive,” the company wrote. The Trump administration submitted a reply denying there was any risk.

The only remaining wind farm still affected by the December pause on construction is Sunrise Wind, a 924-megawatt project being developed by Orsted and set to deliver power to New York State. A hearing for an injunction on that order is scheduled for February 2.

Blue

You’re out of free articles.

Subscribe today to experience Heatmap’s expert analysis 
of climate change, clean energy, and sustainability.
To continue reading
Create a free account or sign in to unlock more free articles.
or
Please enter an email address
By continuing, you agree to the Terms of Service and acknowledge our Privacy Policy
Sparks

Chris Wright Is Overhauling $83 Billion of Loans. He Won’t Say Which Ones.

The Secretary of Energy announced the cuts and revisions on Thursday, though it’s unclear how many are new.

The Energy Department logo holding money.
Heatmap Illustration/Getty Images

The Department of Energy announced on Thursday that it has eliminated nearly $30 billion in loans and conditional commitments for clean energy projects issued by the Biden administration. The agency is also in the process of “restructuring” or “revising” an additional $53 billion worth of loans projects, it said in a press release.

The agency did not include a list of affected projects and did not respond to an emailed request for clarification. However the announcement came in the context of a 2025 year-in-review, meaning these numbers likely include previously-announced cancellations, such as the $4.9 billion loan guarantee for the Grain Belt Express transmission line and the $3 billion partial loan guarantee to solar and storage developer Sunnova, which were terminated last year.

Keep reading...Show less
Green
Sparks

New Jersey’s New Governor Froze Electricity Prices During Her First Speech

Mikie Sherrill used her inaugural address to sign two executive orders on energy.

Mikie Sherrill.
Heatmap Illustration/Getty Images

Mikie Sherill, a former Navy helicopter pilot, was best known during her tenure in the House of Representatives as a prominent Democratic voice on national security issues. But by the time she ran for governor of New Jersey, utility bills were spiking up to 20% in the state, putting energy at the top of her campaign agenda. Sherrill’s oft-repeated promise to freeze electricity rates took what could have been a vulnerability and turned it into an electoral advantage.

“I hope, New Jersey, you'll remember me when you open up your electric bill and it hasn't gone up by 20%,” Sherrill said Tuesday in her inauguration address.

Keep reading...Show less
Blue
Sparks

Offshore Wind Developers Are Now 3 for 3 Against Trump

A third judge rejected a stop work order, allowing the Coastal Virginia offshore wind project to proceed.

Donald Trump and offshore wind.
Heatmap Illustration/Getty Images

Offshore wind developers are now three for three in legal battles against Trump’s stop work orders now that Dominion Energy has defeated the administration in federal court.

District Judge Jamar Walker issued a preliminary injunction Friday blocking the stop work order on Dominion’s Coastal Virginia offshore wind project after the energy company argued it was issued arbitrarily and without proper basis. Dominion received amicus briefs supporting its case from unlikely allies, including from representatives of PJM Interconnection and David Belote, a former top Pentagon official who oversaw a military clearinghouse for offshore wind approval. This comes after Trump’s Department of Justice lost similar cases challenging the stop work orders against Orsted’s Revolution Wind off the coast of New England and Equinor’s Empire Wind off New York’s shoreline.

Keep reading...Show less